Elite retained Southern General Agency (SGA) and The Lincoln Agency, LLC to procure insurance coverage for multiple properties. SGA/Lincoln obtained a property insurance policy from Nautilus. The property had two structures, a single-family home and a rear structure, which contained a small apartment. Elite claimed that it understood the policy to cover both structures. On September 9, 2022, a fire caused catastrophic damage to the rear structure and exterior damage to the primary structure. Nautilus denied payment for the rear structure, claiming it was not covered in the policy.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Most Expensive Signature to Not Get: Why Change Orders Matter
August 16, 2026 —
Kathryne E. Baldwin - Wilke FleuryGeorge Bernard Shaw has a quote we use a lot in my family: “The single biggest problem in communication is the illusion that it has taken place.” This is pertinent to contractors and homeowners alike because the cost of failing to get proper signatures on documents like construction contracts, and particularly, change orders, is heavy. Both contractors and homeowners are in the same boat as far as wanting to complete a job as swiftly as possible: contractors go on to their next job and homeowners can return to peace in their home. This is prime territory for either party to suggest the work be completed today and the contract or change order executed tomorrow, or even later. However, without a contract, there is no memorialization of the communication between the parties, which can lead to confusion and missed expectations on both sides.
Construction plans are rarely as neat and tidy as they originally seem to be. A contractor may uncover unforeseen conditions, an owner may request additional work or changes that require additional work, or weather interferes with project schedules or the work itself. Unfortunately, the signature that never gets collected can become one of the most expensive omissions on a project – for both sides.
Read the full story...Reprinted courtesy of
Kathryne E. Baldwin, Wilke FleuryMs. Baldwin may be contacted at
kbaldwin@wilkefleury.com
Building the Research and Healthcare Facilities of Tomorrow Without Impacting the Progress of Today
August 16, 2026 —
Jason Tobias - Construction ExecutiveResearch labs run experiments that can’t be paused. Hospitals treat patients around the clock. Yet these same facilities constantly need upgrades—new infrastructure, modernized systems, renovated spaces—to meet the demands of twenty-first century science and medicine. The challenge for construction teams isn’t just building. It’s building without ever turning the lights off.
This unique dynamic creates an environment where construction activities are happening adjacent to sensitive testing and treatment, a complex setting where disruptions can have serious consequences.
Skanska continues to successfully navigate these challenges across multiple sectors, including from occupied lab space at the
North Carolina Department of Environmental Quality’s (NCDEQ) Reedy Creek Laboratory in Raleigh to hospital corridors alongside staff and patients in various hospital locations across the country.
Reprinted courtesy of
Jason Tobias, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
What Construction Attorneys Do and When Contractors Need Them
August 11, 2026 —
Construction ExecutiveDirect Answer
A construction attorney advises contractors on contracts, payment rights, mechanic's liens, payment bond claims, change orders, delay claims, OSHA matters, defect claims, terminations and dispute resolution. The work covers far more than lawsuits—much of its value comes before a dispute ever becomes formal.
Construction attorneys help contractors protect payment rights, manage project risk, resolve disputes and avoid contract terms that can turn a profitable job into a financial loss. Their work covers more than lawsuits. A construction attorney may review a contract before bid day, help preserve lien rights, respond to a defective work claim, prepare for mediation or defend a contractor after a safety citation.
For contractors, legal counsel is often most valuable before a dispute becomes formal. A missed notice deadline, vague scope clause, unsigned change order or broad indemnity provision can create problems long before a claim is filed. Construction attorneys help identify those risks while there is still time to negotiate, document the issue or preserve leverage.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Colorado’s New Mechanic’s Lien Law: Bigger Claims, Stronger Protections, and New Risks for Owners and Contractors
October 12, 2026 —
David McLain - Colorado Construction Litigation BlogOn April 6, 2026, the same day that the Colorado Supreme Court issued its decision in Ralph L. Wadsworth Construction Company, LLC v. Regional Rail Partners, Governor Jared Polis signed Senate Bill 26-074 into law. The legislation, which took effect on August 12, 2026, clarifies the amounts that may be included in mechanic’s liens and public construction payment claims, as well as the circumstances under which those claims may be considered excessive.
While the timing of the Supreme Court’s decision and the Governor’s approval of SB 26-074 is noteworthy, the legislation has implications extending beyond the public works claims addressed in Wadsworth. Most significantly, it expressly addresses disputed and unliquidated amounts, including delay and disruption costs, in mechanic’s liens filed against private construction projects.
Read the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Actual Controversy Without Actual Exhaustion: California Supreme Court Allows Declaratory Relief and Bad Faith Claims Against Excess Insurers
August 24, 2026 —
Kyle A. Rudolph - Saxe Doernberger & Vita, P.C.California courts were previously split on the issue of whether an insured may bring declaratory relief claims against excess insurers prior to the exhaustion of underlying insurance. Some California courts held that the actual exhaustion of underlying insurance was necessary, whereas other courts allowed for these types of claims to proceed.[
1]
Recently, the California Supreme Court addressed this split of authority and, in doing so, handed down a significant win for policyholders. In Fox Paine & Company, LLC, et al. v. Twin City Fire Insurance Company et al., the Court held that insureds may proceed with bringing forth viable declaratory relief and bad faith claims against excess insurers prior to the exhaustion of underlying insurance.[
2] A summary of the Court’s opinion is provided below.
Read the full story...Reprinted courtesy of
Kyle A. Rudolph, Saxe Doernberger & Vita, P.C.Mr. Rudolph may be contacted at
KRudolph@sdvlaw.com
From Claim to Courtroom: How Documentation Shapes Construction Disputes
November 16, 2026 —
Taylor Orgeron - Construction ExecutiveThe main recurring issue in construction negligence cases is a lack of documentation during the early
litigation or claim evaluation phase. Proper documentation is not just helpful; it is essential. The moment to start gathering documents is the moment you receive a claim or become aware of a potential claim. Delays in gathering documentation or
inspecting the property can significantly increase exposure, limit available defenses and make the claim much more costly and difficult to resolve. Acting quickly and strategically can make all the difference.
Obviously, contracts, change orders, updated plans and specifications, permit applications and approvals should be requested and reviewed immediately. These items help clarify expectations, timelines, responsibilities and form the backbone of most litigation. The importance of collecting these items is self-evident and most contractors keep them on file. However, equally important and often overlooked are informal communications.
Reprinted courtesy of
Taylor Orgeron, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...Mr. Orgeron may be contacted at
taylor.orgeron@swiftcurrie.com
New York Team Secures Dismissal of Premises Liability Action Against Client
May 26, 2026 —
Lewis BrisboisNew York Associate Nicole Koch and Partner Jennine Gerrard recently secured a complete dismissal of a plaintiff’s claims for injuries following a fall in front of a client’s business at an outdoor mall.
The plaintiff alleged that she was walking on the sidewalk outside of the client's hair care supply store in the Bronx in May 2024 when she tripped and fell on a broken/defective portion of the sidewalk. As a result of the accident, the plaintiff suffered injuries to her spine, hip, wrist, and both knees. She proceeded to file suit in New York County Supreme Court against Lewis Brisbois’ client and the landlord for the property.
Read the full story...Reprinted courtesy of
Lewis Brisbois