GRSM Secures Illinois Appellate Victory for Architectural Firm in Implied Warranty Dispute
May 14, 2026 —
Gordon Rees Scully MansukhaniGordon Rees Scully Mansukhani Partner Jonathan Federman, Partner Thomas Cronin, and Senior Counsel Garrett Lee recently secured a victory in the Illinois Appellate Court, Fifth District, on behalf of the firm’s client, an architectural firm, in a liability dispute.
The case arose following an entity’s purchase of a 111-unit building for use as an investment or rental property. The plaintiff made claims against the architect of the building, alleging that there were design defects that breached an implied warranty, as well as a negligence claim.
GRSM argued that an architect could not be liable for implied warranties, particularly for an implied warranty which no Illinois court has ever recognized. GRSM further argued that Illinois law bars an architect from liability for negligence arising from a duty pursuant to contract under the economic loss doctrine.
Read the full story...Reprinted courtesy of
Gordon Rees Scully Mansukhani
Builders Support Most of Bipartisan Housing Reform Bill in Congress
March 31, 2026 —
Esther D'Amico - Engineering News-RecordSeveral homebuilding groups say they support most of the massive housing reform bill making its way through Congress but want to see certain provisions including those related to build-to-rent and manufactured homes changed before it advances any further.
Read the full story...Reprinted courtesy of
Esther D'Amico, Engineering News-RecordENR may be contacted at
enr@enr.com
Moving in Before Substantial Completion? The Risks of Early Owner Occupancy
March 24, 2026 —
Sydney Koby - ConsensusDocsIntroduction
On many construction projects, particularly large projects facing schedule pressure, owners may begin occupying or using portions of the project before the work reaches substantial completion. This is often due to operational needs, phased turnover, or market demands that drive owners to take possession of all or part of a project while construction activities are ongoing. While early occupancy may seem practical, it can blur the lines of responsibility between owner and contractor and can create significant legal and practical complications.
These disputes are especially common on large, complex projects where punch list work, system commissioning, and closeout activities overlap with owner use. Without clear documentation and carefully drafted contract provisions, early occupancy can undermine an owner’s ability to enforce completion requirements while simultaneously exposing the contractor to claims of delay, inefficiency, or interference.
Read the full story...Reprinted courtesy of
Sydney Koby, Jones WalkerMs. Koby may be contacted at
skoby@joneswalker.com
Potential Gap in Workers Compensation Immunity Statutory Framework
June 02, 2026 —
David Adelstein - Florida Construction Legal UpdatesWorkers compensation insurance is important. As an owner, you want to ensure the contractors you hire have workers compensation insurance. Assuming you hire a contractor that is statutorily exempt from workers compensation, you want to make sure, no exception, that any subcontractor that is hired has workers compensation insurance. (Regardless, you always want subcontractors to have workers compensation insurance.). In construction, the prime contractor serves as the “
statutory employer” for purposes of workers compensation insurance.
With workers compensation comes
workers compensation immunity.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Colorado Supreme Court Reverses Course on Public Project Liens: Key Takeaways From Wadsworth v. Regional Rail Partners
July 27, 2026 —
Amanda E. McKinlay - Snell & WilmerOn April 6, 2026, the Colorado Supreme Court issued a unanimous opinion in Ralph L. Wadsworth Construction Company, LLC v. Regional Rail Partners, 2026 CO 19, reversing the Colorado Court of Appeals and providing much-needed clarity regarding verified statements of claim (VSOCs) under the Colorado Public Works Act, C.R.S. §§ 38-26-101 et seq. The decision resolves two issues that have generated significant concern among construction industry professionals since the Court of Appeals issued its opinion on August 1, 2024.
Under C.R.S. § 38-26-107(1), a subcontractor on a public works project may file a VSOC with the contracting public entity for amounts due and unpaid for “…furnished labor, materials, sustenance, or other supplies used or consumed by a contractor or his or her subcontractor in or about the performance of the work contracted to be done or that supplies laborers, rental machinery, tools, or equipment to the extent used in the prosecution of the work….” If a claimant files a VSOC for “an amount greater than the amount due” without a reasonable possibility that the amount is due and with knowledge that the claim is excessive, the claimant “shall forfeit all rights to the amount claimed” and becomes liable for the opposing party’s costs and attorneys’ fees. C.R.S. § 38-26-110.
Read the full story...Reprinted courtesy of
Amanda E. McKinlay, Snell & WilmerMs. McKinlay may be contacted at
amckinlay@swlaw.com
White and Williams LLP Attorneys Recognized as PA and DE Super Lawyers
July 06, 2026 —
White and Williams LLPWhite and Williams LLP is proud to announce that eight attorneys in the firm’s Philadelphia office and one attorney in the firm's Delaware Office have been recognized on the 2026 Super Lawyers® and Rising Star lists. This recognition highlights our attorney's exceptional legal acumen and their commitment to client service excellence.
Lawyers are selected for inclusion in Pennsylvania and Delaware Area Super Lawyers® and Rising Stars through a process that considers independent research, peer recognition and the professional achievements of attorneys from more than 70 practice areas. Approximately 2.5% of lawyers in each state are selected by the research team at Super Lawyers® to receive this honor.
Read the full story...Reprinted courtesy of
White and Williams LLP
Navigating the New Frontier of Federal-State Energy Regulation: What Energy Companies Need to Know
June 08, 2026 —
Ryan J. Regula - Snell & WilmerIntroduction
The jurisdictional boundary between the Federal Energy Regulatory Commission (FERC) and the states is being actively contested, from challenges to landmark transmission planning rules to disputes over emergency cost-allocation orders, in ways that carry significant legal, financial, and operational implications for energy companies. For utilities, independent power producers, and transmission developers, understanding these dynamics is now a strategic imperative.
The Jurisdictional Divide: A Bright Line That Isn’t
The Federal Power Act divides authority between FERC and the states: FERC exercises jurisdiction over interstate transmission and wholesale electricity sales, while states retain authority over generation facilities, retail rates, and decisions about resource mix. The D.C. Circuit has regularly been called upon to “referee the Federal Power Act’s jurisdictional line separating [FERC’s] jurisdiction over the federal wholesale market and States’ jurisdiction over facilities used in local distribution.”1
Read the full story...Reprinted courtesy of
Ryan J. Regula, Snell & WilmerMr. Regula may be contacted at
rregula@swlaw.com
Surety Liability Is Coextensive with Its Bond Principal
April 14, 2026 —
David Adelstein - Florida Construction Legal UpdatesA recent Miller act payment bond case, U.S. f/u/b/o Whitetail General Constructors v. Northcon, Inc., 2026 WL 46671 (D.Mont. 2026), contains a short noteworthy discussion as to a surety’s liability being coextensive with that of its bond principal. If you are bonded, or you are pursuing a bond, you need to appreciate this, which is why this is a noteworthy discussion:
A “surety’s liability on a Miller Act bond must be at least coextensive with the obligations imposed by the Act if the bond is to have its intended effect.” “Therefore, ‘the liability of a surety and its principal on a Miller Act payment bond is coextensive with the contractual liability of the principal only to the extent that it is consistent with the rights and obligations created under the Miller Act.’” In other words, “[w]here a subcontract’s terms are consistent with the Miller Act’s provisions, the surety’s liability on the Miller Act bond is coextensive with the contractual liability of its princip[al].”
“The liability of a surety under the Miller Act is controlled by federal law, rather than state contract law[.]” The court may, however, “look to state law when interpreting contractual provisions” in a Miller Act case.
“[T]he measure of recovery under the Miller Act is generally determined by the terms of the subcontract [or underlying contract].”
Northcon, supra, at *4-5 (internal citations omitted).
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com