Construction Liens: Liening for Amounts Not Yet Technically Due Does Not Mean Lien Is Fraudulent
August 11, 2026 —
David Adelstein - Florida Construction Legal UpdatesA 2024 bankruptcy ruling, In re Edgewater Construction Group, Inc., 657 B.R. 668 (S.D.Fla. 2024), touched upon an interesting issue when it comes to construction liens. Is a construction lien fraudulent simply because the lien includes amounts not yet due? Not necessarily.
In this bankruptcy dispute, the subcontractor debtor (that filed for bankruptcy) recorded two construction liens on projects. The general contractor argued in the bankruptcy court that the subcontractor debtor’s liens were fraudulent.
As to the first lien, the general contractor argued that the lien was fraudulent because it included amounts that the debtor knew the general contractor had already paid to the debtor’s subcontractors/suppliers. The bankruptcy court disagreed: “The Court finds that, although the Debtor had been told that [the general contractor] had paid these subcontractors, in light of the ongoing dispute between Debtor and [the general contractor], it was reasonable for the Debtor to demand proof. Debtor’s subsequent filing of a partial satisfaction of lien once the Debtor received the requested proof of payment from [the general contractor] counters any claim of willful exaggeration.” In re Edgewater Construction Group, supra, at 672-673.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
$356 Million Judgement Against Developer for Defective Construction of DC Condominium
August 16, 2026 —
Nicholas D. Cowie - Cowie Law GroupOn July 31, 2026, the Superior Court of the District of Columbia entered a $356,085,513.00 judgment against developers JBG Smith for defective construction and renovation of the Wardman Tower Residential Condominium in Washington, D.C. The case is Wardman Tower Residential Condominium Unit Owners Association v. JBG Smith Properties, et al., No. 2020 CA 004807 B (D.C. Super. Ct.). In a 148-page
Trial Order, the D.C. Superior Court awarded $118,695,171.00 in damages in favor of the condominium association and against the condominium developers, including JBG Smith. The Court trebled those damages pursuant to the District of Columbia Consumer Protection Procedures Act (“CPPA”) to reach an ultimate judgment of $356,085,513.00. See Cowie Law Group:
DC Condominium Construction Defects: Recovering Attorney’s Fees, Litigation Expenses & Treble Damages Under the Consumer Protection Procedures Act.
Cowie Law Group, P.C. filed the lawsuit on behalf of the Association in 2020. The firm represented the Association throughout years of pretrial discovery and ultimately served as trial counsel with Williams & Connolly LLP during a lengthy bench trial before the Honorable Yvonne Williams. The Cowie Law Group team included attorneys, George A. Bealefeld, III, Albert G. McCarraher, Stanford L. Kimmel, III and Nicholas D. Cowie.
Read the full story...Reprinted courtesy of
Nicholas D. Cowie, Cowie Law GroupMr. Cowie may be contacted at
ndc@cowielawgroup.com
Achieving Sustainability Through Design-Build Delivery: Part I – An Overview
September 21, 2026 —
Joshua M. Pruett, Jennifer L. Harris & Tiffany A. Harrod - Peckar & Abramson, P.C.This article was written for the AGC’s Law in Brief and first appeared here.
Sustainability is no longer optional. What was once a matter of public policy or corporate preference has become a regulatory mandate and is reshaping how construction projects are designed, built, and operated. This mandate is not solely figurative. Rather, states have started to follow Europe’s lead by beginning to codify sustainability requirements into regulations and law. California led the charge by adding mandatory embodied-carbon emissions regulations into CALGreen, and other states, such as New York, have introduced bills to implement similar requirements. Owners, designers, and builders must now treat sustainability not as aspirational, but as a clearly defined contract issue from the outset, particularly where the project is expected to achieve a third-party rating, meet energy or resiliency targets, qualify for incentives, or comply with evolving green building codes.
In the federal public sector, construction contracts include a layered compliance framework—executive order-inspired policy, FAR-mandated clauses, and enduring statutory requirements—requiring contractors to integrate sustainability into design, material selection, and lifecycle management. Staying ahead means aligning with regulatory standards, conducting life-cycle cost analyses, and embedding sustainability into every procurement and construction decision.
Reprinted courtesy of
Joshua M. Pruett, Peckar & Abramson, P.C.,
Jennifer L. Harris, Peckar & Abramson, P.C. and
Tiffany A. Harrod, Peckar & Abramson, P.C.
Mr. Pruett may be contacted at jpruett@pecklaw.com
Ms. Harris may be contacted at jharris@pecklaw.com
Ms. Harrod may be contacted at tharrod@pecklaw.com
Read the full story...
Insurer Dispenses with Bad Faith Claim on Summary Judgment
June 22, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted the insurer’s motion for partial summary judgment because the insured failed to present evidence that the insurer failed to conduct a reasonable investigation. PSY Burger, LLC v. State Farm General Insurance Company, 2026 U.S. Dist. LEXIS 66991(C.D. Cal. March 20, 2026).
The insured’s commercial property suffered heavy damage from tropical storm Hilary. State Farm denied coverage to repair the damage. The insured sued State Farm alleging breach of contract and bad faith due to an inadequate investigation. Apparently, the insured did not retain an expert to opine on claims handling.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Vacant Building Negates Coverage for Broken Pipe
September 01, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe Michigan Court of Appeals found the insured was not covered for water damage because the commercial space was left vacant. Cherry Hill Recreation Center, Inc. v. Conifer Ins Co., 2026 Mich, App. LEXIS 5099 (Mich Ct. App. June 18, 2026).
Alan Abbas purchased a bowling alley. Due to the onset of the COVID-19 pandemic and executive orders issued by the governor, Abbas was unable to operate the bowling center for several months. During the winter, Abbas allowed the thermostat to drop significantly, with the building expected to be around 43 degrees Fahrenheit. He later admitted the sprinkler system’s pipes were not protected against freezing.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
DOI Finalizes Long-Awaited Modernization of Type A Natural Resource Damage Assessment Regulations
August 03, 2026 —
Amanda G. Halter, Ashleigh K. Myers & Jillian Marullo - Gravel2Gavel Construction & Real Estate Law BlogFor nearly three decades, the U.S. Department of the Interior’s (DOI) simplified “Type A” Natural Resource Damage Assessment (NRDA) regulations were available more in theory than in practice, constrained by dated models, narrow geographic applicability and a $100,000 cap that rarely matched the economics of modern environmental claims. DOI has now finalized revisions to the Type A natural resource damages assessment procedures under 43 C.F.R. Part 11 for hazardous substance releases under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) and the Clean Water Act (CWA), with the final rule published in the
Federal Register on July 13, 2026 and scheduled to become effective August 12, 2026.
As discussed
previously, DOI has sought to modernize what it views as an “inefficient and inflexible” process and restore the Type A procedure to its intended role as a more streamlined pathway for smaller, less contentious NRD claims. The final rule adopts a $5 million default damages threshold, allows use above that amount if all parties agree, clarifies that Type A may be used in all environments and for all natural resource types, and removes legacy model appendices that had tethered the process to outdated formulas.
Reprinted courtesy of
Amanda G. Halter, Pillsbury,
Ashleigh K. Myers, Pillsbury and
Jillian Marullo, Pillsbury
Ms. Halter may be contacted at amanda.halter@pillsburylaw.com
Ms. Myers may be contacted at ashleigh.myers@pillsburylaw.com
Ms. Marullo may be contacted at jillian.marullo@pillsburylaw.com
Read the full story...
Shane Singh Named One of Los Angeles Business Journal's 'Top 100 Lawyers of Los Angeles' for 2026
April 27, 2026 —
Lewis BrisboisSacramento Partner Shane Singh has been named one of the Los Angeles Business Journal's "Top 100 Lawyers of Los Angeles" for 2026.
The LABJ’s annual list honors Los Angeles' top lawyers for their achievements within the city's business community.
Read the full story...Reprinted courtesy of
Lewis Brisbois
Ninth Circuit Holds That Policies Covering Environmental Claims Do Not Have Aggregate Limits
May 12, 2026 —
Lorelie S. Masters & Joseph T. Niczky - Hunton Insurance Recovery BlogIn the case of
County of San Bernardino v. Insurance Company of the State of Pennsylvania, the Ninth Circuit recently addressed the issue of whether general liability policies issued in the 1960s and 1970s included aggregate limits for claims arising under the premises-operations coverage in CGL policies. The difference between the policyholder’s interpretation of the policies’ limits clauses and the insurer’s interpretation was worth hundreds of millions of dollars in exposure for the insurer. The Court closely examined the policy language and extrinsic evidence from both the insurance industry’s drafting history and the parties before concluding that the policies were ambiguous. The Court construed that ambiguity in favor of the policyholder and ruled that aggregate limits did not apply to the claims at issue. The Court’s decision underscores the importance of carefully examining a policy’s limits, especially for older policies written before 1986 when the insurance industry revised the standard-form CGL policy to state the aggregate limits apply not only to products liability claims but to premises-operations claims as well. Decades of insurance industry drafting history confirms, as the policyholder’s submissions in this case indicate, that the industry well understood that operations claims like the environmental waste-disposal claims at issue here typically were not subject to aggregate limits.
Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews Kurth LLP and
Joseph T. Niczky, Hunton Andrews Kurth LLP
Ms. Masters may be contacted at lmasters@hunton.com
Mr. Niczky may be contacted at jniczky@hunton.com
Read the full story...