A Termination for Convenience Is Not a Termination for Default
April 22, 2024 —
David Adelstein - Florida Construction Legal UpdatesA termination for convenience is NOT a termination for default. They are NOT the same. They should NOT be treated as the same. I am a huge proponent of termination for convenience provisions because sometimes a party needs to be able to exercise a termination for convenience, but the termination is not one that rises to a basis for default. However, exercising a termination for convenience does not mean you get to go back in time and convert the termination for convenience into a termination for default. It does not work like that. Nor should it.
An opinion out of the Civilian Board of Contract Appeals – Williams Building Company, Inc. v. Department of State, CBCA 7147, 2024 WL 1099788 (CBCA 2024 – demonstrates a fundamental distinction between a termination for convenience and a termination for default, i.e., that you don’t get to conjure up defaults when you exercise a termination for convenience:
Because a termination for convenience essentially turns a fixed-price construction contract into a cost-reimbursement contract, allowing the contractor to recover its incurred performance costs, the resolution of this appeal will involve identifying the total costs that [Contractor] incurred in performing this contract before [Government] terminated it for convenience. Since [Government] terminated the contract for convenience rather than for default, it no longer matters whether, in the past,[Contractor] acted intentionally in overstating the amount of its incurred costs or committed a contract breach. Ultimately, as permitted in response to a termination for convenience, [Contractor] will recover those allowable costs that [Contractor]establishes it incurred in performing the contract.
Williams Building Company, supra.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Round and Round: Inside the Las Vegas Sphere
December 16, 2023 —
Grace Calengor - Construction ExecutiveHow does the typical contractor approach building something taller than the Statue of Liberty, wider than a football field and with the most square footage of LED lighting in the world? Perhaps it’s enough to say that Sphere Entertainment Company is not your average contractor—and Sphere in Las Vegas is not your average construction project.
With a budget of approximately $2.3 billion, Sphere is a massive entertainment venue constructed mainly of steel and concrete. How different is that from the typical Vegas high-rise, casino or hotel? When you account for the structure’s sheer size, uncommon shape and intertwining technologies—very.
Reprinted courtesy of
Grace Calengor, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
There’s the 5 Second Rule, But Have You Heard of the 5 Year Rule?
April 23, 2024 —
Garret Murai - California Construction Law BlogThey’re called deadlines for a reason. Usually, because something really bad could happen if you fail to meet the deadline.
For those in the construction industry, you probably aware of the “deadline” to bring a claim for latent defects (10 years from substantial completion); the deadline to file suit to foreclose on a mechanics lien (90 days from the date of recording the mechanics lien), and the deadline for serving a preliminary notice (generally, 20 days from the date labor and/or materials are first furnished).
Well, here’s another deadline: Under Code of Civil Procedure section 585.310, you have 5 years after a complaint is filed to bring a case to trial, absent the court granting relief. I could leave it at that, but in the next case, Oswald v. Landmark Builders, Inc., 97 Cal.App.5th 240 (2023), was too interesting to pass up.
The Oswald Case
On June 28, 2016, homeowners Jack Oswald and Anne Seley sued their general contractor and its subcontractors alleging construction defects at their home. Answers and cross-complaints were filed and on February 2017 the trial court determined the case to be complex and appointed a discovery master. A discovery master, for those who may be unfamiliar, is usually a retired judge or third-party lawyer appointed by a court to oversee discovery in a case such as written discovery, depositions, site inspections, etc.
Read the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Just How Climate-Friendly Are Timber Buildings? It’s Complicated
February 12, 2024 —
Eric Roston - BloombergThis article is part of the Bloomberg Green series Timber Town, which looks at the global rise of timber as a low-carbon building material.
The number of people living in urban areas around the world
will swell by upwards of 2 billion over the next three decades. Many of those people will need new homes. But building those with conventional materials would unleash a gusher of carbon dioxide: Concrete, steel, glass and bricks for construction make up a combined
9% of global CO2 emissions, according to research by the United Nations Environment Program.
Enter engineered wood, a seemingly no-brainer solution.
Mass timber is not the typical lumber that has structured single-family houses in North America for decades. The wood components are strong enough to hold up an office tower or apartment block, and building with them is thought to emit much less CO2 than using standard materials. And since wood is about 50% carbon, the material itself even stores a little carbon, to boot.
Read the full story...Reprinted courtesy of
Eric Roston, Bloomberg
Allegations Versus “True Facts”: Which Govern the Duty to Defend? Bonus! A Georgia Court Clears Up What the Meaning of “Is” Is
December 11, 2023 —
Rachel E. Hudgins & Syed S. Ahmad - Hunton Insurance Recovery BlogCourts scrutinize a complaint’s factual allegations to decide whether the allegations trigger a duty to defend.
[1] If the facts unambiguously exclude coverage, there is no duty to defend.
[2] But what if the factual allegations fall within a policy exclusion, but the allegations are untrue or questionable? What if the true facts would mean the exclusion doesn’t apply? In that case, many courts have found that the insurer should base its decision on the policyholder’s version of the “true facts.”
[3] An insurer can’t rely on the complaint’s allegations to deny coverage when the facts that the insurer knows or can ascertain show that the claim is covered.
[4]
A recent case,
United Minerals & Properties Inc. v. Phoenix Insurance Co., No. 4:23-cv-00050 (N.D. Ga.), illustrates these policy interpretation principles.
Reprinted courtesy of
Rachel E. Hudgins, Hunton Andrews Kurth and
Syed S. Ahmad, Hunton Andrews Kurth
Ms. Hudgins may be contacted at rhudgins@HuntonAK.com
Mr. Ahmad may be contacted at sahmad@HuntonAK.com
Read the full story...
No Damages for Delay May Not Be Enforceable in Virginia
January 08, 2024 —
Christopher G. Hill - Construction Law MusingsAnyone who reads Construction Law Musings with any regularity (thank you by the way) knows that the contract is king in most instances here in Virginia. Any commercial construction subcontractor in Virginia is likely also very familiar with so-called “no damages for delay” clauses in construction contracts. These clauses essentially state that a subcontractor’s only remedy for a delay caused by any factor beyond its control (including the fault of the general contractor), after proper notice to the general contractor, is an extension of time to complete the work. However, in 2015 the Virginia General Assembly passed a change in the law that precluded the diminishment of any right to claims for demonstrated additional costs prior to payment. This left open the question as to which types of “diminishment” would be barred by the statute.
The recent case out of the Eastern District of Virginia federal court, Strata Solar LLC v. Fall Line Construction LLC, added a bit of clarity.
Read the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Real Estate & Construction News Roundup (10/11/23) – Millennials Struggle Finding Homes, Additional CHIPS Act Funding Available, and the Supreme Court Takes up Hotel Lawsuit Case
November 16, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, EV charging stations become more prevalent at commercial locations, home ownership becomes more difficult for younger Americans, Macy’s announces plans to build additional stores within strip malls, and more!
- Due to several factors including overpriced housing and student debt, millennials will not have the same level of home ownership as previous generations. (Jordan Rosenfeld, Yahoo)
- With the U.S. being short about 3.8 million housing units according Freddie Mac, 3-D printing may prove to be the answer while also being cost effective and environmentally friendly. (Lesley Stahl, Aliza Chasan, Shari Finkelstein and Collette Richards, CBS)
- The Department Commerce of announced a new initiative to funnel $500 million in CHIPS Act funding to projects with capital investments below $300 million that support the construction, expansion or modernization of semiconductor-related facilities in the U.S. (Sebastian Obando, Construction Dive)
Read the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team, Pillsbury
Insurer's Motion for Judgment on the Pleadings for Construction Defect Claim Rejected
January 22, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe magistrate judge recommended that the insurer's motion for judgment on the pleadings be denied in a case involving coverage for the insured subcontractor's alleged faulty workmanship. Evanston Ins. Co. v. Sonny Glasbrenner, Inc., 2023 U.S. Dist. LEXIS 190019 (M.D. Fla. Oct. 20, 2023).
Cone & Graham (C&G), the general contractor, subcontracted with Sonny Glasbrenner, Inc. (SGI) to work on the project. The project involved the rehabilitation of a bridge due to deterioration of the existing concrete bridge deck by adding additional cross bracing to further stiffen the steel girders and using special lightweight concrete. C&G contracted SGH to demolish the existing concrete bridge deck. SGI completed the work.
Thereafter, C&G made a demand to SGI for alleged damaged caused by SGI's work. C&G alleged that SGI was negligent in performing the demolition work, causing substantial damage to the existing bridge girders. C&G sued SGI.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com