Steel Cooling: Steel Costs Steadily Decline After Pandemic Price Shock
May 12, 2026 —
Construction ExecutiveSteel prices have continued trending downward after several years of volatility, according to Gordian’s latest analysis based on RSMeans Data. After dramatic spikes during the pandemic-era supply disruptions, the market has gradually stabilized as supply chains improve and demand softens in some construction segments. However, selective volatility and tariff uncertainty continue to influence pricing across the sector.
Key findings from the report include:
- Steel prices declining: The national average price of structural steel fell to about $2,343.93 per ton in January 2026, down 5.38% from the previous quarter and 7.18% year over year.
- Longer-term price correction: Steel costs have been trending downward since 2024 after earlier volatility driven by inflation, supply shortages and global demand swings.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
A Permitting Base Checklist for Data Centers and Power Plants
June 02, 2026 —
Michael S. McDonough, Stephen J. Humes & Stacey C. Wright - Gravel2Gavel Construction & Real Estate Law BlogThere is a lot of talk these days about “license to operate” for data centers, meaning management of the relationships with stakeholders and broader communities concerning both the benefits and adverse consequences of locating a facility in a particular locale. Here, we are speaking of “license to operate” more literally—namely, the legal and regulatory permitting and approval requirements for a privately owned data center whether by itself or colocated with a power generating plant.
Our Base Checklist includes generally and potentially applicable permitting requirements for development and operation, using California as an example. (Taking legal authority Frank Sinatra out of context, “If you can make it there, you can make it anywhere.”) The actual requirements for a given facility would depend, in part, on local law, including planning and zoning laws and plans, and the environment of the site. Just as examples, additional permitting and mitigation requirements might apply if sensitive receptors are located nearby (e.g., noise mitigation for residential dwellings), if sensitive and protected biological resources (e.g., jurisdictional waters and/or protected species) would be impacted, or if the present or former land uses require additional measures (e.g., hazardous materials remediation, mitigation for conversion of prime farmland, or protection of cultural resources). The scope of permit requirements would ultimately be determined by the applicable regulatory agencies and by the lead and responsible agencies under the applicable state environmental land use regime—in our reference case here, the California Environmental Quality Act (CEQA).
Reprinted courtesy of
Michael S. McDonough, Pillsbury,
Stephen J. Humes, Pillsbury and
Stacey C. Wright, Pillsbury
Mr. McDonough may be contacted at michael.mcdonough@pillsburylaw.com
Mr. Humes may be contacted at stephen.humes@pillsburylaw.com
Ms. Wright may be contacted at stephen.humes@pillsburylaw.com
Read the full story...
White and Williams LLP Secures $42.4 Million Award for Ventana DBS LLC in Philadelphia Marriott Construction Litigation
July 27, 2026 —
Craig O'Neill, Lindsay Liebman, Kristen Nichols Wright, Zachary Roth & William Taylor - White and WilliamsWhite and Williams LLP's Construction and Surety Practice attorneys secured a significant victory for client Ventana DBS LLC in a complex commercial construction dispute before the Philadelphia Court of Common Pleas, Commerce Division. The trial team, led by Bill Taylor, retired Partner, and Craig O'Neill, Co-Chair of the Construction and Surety Practice Group, with support from Lindsay Liebman, Counsel, Zachary Roth, Partner, Kristen Nichols Wright, Associate, and Sue Ferrante, Legal Secretary, obtained a $42.4 million award on Ventana's claims for unpaid work, delay costs, CASPA penalties and interest, attorneys’ fees and other project-related costs arising from the construction of the Marriott W/Element Hotel Project in Philadelphia.
To achieve this result, the White and Williams team managed an extensive discovery period over the course of four-years of litigation, conducted over sixty depositions, participated in court-ordered mediation and arbitration proceedings, and successfully represented Ventana during a bifurcated trial that spanned over the course of a year.
Reprinted courtesy of
Craig O'Neill, White and Williams,
Lindsay Liebman, White and Williams,
Kristen Nichols Wright, White and Williams,
Zachary Roth, White and Williams and
William Taylor, White and Williams
Mr. O'Neill may be contacted at oneillc@whiteandwilliams.com
Ms. Liebman may be contacted at liebmanl@whiteandwilliams.com
Ms. Wright may be contacted at wrightk@whiteandwilliams.com
Mr. Roth may be contacted at rothz@whiteandwilliams.com
Mr. Taylor may be contacted at taylorw@whiteandwilliams.com
Read the full story...
Seattle’s Residential Zoning Transformation: What Property Owners, Buyers, and Investors Should Understand
May 14, 2026 —
Lawrence S. Glosser - Ahlers Cressman & Sleight PLLCSeattle is in the midst of a significant transformation in residential land use policy. Longstanding neighborhood zoning patterns that historically favored detached single-family development are being reexamined in response to housing supply pressures, affordability concerns, and evolving state mandates.
For homeowners, purchasers, investors, and builders, these changes may create substantial new opportunities. They also create a heightened need for careful legal and practical due diligence.
While zoning reform can expand potential uses of property, it does not eliminate the many other constraints that may still govern what can actually be built.
Read the full story...Reprinted courtesy of
Lawrence S. Glosser, Ahlers Cressman & Sleight PLLCMr. Glosser may be contacted at
larry.glosser@acslawyers.com
Oracle's $16B Michigan Data Center Secures Financing as Power Contracts Face Appeals
June 08, 2026 —
Bryan Gottlieb - Engineering News-RecordA $16 billion hyperscale data center under construction outside Ann Arbor, Mich., has secured financing backed by Blackstone and other institutional investors, even as the project's power supply agreements now face a legal challenge before the Michigan Court of Appeals.
Read the full story...Reprinted courtesy of
Bryan Gottlieb, Engineering News-RecordMr. Gottlieb may be contacted at
gottliebb@enr.com
FERC Issues Show-Cause Orders: Impacts on California and Other Regional Power Markets
July 13, 2026 —
Stephen J. Humes, Alicia M. McKnight & Jason Drogin Atwood - Gravel2Gavel Construction & Real Estate Law BlogAt an open meeting on June 18, 2026, the Federal Energy Regulatory Commission (FERC) issued show-cause orders under Section 206 of the Federal Power Act to the six FERC-jurisdictional RTOs/ISOs—PJM Interconnection, ISO New England, Midcontinent Independent System Operator, Southwest Power Pool, New York Independent System Operator and California Independent System Operator—along with their transmission owners (TOs), directing each region and the TOs to justify or revise tariff provisions governing how data centers and other large loads connect to and receive transmission service from the grid. These show-cause orders will impact several power markets across the country, including California.
Reprinted courtesy of
Stephen J. Humes, Pillsbury,
Alicia M. McKnight, Pillsbury and
Jason Drogin Atwood, Pillsbury
Mr. Humes may be contacted at stephen.humes@pillsburylaw.com
Ms. McKnight may be contacted at alicia.mcknight@pillsburylaw.com
Mr. Atwood may be contacted at jason.atwood@pillsburylaw.com
Read the full story...
LA Scores Major Victory in a High-Exposure Premises Liability Action
July 06, 2026 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPOur firm is proud to announce a decisive defense victory obtained by Partner
Daniel Crespo and Associate
Lauren Landau for our client in a high-exposure premises liability action arising from a 2022 incident at an active school construction site in Perris, California. On March 10, 2026, the Riverside County Superior Court granted Summary Judgment in full for our client, dismissing all claims brought by Plaintiff, who alleged she tripped and fell over a curb while picking up her daughter from school and sustained ankle and wrist injuries as a result.
Through meticulous preparation and the strategic use of construction plans, contractual documents, and onsite surveillance video evidence, our team demonstrated that our client had no ownership, possession, or control over the portion of the existing sidewalk where the incident occurred, with construction plans unambiguously designating the area as pre-existing concrete outside our client’s scope of work, and the Construction Services Agreement expressly reserving control over all existing site improvements to the school district.
Read the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
California Poised for the Most Significant Residential Construction Defect Reforms in Decades
September 01, 2026 —
Thomas D. Fama & Andrew J. Mallon - Wood Smith Henning BermanThe California Legislature is considering legislation that would dramatically alter the landscape of residential construction defect litigation. Assembly Bill 1903, currently pending before the Senate Judiciary Committee, proposes extensive amendments to California's Right to Repair Act (Civil Code sections 895-945.5) that would substantially strengthen procedural protections for builders while narrowing the scope of recoverable construction defect claims.
If enacted, the legislation would affect virtually every stage of a construction defect dispute- from the initial notice of claim through litigation and settlement- and would introduce an entirely new certification process for newly constructed condominium projects. This article details some of the most significant proposed changes.
Higher Burden for Construction Defect Plaintiffs
Perhaps the most consequential change is the bill's modification of the proof required to establish liability. current law generally requires a claimant to demonstrate the residence fails to satisfy one of the statutory performance standards established under the Right to Repair Act. AB1903 would instead require claimants to establish three separate elements:
- A violation of an applicable statutory performance standard;
- The violation caused appreciable, present, non-speculative physical damage to another building component; and
- The violation resulted from the original construction.
Reprinted courtesy of
Thomas D. Fama, Wood Smith Henning Berman and
Andrew J. Mallon, Wood Smith Henning Berman
Mr. Fama may be contacted at tfama@wshblaw.com
Mr. Mallon may be contacted at amallon@wshblaw.com
Read the full story...