Presumption of Prejudice Applies to All Affirmative Defenses Regarding Insured’s Failure to Comply with Post-Loss Policy Conditions
June 23, 2026 —
David Adelstein - Florida Construction Legal Updatesn a recent property insurance coverage dispute, an issue on appeal pertained to the “prejudice” jury instruction associated with the insured’s failure to comply with post-loss policy conditions. The trial court found that the prejudice only pertained to prompt notice and not other post-loss policy conditions. This was reversed on appeal as prejudice applied to ALL the post loss policy conditions that the insured failed to comply with, not just the prompt notice requirement. The prejudice presumption applies to all affirmative defenses regarding an insured’s failure to comply with post-loss policy conditions.
Consider this discussion when dealing with an insurer raising prejudice as an affirmative defense to do an insured’s failure to comply with post-loss policy conditions, and the associated burdens of proof:
On appeal, [the insurer] contends the trial court erred by instructing the jury that the presumption of prejudice was inapplicable to all of its post-loss obligation defenses except prompt notice. We agree.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Endra Rethinks MEP Design with AI
July 06, 2026 —
Aarni Heiskanen - AEC BusinessNiklas Lindgren, co-founder and CEO of Endra, joins the
AEC Business Podcast to discuss why his Stockholm-based startup is rebuilding MEP design from the ground up with AI. Endra recently raised $50 million in Series A funding and counts some of the world’s largest engineering consultancies as customers.
Niklas explains why Revit’s underlying data model is too coarse to support deep automation, and why Endra built its own granular 3D data model instead of working as a plugin. He describes Endra’s “spatial AI” approach to routing conduit and ductwork without clashes, and how the platform models entire electrical systems, from receptacle to transformer, inside a single source of truth.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Did You Get the Message? (And does it count?) The Legal Consequences of Text Messages, Group Chats, and Informal Digital Communication on Construction Projects
March 17, 2026 —
Kellie Ros & Curtis Martin - ConsensusDocsIntroduction: The New Reality of Construction Communication
Construction projects have always depended on a constant stream of communication. Today’s project managers, superintendents, and foremen have broadened the method of communication to include convenient forms of digital communication. Superintendents text photos of field conditions, owners send quick approvals through WhatsApp, architects clarify design intent in a Teams chat, and subcontractors coordinate sequencing through group texts. These channels are fast, convenient, and deeply embedded in modern project culture. Yet the legal framework governing construction contracts has not evolved at the same pace. Many contracts still assume – or require – that notice, directives, and approvals occur through formal written channels—letters, emails to designated recipients, or structured project‑management platforms. This disconnect creates significant legal risk, particularly for contractors who rely on informal messages as authorization for extra work or schedule changes. Courts are increasingly asked to interpret text messages, chat threads, and screenshots as evidence of notice, direction, or waiver. The outcomes vary, but the trend is unmistakable: informal digital communication is now part of the project record, and it can bind parties in ways they did not expect.
Reprinted courtesy of
Kellie Ros, Peckar & Abramson, P.C. and
Curtis Martin, Peckar & Abramson, P.C.
Ms. Ros may be contacted at kros@pecklaw.com
Mr. Martin may be contacted at cmartin@pecklaw.com
Read the full story...
Project Labor Agreements: A New Bid Protest Forum Split
May 14, 2026 —
Dirk D. Haire, David P.J. Timm and Michael J. Brewer - ConsensusDocsAdvertisements often include a disclaimer: “individual results may vary.” Similarly, lawyers are notorious for saying “it depends.” The mandatory Project Labor Agreement (“PLA”) regulations have recently placed into context this adage as it applies to federal contract bid protests, with very different results depending on which forum – the Court of Federal Claims (“COFC”) versus the Government Accountability Office (“GAO”) – different contractors have selected to bring PLA bid protests.
Over the last two years, over 30 protesters have successfully achieved removal of mandatory PLAs from large-scale federal construction contracts based on two landmark bid protest decisions issued by the COFC. Similar challenges to PLAs at the GAO, however, have not been successful in removing PLAs, highlighting an emerging trend that the COFC is often a more effective relief forum than GAO for government construction contractors.
Reprinted courtesy of
Dirk D. Haire, Burr & Forman LLP,
David P.J. Timm, Burr & Forman LLP and
Michael J. Brewer, Burr & Forman LLP
Mr. Haire may be contacted at dhaire@burr.com
Mr. Timm may be contacted at dtimm@burr.com
Mr. Brewer may be contacted at mbrewer@burr.com
Read the full story...
Differing Site Conditions Claim Requires a Misrepresentation
May 14, 2026 —
David Adelstein - Florida Construction Legal UpdatesIf you are entertaining a
differing site conditions claim, consider this Third District Court of Appeals case from the mid-90s.
In Hendry Corp. v. Metropolitan Dade County, 648 So.2d 140 (Fla. 3d DCA 1995), a contractor was hired by Dade County to demolish the old Rickenbacker Causeway in Miami. The original 1941 plans of the causeway were made available to contractors. The lowest bidding contractor that was awarded the project based its bid “on its conclusion that the pilings supporting the old bridge were made of concrete.” Hendry, supra at 141. The contractor based this conclusion on the original plans, its visual observation, and experience.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
On Checks and Balances
March 03, 2026 —
Garret Murai - California Construction Law BlogIt’s called “checks and balances” for a reason. And, generally, it works well so long as there are clear boundaries between the “co-equal” branches of government.
In
Associated General Contractors of California, Inc. v. Department of Industrial Relations, 108 Cal.App.5th 243 (2025), the 3rd District Court of Appeals upheld a set of regulations issued by the California Apprenticeship Council that contradicted an earlier 2015 ruling of the Court of Appeals.
The Associated General Contractors of California Case
At issue in the case was California’s Prevailing Wage Law which requires public works contractors to hire a certain ratio of apprentices. The purpose of the apprenticeship requirements is to maintain the pipeline of skilled tradespeople on taxpayer-funded projects.
Read the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Builders Support Most of Bipartisan Housing Reform Bill in Congress
March 31, 2026 —
Esther D'Amico - Engineering News-RecordSeveral homebuilding groups say they support most of the massive housing reform bill making its way through Congress but want to see certain provisions including those related to build-to-rent and manufactured homes changed before it advances any further.
Read the full story...Reprinted courtesy of
Esther D'Amico, Engineering News-RecordENR may be contacted at
enr@enr.com
Pulling the Plug, Preserving the Product: Protecting Rights to a Modular Subcontractor’s Work Post-Termination
June 08, 2026 —
Paul Williamson - ConsensusDocsVolumetric Modular Construction (VMC) is a building method where a structure is divided into large components or modules, fabricated in an offsite factory and then transported to a construction site for assembly.[
1] Proponents of VMC hail it as a cost-efficient alternative to traditional building methods that leads to more consistent quality and shorter construction duration.[
2] Due to a growing labor shortage, high demand for compressed project schedules, and stagnant construction productivity rates, the construction industry is embracing VMC.[
3] A recent report on the market size of prefabricated construction estimates that from 2026 to 2031, VMC will grow at a compound annual growth rate of 7.16% and become a 413.11-billion-dollar industry.[
4]
As VMC becomes more prevalent, owners, general contractors, and subcontractors must consider how to effectively contract for modular construction. One important consideration, which this article focuses on, is navigating termination of a modular subcontractor.
Read the full story...Reprinted courtesy of