Colorado Supreme Court Reverses Course on Public Project Liens: Key Takeaways From Wadsworth v. Regional Rail Partners
July 27, 2026 —
Amanda E. McKinlay - Snell & WilmerOn April 6, 2026, the Colorado Supreme Court issued a unanimous opinion in Ralph L. Wadsworth Construction Company, LLC v. Regional Rail Partners, 2026 CO 19, reversing the Colorado Court of Appeals and providing much-needed clarity regarding verified statements of claim (VSOCs) under the Colorado Public Works Act, C.R.S. §§ 38-26-101 et seq. The decision resolves two issues that have generated significant concern among construction industry professionals since the Court of Appeals issued its opinion on August 1, 2024.
Under C.R.S. § 38-26-107(1), a subcontractor on a public works project may file a VSOC with the contracting public entity for amounts due and unpaid for “…furnished labor, materials, sustenance, or other supplies used or consumed by a contractor or his or her subcontractor in or about the performance of the work contracted to be done or that supplies laborers, rental machinery, tools, or equipment to the extent used in the prosecution of the work….” If a claimant files a VSOC for “an amount greater than the amount due” without a reasonable possibility that the amount is due and with knowledge that the claim is excessive, the claimant “shall forfeit all rights to the amount claimed” and becomes liable for the opposing party’s costs and attorneys’ fees. C.R.S. § 38-26-110.
Read the full story...Reprinted courtesy of
Amanda E. McKinlay, Snell & WilmerMs. McKinlay may be contacted at
amckinlay@swlaw.com
A Permitting Base Checklist for Data Centers and Power Plants
June 02, 2026 —
Michael S. McDonough, Stephen J. Humes & Stacey C. Wright - Gravel2Gavel Construction & Real Estate Law BlogThere is a lot of talk these days about “license to operate” for data centers, meaning management of the relationships with stakeholders and broader communities concerning both the benefits and adverse consequences of locating a facility in a particular locale. Here, we are speaking of “license to operate” more literally—namely, the legal and regulatory permitting and approval requirements for a privately owned data center whether by itself or colocated with a power generating plant.
Our Base Checklist includes generally and potentially applicable permitting requirements for development and operation, using California as an example. (Taking legal authority Frank Sinatra out of context, “If you can make it there, you can make it anywhere.”) The actual requirements for a given facility would depend, in part, on local law, including planning and zoning laws and plans, and the environment of the site. Just as examples, additional permitting and mitigation requirements might apply if sensitive receptors are located nearby (e.g., noise mitigation for residential dwellings), if sensitive and protected biological resources (e.g., jurisdictional waters and/or protected species) would be impacted, or if the present or former land uses require additional measures (e.g., hazardous materials remediation, mitigation for conversion of prime farmland, or protection of cultural resources). The scope of permit requirements would ultimately be determined by the applicable regulatory agencies and by the lead and responsible agencies under the applicable state environmental land use regime—in our reference case here, the California Environmental Quality Act (CEQA).
Reprinted courtesy of
Michael S. McDonough, Pillsbury,
Stephen J. Humes, Pillsbury and
Stacey C. Wright, Pillsbury
Mr. McDonough may be contacted at michael.mcdonough@pillsburylaw.com
Mr. Humes may be contacted at stephen.humes@pillsburylaw.com
Ms. Wright may be contacted at stephen.humes@pillsburylaw.com
Read the full story...
Congratulations to Gianna Liddy on Her Promotion to Partner
September 21, 2026 —
Dolores Montoya - Bremer Whyte Brown & O’Meara, LLPBremer Whyte Brown & O’Meara, LLP is proud to announce that Gianna Liddy has been promoted to partner. Gianna’s dedication, leadership, and exceptional contributions to the firm have earned her this well-deserved recognition. Please join us in congratulating her on this exciting achievement!
Meet Gianna Liddy!
Gianna has been with BWB&O since 2019 and has been practicing law since 2017. Her practice focuses on complex civil defense litigation, including high-exposure personal injury, premises liability, transportation, construction defect, habitability, and general liability matters. As a Supervising Attorney in the firm’s Encinitas office, she oversees a team of attorneys, collaborates closely with clients and insurance professionals, and develops litigation strategy in complex matters.
Read the full story...Reprinted courtesy of
Bremer Whyte Brown & O’Meara, LLP
Navigating Timelines and Technology: Patent Strategies for Space and Earth
June 01, 2026 —
Kate Nuehring Su & Vanessa Wang - Engineering News-RecordMore than half a century after the Apollo 11 landing
fulfilled President John F. Kennedy’s bold vision, the global race back to the Moon is no longer theoretical. With renewed attention on NASA’s Artemis program and a surge of commercial investment in space infrastructure, lunar exploration is again shaping technology priorities here on Earth.
Reprinted courtesy of
Kate Nuehring Su, Engineering News-Record and
Vanessa Wang, Engineering News-Record Read the full story...ENR may be contacted at
enr@enr.com
New Florida Law Adds Licensing Risk to Contractor/Subcontractor Payment Disputes
September 29, 2026 —
Brett J. Moritz & Ali Heyat - Peckar & Abramson, P.C.Effective July 1, 2026, Florida’s newly enacted Section 489.1295 of the Florida Statutes, titled “Prohibition Against Nonpayment,” requires licensed contractors to timely compensate subcontractors and suppliers for labor, services, or materials. Enacted as part of Senate Bill 290 (Ch. 2026-3, Laws of Fla.), the statute adds a new basis for instituting disciplinary proceedings against a contractor’s license if a payment is knowingly or willfully withheld.
While this is not a sweeping overhaul of Florida construction payment laws by any means, contractors should be aware that nonpayment disputes with subcontractors and suppliers may carry potential licensing consequences.
Reprinted courtesy of
Brett J. Moritz, Peckar & Abramson, P.C. and
Ali Heyat, Peckar & Abramson, P.C.
Mr. Moritz may be contacted at bmoritz@pecklaw.com
Mr. Heyat may be contacted at aheyat@pecklaw.com
Read the full story...
Executive Insights 2026: Leaders in Construction Law
October 06, 2026 —
Construction ExecutiveWhat advice would you give contractors regarding documentation and recordkeeping to better protect themselves during disputes?
Jim Archibald
Partner
Bradley Arant Boult Cummings LLP
Disputes over payment, scope and delays are among the biggest risks contractors face. Thorough documentation doesn’t just help win these disputes; it may prevent them from happening at all.
Start with the contract: Every project should begin with a written agreement that clearly defines scope, schedule, payment terms and change-order procedures. Verbal understandings are difficult to enforce.
Track changes in real time: Change orders, change directives, RFIs and scope clarifications should always be documented in writing.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
$356 Million Judgement Against Developer for Defective Construction of DC Condominium
August 16, 2026 —
Nicholas D. Cowie - Cowie Law GroupOn July 31, 2026, the Superior Court of the District of Columbia entered a $356,085,513.00 judgment against developers JBG Smith for defective construction and renovation of the Wardman Tower Residential Condominium in Washington, D.C. The case is Wardman Tower Residential Condominium Unit Owners Association v. JBG Smith Properties, et al., No. 2020 CA 004807 B (D.C. Super. Ct.). In a 148-page
Trial Order, the D.C. Superior Court awarded $118,695,171.00 in damages in favor of the condominium association and against the condominium developers, including JBG Smith. The Court trebled those damages pursuant to the District of Columbia Consumer Protection Procedures Act (“CPPA”) to reach an ultimate judgment of $356,085,513.00. See Cowie Law Group:
DC Condominium Construction Defects: Recovering Attorney’s Fees, Litigation Expenses & Treble Damages Under the Consumer Protection Procedures Act.
Cowie Law Group, P.C. filed the lawsuit on behalf of the Association in 2020. The firm represented the Association throughout years of pretrial discovery and ultimately served as trial counsel with Williams & Connolly LLP during a lengthy bench trial before the Honorable Yvonne Williams. The Cowie Law Group team included attorneys, George A. Bealefeld, III, Albert G. McCarraher, Stanford L. Kimmel, III and Nicholas D. Cowie.
Read the full story...Reprinted courtesy of
Nicholas D. Cowie, Cowie Law GroupMr. Cowie may be contacted at
ndc@cowielawgroup.com
Arizona Court Enters $323 Million Judgment Against ZOM Living Following Unanimous Jury Verdict
May 26, 2026 —
Gray Development GroupPHOENIX, May 19, 2026 /PRNewswire/ -- A Maricopa County court has entered a $323 million compensatory damages judgment in favor of Gray Development Group against ZOM Holding Inc., doing business as ZOM Living, following a 12-day trial, a unanimous jury verdict and post-trial proceedings related to a proposed business transaction.
The jury found ZOM liable on claims of breach of contract and breach of the implied covenant of good faith and fair dealing stemming from a proposed joint venture tied to a planned pipeline of luxury multifamily and commercial projects in Phoenix and Scottsdale.
The lawsuit centered on a 13-project, $1.4 billion development pipeline originated and planned by Gray Development Group over more than a decade. In 2019, Gray invited Florida-based ZOM to participate in a joint venture involving the completion of five projects, which would have marked ZOM's entry into the Arizona market.
According to court findings presented at trial, the companies entered into a mutual confidentiality and non-circumvention agreement before Gray shared extensive sensitive and proprietary information related to the projects, including planning, market analysis, costs, financial data, local business relationships and operational strategies developed by Gray over decades in Arizona.
Evidence presented during trial showed that over a 10-month period while under contract, ZOM made hundreds of requests for confidential project and market information before circumventing Gray and pursuing the projects independently, ultimately displacing Gray from projects it spent years planning and developing.
ZOM Living, headquartered in Orlando, develops multifamily and senior housing communities across the United States and operates regional offices in Boston, Dallas, Fort Lauderdale, Nashville, Phoenix, and Raleigh. ZOM is owned by Timeless Investments, the Amsterdam-based family office of Dutch businessman Hans van Veggel, which acquired the company in 1997.
About Gray Development Group
Gray Development Group was founded by architect Bruce Gray in 1991. The Phoenix-based company was the top-ranked multifamily developer in Arizona for more than a decade. The company designed and developed more than 15,000 apartment and condominium units throughout metropolitan Phoenix. Two Gray-designed developments — a Tempe midrise and a San Diego high-rise — received National Apartment Community of the Year awards.