Alert: Fraudulent Notice of Nonpayment Defense Applies to Payment Bond Claims
April 27, 2026 —
David Adelstein - Florida Construction Legal UpdatesUnder Florida’s Lien Law, there’s an affirmative defense or affirmative claim known as a “
fraudulent lien.” The fraudulent lien defense or claim is set out in Florida Statute s. 713.31. This defense also extends to payment bond claims, whether under a private statutory payment bond (Florida Statute s. 713.23) or a public payment bond (Florida Statute s. 255.05), as it pertains to the notice of nonpayment. A notice of nonpayment needs to be served within 90 days from final furnishing to preserve a claimant’s rights against the bond. However, there really has not been a case, until now, that discusses a “fraudulent notice of nonpayment.”
In K&M Electric Supply, Inc. v. Brown Electrical Solutions, LLC, 51 Fla.L.Weekly D672a (Fla. 4th DCA 2026), a prime contractor and surety prevailed at the trial level on their fraudulent notice of nonpayment defense based on a supplier’s notice of nonpayment and action against a public payment bond (under Florida Statute s. 255.05).
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
HHMR and Every One of its Partners Recognized by Legal 500 in Denver Elite – Real Estate
April 20, 2026 —
David McLain - Colorado Construction Litigation BlogHiggins, Hopkins, McLain & Roswell, LLC is pleased to announce its recognition as a Tier 1 firm in the Denver Elite rankings for Real Estate, a category that includes construction law and construction litigation, by The Legal 500. In addition, each of the firm’s partners has been individually recognized in the same rankings.
The firm’s individual recognitions include:
Read the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Navigating the New Frontier of Federal-State Energy Regulation: What Energy Companies Need to Know
June 08, 2026 —
Ryan J. Regula - Snell & WilmerIntroduction
The jurisdictional boundary between the Federal Energy Regulatory Commission (FERC) and the states is being actively contested, from challenges to landmark transmission planning rules to disputes over emergency cost-allocation orders, in ways that carry significant legal, financial, and operational implications for energy companies. For utilities, independent power producers, and transmission developers, understanding these dynamics is now a strategic imperative.
The Jurisdictional Divide: A Bright Line That Isn’t
The Federal Power Act divides authority between FERC and the states: FERC exercises jurisdiction over interstate transmission and wholesale electricity sales, while states retain authority over generation facilities, retail rates, and decisions about resource mix. The D.C. Circuit has regularly been called upon to “referee the Federal Power Act’s jurisdictional line separating [FERC’s] jurisdiction over the federal wholesale market and States’ jurisdiction over facilities used in local distribution.”1
Read the full story...Reprinted courtesy of
Ryan J. Regula, Snell & WilmerMr. Regula may be contacted at
rregula@swlaw.com
HDR Agreed to $12M Settlement With Miami Bridge Design-Build Team
May 12, 2026 —
Richard Korman - Engineering News-RecordHDR last year agreed to pay $12 million to the design-build construction contractor Archer Western-de Moya Group to settle its claims that the engineer had incompletely designed and under-designed Miami's new Signature Bridge when the joint venture committed to a fixed price prior to construction in 2018.
Read the full story...Reprinted courtesy of
Richard Korman, Engineering News-RecordMr. Korman may be contacted at
kormanr@enr.com
Ninth Circuit Holds That Policies Covering Environmental Claims Do Not Have Aggregate Limits
May 12, 2026 —
Lorelie S. Masters & Joseph T. Niczky - Hunton Insurance Recovery BlogIn the case of
County of San Bernardino v. Insurance Company of the State of Pennsylvania, the Ninth Circuit recently addressed the issue of whether general liability policies issued in the 1960s and 1970s included aggregate limits for claims arising under the premises-operations coverage in CGL policies. The difference between the policyholder’s interpretation of the policies’ limits clauses and the insurer’s interpretation was worth hundreds of millions of dollars in exposure for the insurer. The Court closely examined the policy language and extrinsic evidence from both the insurance industry’s drafting history and the parties before concluding that the policies were ambiguous. The Court construed that ambiguity in favor of the policyholder and ruled that aggregate limits did not apply to the claims at issue. The Court’s decision underscores the importance of carefully examining a policy’s limits, especially for older policies written before 1986 when the insurance industry revised the standard-form CGL policy to state the aggregate limits apply not only to products liability claims but to premises-operations claims as well. Decades of insurance industry drafting history confirms, as the policyholder’s submissions in this case indicate, that the industry well understood that operations claims like the environmental waste-disposal claims at issue here typically were not subject to aggregate limits.
Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews Kurth LLP and
Joseph T. Niczky, Hunton Andrews Kurth LLP
Ms. Masters may be contacted at lmasters@hunton.com
Mr. Niczky may be contacted at jniczky@hunton.com
Read the full story...
50 State Matrices | 2026 Edition
March 03, 2026 —
Gordon Rees Scully MansukhaniGRSM’s 50 State Legal Matrices provide a comprehensive, state-by-state snapshot of statutory law across all 50 U.S. states. Spanning critical areas such as indemnification, contractor licensing, labor standards, statute of limitations, and more, this resource enables businesses and counsel to quickly identify key legal requirements and variations across jurisdictions.
Designed as a practical starting point rather than definitive legal advice, the Matrices help multi-state operators and attorneys navigate the complex patchwork of laws that can vary dramatically from one state to another.
Read the full story...Reprinted courtesy of
Gordon Rees Scully Mansukhani
Four Families Now Live in the Season Six Rock the Block Homes in Grantsville, Utah
April 20, 2026 —
Hamlet HomesSALT LAKE CITY, April 20, 2026 /PRNewswire/ -- The premier of Rock the Block season seven aired last Monday and is set in Las Vegas, Nevada. Rock The Block is HGTV's highest rated show. Last year, season six was set in Utah and had HGTV's highest rating yet, with over 14 million viewers. All episodes of season six were filmed in the Worthington Ranch community in Grantsville, Utah. The four homes on the show were built by Utah builder Hamlet Homes. During the show, the location of the four Rock The Block homes had to be kept secret and were surrounded by a locked gate. After over a year of being inaccessible, the Utah public was invited in May 2025 to tour the homes and help raise money together for charity. On May 30-31, 2025, Hamlet hosted a 'Rock The Block Party' where the public was able to walk through the homes made famous by the show.
Hamlet Owner, VP of Marketing & Design Tami Ostmark shares stories from the show and her perspective of what it's like to be the builder on a national show like this. Ostmark was on set almost the entire time. "As expected, there were times when there was tension on the set. All four designers were super competitive with each other. It's amazing that the production team was able to produce the show as well as they did. I'm very impressed," said Ostmark.
Another interesting point related to the show is how much work the local builder is responsible for. Some nights as many as 30 Hamlet team members worked through the night to keep up with the pace of production. "Each designer provided their own trusted carpenters to do finishing work. In two of the cases, designers' flew their favorite carpenters in to carry out their visions. Given the quick turnaround, it's not always practical for finishing work to be permanent. Sometimes, it just needs to look appealing on camera," said Ostmark. This is frequently referred to as 'TV Magic'. "When the show was over, Hamlet re-did any areas that required extra attention". The show really does shoot in only 7 weeks as depicted. This creates a fast pace that was very exciting to be a part of", continued Ostmark. All four of the homes featured on the show have since been purchased; four Utah families currently call them home.
ABOUT HAMLET HOMES
Hamlet Homes (www.hamlethomes.com) crafts quality customer-oriented townhomes and single-family homes located in attractively designed communities in Utah and Idaho. Since the company's founding in 1995, Hamlet has built over 5,000 homes in 80 communities. The company is a proud recipient of many awards on Sustainable Business & Design, Quality Builder Awards; recognized both locally and nationally. Named by the Salt Lake Chamber of Commerce as the 'Veteran Owned Small Business of the Year, in 2019'. Hamlet has since been named several times to the Professional Builder's Housing Giants List and annual HOME AWARDS Best Customer Experience. Most recently in 2026, Hamlet was named Utah's 'Best of State for Real Estate Development and Utah Businesses 'Best Companies to Work For' for the 6th consecutive year.
Are “Financial Hardship” Damages Recoverable?
June 08, 2026 —
David Adelstein - Florida Construction Legal UpdatesIn a case out of the Civilian Board of Contract Appeals, F.O.G., LLC v. Department of the Interior, CBCA 8203, 2026 WL 1191881 (CBCA 2026) a contractor claimed damages that included “financial hardship” damages due to slow payments. The financial hardship damages included personal damages to the contractor’s president and his wife. Are these damages recoverable? Drumroll…The Board ruled that the contractor cannot recover such financial hardship damages.
As it relates the personal financial hardship damages, the Board ruled, “Neither [the contractor’s] president nor his wife are a party to this contract, are in privity of contract with [the government], or are the beneficiaries under this contract. [The contractor], therefore, cannot recover for any losses that either one has suffered individually and that [the contractor] claimed in this appeal.” F.O.G., LLC, supra.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at