What Massachusetts Contractors and Developers Can Learn from Cannistraro v. Columbia Construction
July 13, 2026 —
Anthony LaPlaca & Luke Marston - The Construction SeytIntroduction
On June 26, 2026 the Massachusetts Supreme Judicial Court issued its decision in J.C. Cannistraro, LLC v. Columbia Construction Co.—a holding that sits at the intersection of Prompt Pay Act compliance and the Massachusetts Arbitration Act.
[1]
Most already know that the Massachusetts Prompt Pay Act (PPA) imposes strict timing and certification requirements for rejecting payment applications and proposed change orders on projects valued at $3 million or more. Most notably, the PPA requires the paying party to give the payee written notice of its approval or rejection of progress applications and proposed changes within 15 days of receipt, which notice must include a “factual and contractual basis for the rejection” and must be “certified as made in good faith.”
[2] In the absence of a timely certified notice, payment is “deemed to be approved” unless the payor properly rejects payment before it comes due.
[3]
Reprinted courtesy of
Anthony LaPlaca, Seyfarth Shaw LLP and
Luke Marston, Seyfarth Shaw LLP
Mr. LaPlaca may be contacted at alaplaca@seyfarth.com
Mr. Marston may be contacted at lmarston@seyfarth.com
Read the full story...
White and Williams LLP Secures $42.4 Million Award for Ventana DBS LLC in Philadelphia Marriott Construction Litigation
July 27, 2026 —
Craig O'Neill, Lindsay Liebman, Kristen Nichols Wright, Zachary Roth & William Taylor - White and WilliamsWhite and Williams LLP's Construction and Surety Practice attorneys secured a significant victory for client Ventana DBS LLC in a complex commercial construction dispute before the Philadelphia Court of Common Pleas, Commerce Division. The trial team, led by Bill Taylor, retired Partner, and Craig O'Neill, Co-Chair of the Construction and Surety Practice Group, with support from Lindsay Liebman, Counsel, Zachary Roth, Partner, Kristen Nichols Wright, Associate, and Sue Ferrante, Legal Secretary, obtained a $42.4 million award on Ventana's claims for unpaid work, delay costs, CASPA penalties and interest, attorneys’ fees and other project-related costs arising from the construction of the Marriott W/Element Hotel Project in Philadelphia.
To achieve this result, the White and Williams team managed an extensive discovery period over the course of four-years of litigation, conducted over sixty depositions, participated in court-ordered mediation and arbitration proceedings, and successfully represented Ventana during a bifurcated trial that spanned over the course of a year.
Reprinted courtesy of
Craig O'Neill, White and Williams,
Lindsay Liebman, White and Williams,
Kristen Nichols Wright, White and Williams,
Zachary Roth, White and Williams and
William Taylor, White and Williams
Mr. O'Neill may be contacted at oneillc@whiteandwilliams.com
Ms. Liebman may be contacted at liebmanl@whiteandwilliams.com
Ms. Wright may be contacted at wrightk@whiteandwilliams.com
Mr. Roth may be contacted at rothz@whiteandwilliams.com
Mr. Taylor may be contacted at taylorw@whiteandwilliams.com
Read the full story...
U.S. Supreme Court Decision May Negate State Law Requirement to File a Certificate of Merit with the Complaint in a Federal Action Against a Design Professional
April 27, 2026 —
Christopher Olsen & Phillip Boldt - ConsensusDocsTo deter frivolous and unfounded claims against design professionals, states throughout the country have enacted statutes which generally require litigants to furnish a formal certification of merit (“COM”) from a qualified expert or face potential dismissal of their lawsuit. These COM statutes can impose a significant front-end burden on claimants who must pay an expert to review project records, interview the project team, and prepare a formal report before the lawsuit can be filed—often regardless of the amount in controversy. However, in light of a recent U.S. Supreme Court decision in a medical malpractice case, most, if not all of these statutes, may no longer be enforceable in federal court. This article examines the recent decision in Berk v. Choy, 146 S. Ct. 546 (2026), the decisions thus far which have applied Berk to invalidate COM statutes, and other categories of statutes applicable to the construction industry which may face a similar fate.
The U.S. Supreme Court Decision (Berk v. Choy)
In Berk, the plaintiff, Harold Berk, sued a doctor for medical malpractice under Delaware law in Delaware federal court. 146 S. Ct. at 551. Under Del. Code, Tit. 18, § 6853(a)(1), an affidavit of merit (like a COM) must accompany a complaint alleging medical malpractice. Id. Berk failed to include an affidavit of merit with his complaint. Id. at 552. Applying Delaware state law, the federal court dismissed Berk’s medical malpractice claim. Berk appealed to the Third Circuit, arguing that the affidavit of merit required by § 6853(a)(1) is unenforceable in federal court because it is more onerous than the Federal Rules of Civil Procedure. The Third Circuit affirmed the District Court’s ruling, finding § 6853(a)(1) enforceable in federal court.
Reprinted courtesy of
Christopher Olsen, Peckar & Abramson, P.C. and
Phillip Boldt, Peckar & Abramson, P.C.
Mr. Olsen may be contacted at colsen@pecklaw.com
Mr. Boldt may be contacted at pboldt@pecklaw.com
Read the full story...
Court to General Contractor: Too Late to Reclaim $600K Sub Overpayment
March 03, 2026 —
Richard Korman - Engineering News-RecordMassachusetts contractors and their attorneys are once again testing the limits of the state's 15-year-old prompt-pay law, with concerned prime contractors asking an appeals court to overturn a lower court ruling that they believe gives subcontractors a powerful upper hand in payment disputes.
Read the full story...Reprinted courtesy of
Richard Korman, Engineering News-RecordMr. Korman may be contacted at
kormanr@enr.com
DOI Finalizes Long-Awaited Modernization of Type A Natural Resource Damage Assessment Regulations
August 03, 2026 —
Amanda G. Halter, Ashleigh K. Myers & Jillian Marullo - Gravel2Gavel Construction & Real Estate Law BlogFor nearly three decades, the U.S. Department of the Interior’s (DOI) simplified “Type A” Natural Resource Damage Assessment (NRDA) regulations were available more in theory than in practice, constrained by dated models, narrow geographic applicability and a $100,000 cap that rarely matched the economics of modern environmental claims. DOI has now finalized revisions to the Type A natural resource damages assessment procedures under 43 C.F.R. Part 11 for hazardous substance releases under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) and the Clean Water Act (CWA), with the final rule published in the
Federal Register on July 13, 2026 and scheduled to become effective August 12, 2026.
As discussed
previously, DOI has sought to modernize what it views as an “inefficient and inflexible” process and restore the Type A procedure to its intended role as a more streamlined pathway for smaller, less contentious NRD claims. The final rule adopts a $5 million default damages threshold, allows use above that amount if all parties agree, clarifies that Type A may be used in all environments and for all natural resource types, and removes legacy model appendices that had tethered the process to outdated formulas.
Reprinted courtesy of
Amanda G. Halter, Pillsbury,
Ashleigh K. Myers, Pillsbury and
Jillian Marullo, Pillsbury
Ms. Halter may be contacted at amanda.halter@pillsburylaw.com
Ms. Myers may be contacted at ashleigh.myers@pillsburylaw.com
Ms. Marullo may be contacted at jillian.marullo@pillsburylaw.com
Read the full story...
The AVOID Act: A New Timeline for Liability in New York Construction Projects
February 23, 2026 —
Meghan Douris - The Construction SeytBy April 18, 2026, New York construction litigation will operate on a faster—and far less forgiving—timeline. The Avoiding Vexatious Overuse of Impleading to Delay (the “AVOID Act”), signed into law on December 19, 2025, fundamentally rewrites third‑party practice under CPLR § 1007 by imposing strict deadlines to bring subcontractors, suppliers, and other responsible parties into a case.
For owners, developers, general contractors, and their in‑house counsel, this change will shift risk assessment, contract enforcement, and litigation strategy to the very front end of a claim—particularly in New York Labor Law and construction defect cases.
What Changed—and Why It Matters to Construction Cases
Historically, New York defendants could implead subcontractors and other players well into discovery. The AVOID Act ends that practice.
Read the full story...Reprinted courtesy of
Meghan Douris, Seyfarth Shaw LLPMs. Douris may be contacted at
mdouris@seyfarth.com
Construction Liens and the “Substantial Performance” Doctrine
April 08, 2026 —
David Adelstein - Florida Construction Legal UpdatesIn a recent case dealing with a construction lien, the driving issue was whether the air conditioning contractor “substantially performed” before recording its construction lien against residential property. The importance here pertains to the substantial performance doctrine with respect to construction liens. The Third District Court of Appeal explained, with relevant citations, this doctrine as follows:
Under Florida law, a contractor is entitled to a mechanic’s lien if he complies with all provisions of Chapter 713, governing construction liens, and “has substantially performed the contract.” Grant v. Wester, 679 So. 2d 1301, 1307 (Fla. 1st DCA 1996) (quotation omitted); Langley v. Knowles, 958 So. 2d 1149, 1151 (Fla. 5th DCA 2007) (“The substantial performance doctrine recognizes that a contactor who complies with all of the provisions of the contactor’s lien statute is entitled to enforce a lien if he has substantially, but not completely, performed his contractual obligations.”). Substantial performance is performance “so nearly equivalent to what was bargained for that it would be unreasonable to deny the promisee the full contract price subject to the promisor’s right to recover whatever damages may have been occasioned him by the promisee’s failure to render full performance.” Ocean Ridge Dev. Corp. v. Quality Plastering, Inc., 247 So. 2d 72, 75 (Fla. 4th DCA 1971).
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Texas Voids Out-of-State Forum and Choice of Law Clauses in Construction Contracts
March 17, 2026 —
Conor G. Bateman - Snell & WilmerThe Texas Legislature amended statutes impacting construction contracts for projects located in Texas to declare any forum selection clause or choice of law provision “void as against public policy,” and mandate venue for any litigation or arbitration shall be in the Texas county in which the work is performed. The parties may stipulate to a different venue only after the dispute arises.
Forum selection clauses and choice of law provisions are common in construction contracts. Frequently, general contractors based in other jurisdictions require subcontractors to sign contracts designating the contractor’s preferred venue for any dispute. These contracts may also select the law of another state to govern the contract.
Read the full story...Reprinted courtesy of
Conor G. Bateman, Snell & WilmerMr. Bateman may be contacted at
cbateman@swlaw.com