It’s More Than a Feeling: Proving Construction Damages and When You Should Hire an Expert to Help Do It
July 27, 2026 —
Bradley E. Sands & Katie McCracken - ConsensusDocsWhen you win a bid, you might be singing that everything is going your way. Then something goes wrong. The owner hands you defective plans, sits on RFI responses or other critical information, or otherwise upends the work. The costs pile up through no fault of your own. You feel wronged, and you want to be made whole. But a feeling that you got burned is not enough. To recover, that feeling has to become something the law recognizes as damages. So, what are damages, and how do you prove them?
At bottom, contract damages are the money that puts the non-breaching party (i.e., the party that doesn’t breach the contract) in the position it would have occupied had the contract been performed.
Reprinted courtesy of
Bradley E. Sands, Jones Walker LLP and Katie McCracken, Summer Associate, University of Georgia School of Law
Read the full story...Mr. Sands may be contacted at
bsands@joneswalker.com
Generic Complaint Alleging Bad Faith is Insufficient
August 24, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court granted the insurer’s motion for judgment on the pleadings after determining that the insured’s claims for bad faith and unfair claims settlement practices were insufficiently pled. Navia v. State Farm Fire & Cas. Co., 2026 U.S. Dist. LEXIS 111261 (W.D. N. C. May 20, 2026).
The insured submitted a claim for damages to real property owned by the insured allegedly caused by Hurricane Helene. State Farm advised the insured that only some of the claimed damages were covered by the policy and payment for such damages were denied because the estimate for the covered damages did not exceed the policy’s deductible. The insured sued asserting claims for breach of contract, bad faith, and unfair claim settlement practices.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Can Anything Supersede Excel in AEC?
April 27, 2026 —
Aarni Heiskanen - AEC BusinessIf there’s one piece of software that dominates the business world across industries, it’s Microsoft Excel. Can AI finally dethrone the mighty spreadsheet?
Memorable Spreadsheet Moments
Everyone has memorable spreadsheet moments. I have a few. For example, my then-architecture firm was involved in more than a dozen housing developments abroad. I developed an Excel workbook that took the required number of households as input and automatically generated a breakdown of buildings and their apartment types for AutoCAD. This was urban planning and architectural design done with a spreadsheet.
I also developed business software using Excel for project portfolio management. The prototype was later scaled into a commercial SaaS that is now used globally.
Another memorable moment was when a property owner told me their Excel file grew so large that it ran out of rows and columns. That must have been before 2007, when the maximum number of columns on a sheet was still just 256 and the maximum number of rows was 65,536. The current limits are 1,048,576 rows and 16,384 columns, which I hope no one will exceed.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Bona Fide Dispute Defeats Violation of Prompt Payment Act
June 15, 2026 —
David Adelstein - Florida Construction Legal UpdatesMost, if not all, jurisdictions, including the federal government, have what is known as a “Prompt Payment Act.” The objective is to ensure prompt payment. If prompt payment is not made, the Prompt Payment Act provides for interest penalties, as well as potentially other costs such as attorney’s fees.
But the thing is, it’s not as simple as untimely payment to support the recourse and interest penalties the applicable Prompt Payment Act affords. And the teeth associated with the applicable Prompt Payment Act are not as sharp as perhaps the party claiming untimely payment prefers.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Substantial Evidence of Flood Loss is Not a Substitute for Required Proof of Loss
April 20, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe court found that the insurer properly denied the insured’s claim for loss due to flood because a proof of loss was never submitted. Bay Haven at Coco Bay Condominium Association, Inc. v. Hartford Ins. Co. of the Midwest, 2026 U.S. Dist. LEXIS 6847 (M.D. Fla. Jan. 14, 2026).
Bay Haven managed several condo buildings. When Hurricane Ian hit, it caused significant flood damage to these properties. Bay Haven held federal flood insurance policies through Hartford under “Write-Your-Own” policies. This meant Hartford was essentially a fiscal agent that managed policies and handled claims but paid them using federal funds.
Following the storm, FEMA extended the usual 60-day deadline for filing a proof of loss to one year, or until September 28, 2023. Bay Haven did not submit its proofs of loss until November 2023. FEMA granted an extension but only for the specific amounts in the November requests. Hartford did not waive the 60-day proof of loss requirement for any other proof of loss. Hartford paid the amounts reflected in the November submissions.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
4th Department Narrowly Interprets Professional Services
August 11, 2026 —
Craig Rokuson - Traub LiebermanIn the recent case of Cty. of Erie v. Selective Ins. Co. of Am., 2026 NY Slip Op 04092 (App. Div. 4th Dept.), New York’s Appellate Division, Fourth Department held that a general liability carrier for a construction manager owed additional insured coverage to the County of Erie, notwithstanding an exclusion in the construction manager’s policy for injuries arising out of professional services.
The underlying case involved injuries sustained when the underlying plaintiff fell off of her bicycle at a park owned by the County when she transitioned from the pavement edge to grass.
Read the full story...Reprinted courtesy of
Craig Rokuson, Traub LiebermanMr. Rokuson may be contacted at
crokuson@tlsslaw.com
Voluntary Dismissal of an Indemnity Claim Does Not Make the Subcontractor a “Prevailing Party,” Washington Court of Appeals Holds
September 21, 2026 —
Margarita Kutsin - Ahlers Cressman & Sleight PLLCIn
King County v. Walsh Construction Company II, LLC, No. 86503-0-I (Wash. Ct. App. Aug. 4, 2025), an unpublished decision from Division I of the Washington Court of Appeals, the Court affirmed the denial of a subcontractor’s request for prevailing-party attorney fees under an indemnity clause after the general contractor voluntarily dismissed its indemnity claims. Because the indemnity claim was no longer live and no determination of fault had occurred, the Court held that the trial court did not err in denying the request. ACS represented Walsh, the general contractor, in securing the denial of the fee request at the trial court that the Court of Appeals affirmed.
A Pass-Through Indemnity Claim That Ended Before Fault Was Decided
The dispute arose out of a public works contract under which King County hired Walsh Construction Company II, LLC (“Walsh”) to construct and install a conveyance pipeline. After the pipeline broke, King County sued Walsh for breach of contract and warranty, expressly identifying both Walsh and its subcontractor, Mears Group Inc., (“Mears”) as responsible. Walsh tendered defense and indemnity to Mears under the subcontract.
Read the full story...Reprinted courtesy of
Margarita Kutsin, Ahlers Cressman & Sleight PLLCMs. Kutsin may be contacted at
margarita.kutsin@acslawyers.com
Anomaly in Adding a Third-Party Claimant to a Liability Insurance Coverage Dispute
May 05, 2026 —
David Adelstein - Florida Construction Legal UpdatesIn an insurance coverage lawsuit seeking declaratory relief, an insurer sued the third-party claimant. The insurer was seeking a declaration that there was no coverage, which naturally would impact the third-party claimant. The insured did not respond to the lawsuit and the insurer moved for a default judgment which was objected to by the third-party claimant. The trial court granted a final judgment in favor of the insurer, which prompted an appeal from the third-party claimant because the final judgment impacts its rights to coverage if it obtains a judgment against the insured.
The appellate court reversed but please take a look at this Court’s discussion on the issue of an insurer adding a third-party claimant to a coverage lawsuit when then the third-party cannot pursue a direct claim against the insurer until it obtains a settlement or judgment against the insured. It presents an interesting argument and counter-point for a third-party claimant that is added to the coverage lawsuit which has implications if it obtains a judgment against the insured:
This case involves an apparent anomaly in Florida law. It is well-established that third-party claimants injured by an insured’s negligence have a right as third-party beneficiaries to payment from the insured’s insurance proceeds. It is equally well-established that the third-party claimants’ rights in this regard do not accrue unless and until they obtain a verdict or settlement against the insured. A quick review of this law is helpful at this point.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com