Court Finds Matching of Damaged Materials is Required by Policy
April 02, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted, in part, the insured's motion for summary judgment by finding that matching roof tiles were required under the policy. Bertisen v. Travelers Home and Marine Ins. Co., 2024 U.S. Dist. LEXIS 3907 (D. Colo. Jan. 8, 2024).
The insureds sued Travelers for breach of contract, common law bad faith, and unreasonable delay or denial of benefits. They alleged that their residence was damaged by a hailstorm and that Travelers breached their policy and acted in bad faith in the handling of the claim. The insureds demanded an appraisal to determine the "amount of loss" under the policy and an appraisal award was issued. Travelers then denied payment for all roof tiles that were contemplated by the appraisal award.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Word “Estimate” in a Contract Matters as to a Completion Date
February 12, 2024 —
David Adelstein - Florida Construction Legal UpdatesLanguage in a contract matters. The word “estimates” or “estimated” matters particularly when it comes to a date certain such as a substantial completion or completion date. Remember this.
Here is an example.
In Parque Towers Developers, LLC v. Pilac Management, Ltd., 49 Fla.L.Weekly D190a (Fla. 3d DCA 2024), a trial court held that the developer did not complete the construction of five condominium units by the date in the purchase agreements. The developer appealed because “[t]he agreements contain no date certain for the completion of the units, but rather include a clause that ‘Seller estimates it will substantially complete construction of the Unit, in the manner specified in this Agreement, by December 31, 2017, subject to extensions resulting from ‘Force Majeure (the ‘Outside Date’).’” Parque Towers, supra. Another provision in the purchase agreements stated, “[w]henver this Agreement requires Seller to complete or substantially complete any item of construction, that item will be understood to be complete or substantially complete when so completed or substantially completed in Seller’s opinion. Id.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Traub Lieberman Partner Lisa M. Rolle Wins Summary Judgment in Favor of Third-Party Defendant
May 06, 2024 —
Traub LiebermanTraub Lieberman Partner Lisa M. Rolle won summary judgment in favor of Third-Party Defendant, a general contracting company (the “Contracting Company”), in a personal injury action brought in Suffolk County. In the underlying matter, the Plaintiff—an employee of the Contracting Company—alleged that they sustained injuries from an incident which occurred when they were struck by a skid-steer loader owned by the Co-Defendant masonry company (the “Masonry Company”) and operated by the president and owner of the Co-Defendant/Third-Party Plaintiff construction company (the “Construction Company”). The Plaintiff brought claims against the Defendant companies for common law negligence and violations of Labor Law § § 200, 240, and 241, as well as Industrial code (12 NYCRR) subpart 23-2.
Reprinted courtesy of
Lisa Rolle, Traub Lieberman
Ms. Rolle may be contacted at lrolle@tlsslaw.com
Read the full story...
Co-Founding Partner Jason Feld Named Finalist for CLM’s Outside Defense Counsel Professional of the Year
March 19, 2024 —
Linda Carter - Kahana FeldKahana Feld congratulates Co-Founding Partner Jason Daniel Feld, Esq., for being named one of three finalists for Claims & Litigation Management Alliance (CLM) Outside Defense Counsel Professional of the Year.
Mr. Feld is a nationwide leader in construction claims and an active industry speaker, serving as panel counsel for many prominent insurance carriers, and personal counsel to multiple national and regional homebuilders, developers, and general contractors.
Co-Founding Partner, Amir Kahana, states, “Jason is incredibly deserving of this recognition. When he joined our firm, we were 3 lawyers in one city, and seven years later, we are a national firm with over 65 attorneys in 10 cities and 6 states. Jason is a natural leader who is highly respected. He has earned the trust of his carrier clients, as well as his colleagues in the industry. In addition to everything he does for Kahana Feld, he also works tirelessly on behalf of CLM and has been a great leader in the Orange County Chapter. I am thrilled to see Jason receive the recognition he richly deserves.”
Read the full story...Reprinted courtesy of
Linda Carter, Kahana FeldMs. Carter may be contacted at
lcarter@kahanafeld.com
Veolia Agrees to $25M Settlement in Flint Water Crisis Case
February 19, 2024 —
James Leggate - Engineering News-RecordEngineering firm Veolia North America agreed to a $25-million settlement to resolve a federal class action case related to its work for the city of Flint, Mich., during the city’s lead-in-water crisis, the company and attorneys for the plaintiffs announced Feb. 1. Veolia is the second engineering firm that worked for the city to settle with city residents, and the deal came ahead of a class-action trial scheduled to start later this month.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story...
Wyncrest Commons: Commonly Used Progress Payments in Construction Contracts Do Not Render Them Installment Contracts
December 11, 2023 —
Benjamin J. Hochberg - Peckar & Abramson, P.C.In BIL-JIM Construction Company, Inc. v. Wyncrest Commons, LP, 2023 WL 7276637 (Unpublished, decided November 3, 2023), the New Jersey Appellate Division was asked to consider two issues regarding the interpretation and application of a construction contract that utilized the standard form American Institute of Architects owner/contractor agreement (AIA Document A101-2007) (the “AIA Contract”). Specifically, it was asked to consider: 1) whether a modified AIA Contract was an “installment contract,” whereby each progress payment was subject to its own statute of limitations; and 2) whether and when work had been approved in the context of New Jersey’s Municipal Land Use Law. While the decision is presently unpublished, it provides guidance as to how form contracts utilizing the same or similar terms will be treated by New Jersey’s courts and is a reminder that the potential for future claims must be considered during contract negotiations.
Discussion
The primary issue in Wyncrest was whether an AIA Contract was an “installment contract,” and the remaining issues turned on the resolution of this question. Wyncrest, the owner for the project at issue, did not dispute that its contractor, BIL-JIM Construction Company, Inc., had not been fully paid for work that it had performed in connection with a construction project located in Ocean County, New Jersey. Instead, Wyncrest argued that because its AIA Contract with BIL-JIM required that invoices be presented and paid monthly, it constituted an “installment contract.” As such, older payments would be treated as individual transactions and were time barred by the applicable statute of limitations. The trial court agreed with Wyncrest’s characterization of the AIA Contract as an “installment contract,” and found that BIL-JIM’s invoices were each subject to their own statute of limitations. However, the trial court disagreed with Wyncrest’s argument that BIL-JIM’s claim for retainage—which was submitted at the end of its work at the project—was time barred.
Read the full story...Reprinted courtesy of
Benjamin J. Hochberg, Peckar & Abramson, P.C.Mr. Hochberg may be contacted at
bhochberg@pecklaw.com
Contract Void Ab Initio: Key Insights into the KBR vs. Corps of Engineers Affirmative Defense
February 12, 2024 —
Matthew DeVries - Best Practices Construction LawIn a recent Board decision dated December 13, 2023, the United States Army Corps of Engineers sought to amend its answer in the case of APPEALS OF – KELLOGG BROWN & ROOT SERVICES, INC., under Contract No. W912GB-13-C-0011. The proposed amendment introduces an affirmative defense, contending that Kellogg Brown & Root Services, Inc. (KBR) made material misrepresentations in its proposal, rendering the fully-performed contract void ab initio.
Background: The contract in question, executed on July 9, 2013, was for the construction of an Aegis Ashore Missile Defense System site in Deveselu, Romania, with a firm, fixed-price amount of $134,211,592. The Corps moved to amend its answer to allege that KBR’s material misrepresentations induced the Corps to enter the contract, justifying the voiding of the contract. The alleged misrepresentations include issues related to subcontractor quotes, firm fixed prices, subcontracting plans, and more.
Motion to Amend and Legal Defense: The Corps, despite delays in formally amending its answer, argued that KBR was aware of the potential affirmative defense before the conclusion of fact discovery. The proposed affirmative defense asserts that KBR made eight material misrepresentations in its proposal, upon which the Corps relied in awarding the contract and defending against a GAO protest.
Read the full story...Reprinted courtesy of
Matthew DeVries, Burr & Forman LLPMr. DeVries may be contacted at
mdevries@burr.com
Resolving Subcontractor Disputes with Pass-Through Claims and Liquidation Agreements
May 13, 2024 —
Stephanie Cooksey - Peckar & Abramson, P.C.Imagine a project where you are unable to reach final completion due to an unresolved subcontractor claim. If the project owner is responsible for the claim, and both the owner and subcontractor are entrenched in their positions, how would you resolve this dispute?
The default option is a three-party lawsuit where the subcontractor sues you in your capacity as general contractor. By denying the claim, you bring the owner into the lawsuit as a liable party to the subcontractor’s claim. This option is efficient from the judicial system’s perspective, as it means one lawsuit instead of two. The subcontractor cannot sue the owner since the two have no contract between them. Thus, the subcontractor’s recourse is limited to suing the contractor. In the three-party lawsuit, you argue that if the subcontractor prevails in its claim against you, the owner is liable. If the owner successfully defends against the claim, the subcontractor takes nothing.
Putting judicial economy aside, it may not make economic sense for contractors to have a lawyer involved in litigating a case where they have no skin in the game. Fortunately, there is a better option than the three-party lawsuit on multi-party construction projects.
Read the full story...Reprinted courtesy of
Stephanie Cooksey, Peckar & Abramson, P.C.Ms. Cooksey may be contacted at
scooksey@pecklaw.com