Arizona Court of Appeals Clarifies Homeowners Association Open Meeting Requirements
June 29, 2026 —
Jill Casson Owen, Benjamin J. Hawkins & Stephen Wright - Snell & WilmerA Z N H Revocable Trust v. Sunland Springs Village Homeowners Association, No. 1 CA-CV 25-0424 (Ariz. Ct. App. Apr. 28, 2026)
OVERVIEW
The Arizona Court of Appeals issued an opinion clarifying how homeowners associations must conduct meetings under A.R.S. § 33-1804. The decision reinforces the legislative policy favoring transparency in association governance, bringing association meeting requirements more in line with the open meeting standards applicable to public bodies under A.R.S. § 38-431 et seq. (Arizona’s Open Meeting Law).
KEY HOLDINGS
1. All Voting and Formal Actions Must Occur in Open Meetings
The Court affirmed that association boards cannot vote or take formal action during closed (executive) sessions. Under A.R.S. § 33-1804(A), associations may close portions of meetings only for “consideration” of certain enumerated topics, such as legal advice, pending litigation, or personal/financial information about individual members. The Court interpreted “consideration” to mean discussion and deliberation, not voting. The Court noted that dictionaries define “consider” as “spending time thinking about a possibility” and “formulating an opinion,” which are processes that precede formal action. This interpretation mirrors how Arizona’s Open Meeting Law (A.R.S. § 38-431.03(D)) prohibits public bodies from voting in executive session.
Reprinted courtesy of
Jill Casson Owen, Snell & Wilmer,
Benjamin J. Hawkins, Snell & Wilmer and
Stephen Wright, Snell & Wilmer
Ms. Owen may be contacted at jowen@swlaw.com
Mr. Hawkins may be contacted at bhawkins@swlaw.com
Mr. Wright may be contacted at swright@swlaw.com
Read the full story...
Builders Oppose Senate Housing Bill Over Investor Ban Provision
March 24, 2026 —
Katy O'Donnell - BloombergA powerful group representing the nation’s home builders is coming out against the most significant housing legislation in more than a decade over a provision negotiated by the White House that would restrict institutional investors from purchasing single-family homes.
The builders’ objection could imperil the bill’s chances of becoming law, even as leaders of both parties are desperate to show they are doing something to alleviate voters’
cost-of-living concerns. The Senate voted 90-8 to clear a procedural hurdle for the bill on Wednesday, with a vote on final passage expected early next week.
The inclusion of the investor ban in a broader housing bill was key to getting the White House on board,
Senate Banking Committee Chairman Tim Scott, a Republican from South Carolina, told reporters Tuesday.
Read the full story...Reprinted courtesy of
Katy O'Donnell, Bloomberg
Why Travelers Fought a Fire Claim for Invisible Smoke Damage
February 23, 2026 —
Elaine Silver - Engineering News-RecordJust 40 minutes after midnight on Sept. 27, 2018, the sky lit up over Birmingham, Ala. A fire engulfed an apartment building under construction—the last-to-be completed section of a wood-framed complex called the Metropolitan. It fueled one of the largest recorded blazes in the city’s history.
Read the full story...Reprinted courtesy of
Elaine Silver, Engineering News-RecordENR may be contacted at
enr@enr.com
Building in Arizona’s Data Center Boom: How Federal Executive Orders, State Regulation, and National-Security Policy Are Reshaping the Rules for Developers
June 02, 2026 —
Ryan J. Regula - Snell & WilmerDevelopers and practitioners evaluating data center projects in Arizona face a regulatory environment shifting on three fronts simultaneously. Federal executive orders are opening new land, streamlining permitting, and channeling financial incentives toward qualifying projects — but they are not preempting the state and local rules that most directly affect project economics. A carve-out in the December 2025 Artificial Intelligence (AI) Framework Executive Order preserves Arizona’s authority over data center infrastructure, meaning the Arizona Corporation Commission’s (ACC) rate-classification docket, municipal zoning restrictions, water-use ordinances, and pending grid cost-allocation legislation remain the binding constraints on project feasibility. Understanding where federal tailwinds end and state and local headwinds begin is essential for any developer sizing risk or selecting sites in the state.
The Federal Landscape: An Interlocking Framework of Executive Orders
Five interlocking executive orders are accelerating data center development nationally, but none overrides Arizona’s authority over siting energy, or infrastructure.
Read the full story...Reprinted courtesy of
Ryan J. Regula, Snell & WilmerMr. Regula may be contacted at
rregula@swlaw.com
Seventh Circuit Finds “Additional Insured” Requirements Met Where Non-Party Subcontractor Was Proximate Cause of Underlying Injuries
February 23, 2026 —
Jason Taylor - Traub Lieberman Insurance Law BlogIn Atlanta Gas Light Company et al v. Navigators Ins. Co., Nos. 24-2888 & 24-2889 (7th Cir. Jan. 22, 2026), the Seventh Circuit Court of Appeals assessed whether an upstream contractor was an “additional insured” under an umbrella policy issued to its subcontractor. Atlanta Gas and Southern Company Gas (“AGL”) hired United States Infrastructure Corporation (“USIC”) to locate and mark gas lines that AGL owned throughout Georgia. In 2018, USIC failed to mark a gas line in Homerville, Georgia, and a boring company struck it, leading to an explosion that severely injured three women. The victims settled their claims with USIC but did not come to terms with AGL. AGL eventually did settle with the victims, but only after they sued AGL in Georgia state court (the “Underlying Suits”). AGL’s service agreement with USIC required USIC to obtain primary and excess liability insurance coverage that included AGL as an additional insured. Because USIC’s settlement with the victims exhausted its primary policy, AGL tendered the defense and indemnification of the Underlying Suits to USIC’s excess insurer, Navigators. Navigators denied the request on the ground that AGL was not an “additional insured” under the policy.
Read the full story...Reprinted courtesy of
Jason Taylor, Traub LiebermanMr. Taylor may be contacted at
jtaylor@tlsslaw.com
Celebrating Freedom: The Overlooked Freedom to Contract in Commercial Insurance
July 20, 2026 —
Michael S. Levine & Andrea DeField - Hunton Insurance Recovery BlogHappy 4th and 250 years of freedom . . . to contract!
Many policyholders assume insurance policies are “standard” and must be accepted as-is. That assumption is often wrong—and dangerously limiting. Unlike many consumer insurance markets, the commercial insurance realm preserves a robust “freedom to contract,” allowing sophisticated policyholders to negotiate terms, exclusions, definitions, and limits before a policy is even issued. Particularly in recent years, high-profile disputes over cyber coverage, business interruption, and war/cyber exclusions have shown not just what happens when coverage is denied, but what could have been done up front to avoid those fights.
This post highlights the power policyholders still hold in the negotiation process and illustrates, with concrete examples from recent media-covered disputes, how that freedom can be strategically used.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth LLP and
Andrea DeField, Hunton Andrews Kurth LLP
Mr. Levine may be contacted at mlevine@hunton.com
Ms. DeField may be contacted at adefield@hunton.com
Read the full story...
New York Team Secures Dismissal of Premises Liability Action Against Client
May 26, 2026 —
Lewis BrisboisNew York Associate Nicole Koch and Partner Jennine Gerrard recently secured a complete dismissal of a plaintiff’s claims for injuries following a fall in front of a client’s business at an outdoor mall.
The plaintiff alleged that she was walking on the sidewalk outside of the client's hair care supply store in the Bronx in May 2024 when she tripped and fell on a broken/defective portion of the sidewalk. As a result of the accident, the plaintiff suffered injuries to her spine, hip, wrist, and both knees. She proceeded to file suit in New York County Supreme Court against Lewis Brisbois’ client and the landlord for the property.
Read the full story...Reprinted courtesy of
Lewis Brisbois
U.S. Supreme Court Decision May Negate State Law Requirement to File a Certificate of Merit with the Complaint in a Federal Action Against a Design Professional
April 27, 2026 —
Christopher Olsen & Phillip Boldt - ConsensusDocsTo deter frivolous and unfounded claims against design professionals, states throughout the country have enacted statutes which generally require litigants to furnish a formal certification of merit (“COM”) from a qualified expert or face potential dismissal of their lawsuit. These COM statutes can impose a significant front-end burden on claimants who must pay an expert to review project records, interview the project team, and prepare a formal report before the lawsuit can be filed—often regardless of the amount in controversy. However, in light of a recent U.S. Supreme Court decision in a medical malpractice case, most, if not all of these statutes, may no longer be enforceable in federal court. This article examines the recent decision in Berk v. Choy, 146 S. Ct. 546 (2026), the decisions thus far which have applied Berk to invalidate COM statutes, and other categories of statutes applicable to the construction industry which may face a similar fate.
The U.S. Supreme Court Decision (Berk v. Choy)
In Berk, the plaintiff, Harold Berk, sued a doctor for medical malpractice under Delaware law in Delaware federal court. 146 S. Ct. at 551. Under Del. Code, Tit. 18, § 6853(a)(1), an affidavit of merit (like a COM) must accompany a complaint alleging medical malpractice. Id. Berk failed to include an affidavit of merit with his complaint. Id. at 552. Applying Delaware state law, the federal court dismissed Berk’s medical malpractice claim. Berk appealed to the Third Circuit, arguing that the affidavit of merit required by § 6853(a)(1) is unenforceable in federal court because it is more onerous than the Federal Rules of Civil Procedure. The Third Circuit affirmed the District Court’s ruling, finding § 6853(a)(1) enforceable in federal court.
Reprinted courtesy of
Christopher Olsen, Peckar & Abramson, P.C. and
Phillip Boldt, Peckar & Abramson, P.C.
Mr. Olsen may be contacted at colsen@pecklaw.com
Mr. Boldt may be contacted at pboldt@pecklaw.com
Read the full story...