Replacement of Gym Floor Due to Sloppy Paint Job is Not Resulting Loss
January 02, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted the insurer's motion for summary judgment finding damage to the gym floor due to a poor paint job was not a resulting loss. Bob Robinson Commercial Flooring, Inc. v. RLI Ins,. Co., 2023 U.S. Dist. LEXIS 196105 (D. Ark. Nov. 1, 2023).
Bob Robinson Commercial Flooring (BRCF) submitted a bid to the general contractor, Nabholz Construction Corporation, to install a vinyl athletic floor and striping at a middle school. The job also included the painting of a "Wildcat" logo the main gym floor. Therefore, BRCF's job was to install floors with proper painting and striping. Robert Liles and Robert Lines Parking Lot Services was the subcontractor hired to do the painting and striping. BRCF did not supervise or inspect Liles' work while it was ongoing.
Nabholz informed BRCF that there were problems with the floor painting, including crooked lines, incorrect markings, misplacement of the three point lines for the basketball surface, drips, smudges, etc. The gym floor was eventually rejected due to the nature of the vinyl flooring, once primer and paint were applied, the paint could not be removed and repainted. BRCF had to hire a new subcontractor to remove the flooring, install new flooring and then paint new lines. The cost for removal and replacement was $134,188.95.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Action Needed: HB24-1230 Spells Trouble for Colorado Construction Industry and its Insurers
March 25, 2024 —
David McLain - Higgins, Hopkins, McLain & Roswell, LLCIn an apparent gift to plaintiffs’ construction defect lawyers, Representatives Parenti and Bacon introduced House Bill 24-1230 on February 12, 2024. The bill was assigned to the House Judiciary Committee and is scheduled for hearing on March 6th, during the afternoon session beginning at 1:30 pm. To date, the bill does not have any senate sponsors, perhaps because the senators are more interested in serving their constituents’ needs for attainable housing than in lining the pockets of their plaintiffs’ construction defect attorney friends.
According to the bill’s summary, HB 24-1230 contains the following provisions:
Current law declares void any express waivers of or limitations on the legal rights or remedies provided by the “Construction Defect Action Reform Act” or the “Colorado Consumer Protection Act.” Sections 1 and 4 make it a violation of the “Colorado Consumer Protection Act” to obtain or attempt to obtain a waiver or limitation that violates the aforementioned current law.
Read the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
Project Completion Determines Mechanics Lien Recording Deadline
April 08, 2024 —
William L. Porter - Porter Law GroupThe California mechanics lien is one of the most powerful collection remedies available to contractors, subcontractors and suppliers who are unpaid for work performed and materials supplied in relation to a California private works construction project. The mechanics lien allows the claimant to actually sell the property where the work was carried out in order to obtain payment, entirely of course, against the wishes of the property owner. There are a number of important steps to follow and timelines to be met in order to pursue this remedy.
First, Understand Your Preliminary Notice Deadline
Working within deadlines is absolutely crucial to preserving mechanics lien rights under California law. The deadlines differ, depending on whether you are a “direct” contractor, also known as “original” or “prime” contractor (one who contracts directly with the property owner) or a subcontractor or material supplier. The process begins with the serving of a “preliminary notice” no later than 20 days after the party serving the preliminary notice begins supplying labor or materials to the project. Direct contractors are only required to serve the preliminary notice on the construction lender (Civil Code section 8200-8216), whereas subcontractors and material suppliers must serve not only the construction lender, but also the owner and direct contractor (see Civil Code section 8200(e)).
Read the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Don’t Fall in Trap of Buying the Cheapest Insurance Policy as it May be Bad for Your Business Risks and Needs
March 25, 2024 —
David Adelstein - Florida Construction Legal UpdatesDon’t fall in the trap of buying the cheapest insurance policy. It will come and bite you in the butt big time! Consult with an insurance broker that understands construction and, importantly, your specific industry, to provide you coverage within your industry. Otherwise, you’ll be paying for a policy that may (i) not be a good policy, and (ii) may provide you minimal to no value for your industry’s RISKS and NEEDS when factoring in exclusions. When procuring insurance, think of the old adage “penny wise and pound foolish,” and don’t make decisions that fit within this adage!
The recent decision in Nautilus Ins. Co. v. Pinnacle Engineering & Development, Inc., 2024 WL 940527 (S.D. Fla. 2024) serves as an example. Here, a subcontractor was hired by a general contractor to perform underground utility work for a townhome development which consisted of 57 townhome units included in 18 detached structures. The subcontractor’s underground work was defective which caused damage to the property’s water line, sewer system, plumbing lines, pavers, etc. The general contractor was liable to the owner for this defective work. Although the general contractor was an additional insured under the subcontractor’s commercial general liability (CGL) policy, the subcontractor’s CGL carrier denied the duty to defend and initiated an insurance coverage lawsuit. Motions for summary judgment were filed.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Final Rule Regarding Project Labor Agreement Requirements for Large-Scale Federal Construction Projects
January 29, 2024 —
Aaron C. Schlesinger & Julia Loudenburg - Peckar & Abramson, P.C.Beginning on January 22, 2024, in compliance with President Biden’s February 4, 2022 Executive Order, 14603, federal construction projects with a total estimated cost of $35 million are required to utilize a project labor agreement (“PLA”) unless the contracting agency grants an exception. The Federal Register estimates that this rule will impact approximately 119 IDIQ contracts each year; these contracts have an average award value of about $114 million.
The White House claims the PLAs will improve projects by:
- Eliminating project delays from labor unrest, such as strikes;
- Creating dispute resolution procedures and cooperation for labor-management disputes, such as those over safety;
- Including provisions “to support workers from underserved communities and small businesses”;
- Helping to create a steady pipeline of workers for federal projects; and
- Promoting competition on government contracts so that all builders, even those who are non-union, can bid on jobs that require a PLA.
Read the full story...Reprinted courtesy of
Aaron C. Schlesinger, Peckar & Abramson, P.C.Mr. Schlesinger may be contacted at
aschlesinger@pecklaw.com
The Increasing Trend of Caps in Construction Contracts and Negotiating Them
November 27, 2023 —
Jarred Trauth - ConsensusDocsRisks are inherent in every construction project and all parties involved face them: owners, designers, general contractors/builders, subcontractors, suppliers…. Equitably allocating such risks is one of the most important and most negotiated areas of any construction related contract. Limitations of liability provisions are key to risk allocation. These provisions include no damage for delay provisions and caps on delay damages, warranty limitations and exclusions, indemnity limitations, and consequential damage waivers. Another, and the focus of this article, is a liability cap fixing the total amount of damages for which a party may be liable under the contract (the “Liability Cap”). Liability Caps have become more and more common in construction and construction related contracts, including major component supply agreements and design agreements.
This article will discuss Liability Caps generally and considerations of an owner or contractor negotiating them, including carve-outs (i.e. exceptions) to them.
Read the full story...Reprinted courtesy of
Jarred Trauth, Jones Walker LLPMr. Trauth may be contacted at
jtrauth@joneswalker.com
Michael Baker Intl. Settles Federal Pay Bias Allegations
February 26, 2024 —
James Leggate - Engineering News-RecordMichael Baker International Inc. agreed to pay $122,299 in back wages as part of an agreement with the U.S. Dept. of Labor to resolve allegations that the engineer-consultant paid women in four job titles less than their male counterparts.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story...
Construction Industry Groups Challenge DOL’s New DBRA Regulations
December 16, 2023 —
Bret Marfut - The Construction SeytLess than a month after taking effect, the Department of Labor’s (“DOL”) broad changes to the regulations implementing Davis-Bacon and Related Acts (“DBRA”) are facing legal challenges in two federal courts. These newly-filed lawsuits could change things for those trying to navigate the new regulatory landscape. Contractors on DBRA-covered contracts should keep an eye out for developments.
On October 23, 2023, DOL’s final rule updating the regulations implementing DBRA became effective. The first major overhaul of its kind in forty years, the final rule made sweeping changes to the regulations governing payment of prevailing wages on most federally-funded construction contracts.