Contract Disputes Act and Jurisdictional Requirements
March 17, 2026 —
David Adelstein - Florida Construction Legal UpdatesWhen dealing with a claim on a federal construction project, there are a couple of key background jurisdictional points. These points were briefly highlighted in the recent appeal, Mega Star Logistics Service Co. v. Department of State, CBCA 8232, 2026 WL 253738 (CBCA 2026). Here are the two points.
FIRST, when it comes to jurisdiction, for a board of contract appeals âto exercise jurisdiction over a claim, the CDA [Contract Disputes Act] requires the contractor to submit a written claim to the contracting officer for a COFD [contracting officer final decision], with a subsequent appeal of the COFD or deemed denial if the CO [contracting officer] does not issue a COFD.â Thus, you need to submit a formal claim under the Contract Disputes Act to the contracting officer to get a final decision from the contracting officer (or the contracting officer waiving the final decision by not timely furnishing one). Mega Star Logistics, supra.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
A Couple of Mechanicâs Lien Bills in VA [UPDATED]
February 23, 2026 —
Christopher G. Hill - Construction Law MusingsWell, its that time of year again, the Virginia General Assembly is in session and looking to make changes to all kinds of things here in the Commonwealth. While most of those changes are well outside of the subject of Construction Law Musings, changes to the
mechanicâs lien statutes certainly are not. This year, the Virginia General Assembly is poised to make some big changes if certain legislation gets out of committee and passes the legislature, a description and some comments on these follow:
HB752 â Mechanicsâ liens; liens attaching to property; memorandum of lien. [Original Description] Removes the exclusion of the attachment of a mechanicâs lien to property improved or repaired when the lien is based on a claim for repairs or existing structures. The bill further removes (i) the ability of a lien claimant to file any number of memoranda of lien including the details relating to the lien and (ii) the provisions of the Code specifying that no memorandum filed shall include sums due for (a) labor or materials furnished more than 150 days prior to the last day labor was performed or (b) material furnished to the job preceding the filing of such memorandum.
Read the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Daily Journal Publishes Article by Brenda Radmacher on Proposed Overhaul of California Construction Defect Law
June 29, 2026 —
Brenda Radmacher - The Construction SeytDaily Journal (California) featured an article by Construction Law partner
Brenda Radmacher, âA new path for construction defects in California.â The piece, published on June 15, 2026, examines Assembly Bill 1903 and its potential to significantly reshape Californiaâs construction defect framework, particularly for common interest properties.
The article highlights how AB 1903 would overhaul the stateâs current right-to-repair system by mandating completion of prelitigation procedures, raising requirements for defect claims, strengthening developersâ/buildersâ rights to repair, and introducing a voluntary âcertified buildingâ program. The legislation aims to rebalance competing interests by reducing litigation-driven costs while preserving protections for homeowners.
Read the full story...Reprinted courtesy of
Brenda Radmacher, Seyfarth Shaw LLPMs. Radmacher may be contacted at
bradmacher@seyfarth.com
White and Williams LLP is Proud to Host the 20th Anniversary Virginia Barton Wallace Award and Reception
May 05, 2026 —
White and Williams LLPWhite and Williams LLP is proud to host the 20th Anniversary Virginia Barton Wallace (VBW) Award and Reception, which will celebrate this yearâs honoree,
The Rendell Center for Civics & Civic Engagement. This award was created to celebrate the remarkable career of Virginia âGinnyâ Barton Wallace, the first woman to be elected to partnership not only at White and Williams but also at any law firm in Philadelphia. The VBW Award is presented to a woman or organization that embodies the same qualities that Ginny possessed: leadership, drive, exemplary work ethic, overall excellence in her field, or an ability to inspire other women to succeed.
Read the full story...Reprinted courtesy of
White and Williams LLP
Construction Seyt Named a Top Construction Blog by FeedSpot
March 31, 2026 —
Seyfarth Shaw LLP - The Construction SeytSince 2019, we have strived to bring our readers practical, useful insights on recent trends shaping our industry. Whether you are a contractor, designer, developer, attorney, or industry professional, our goal is to equip you with the knowledge to navigate your business with that much more confidence. We are honored that âThe Construction Seytâ has been named by FeedSpot as a âBest Construction Blogâ to follow for 2026.
Read the full story...Reprinted courtesy of
Seyfarth Shaw LLP
Bona Fide Dispute Defeats Violation of Prompt Payment Act
June 15, 2026 —
David Adelstein - Florida Construction Legal UpdatesMost, if not all, jurisdictions, including the federal government, have what is known as a âPrompt Payment Act.â The objective is to ensure prompt payment. If prompt payment is not made, the Prompt Payment Act provides for interest penalties, as well as potentially other costs such as attorneyâs fees.
But the thing is, itâs not as simple as untimely payment to support the recourse and interest penalties the applicable Prompt Payment Act affords. And the teeth associated with the applicable Prompt Payment Act are not as sharp as perhaps the party claiming untimely payment prefers.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Real Estate & Construction News Roundup (3/18/25) â Data Center Frenzy, Chinaâs Expanding REIT Market and Tariff-Affected Construction Costs
March 31, 2026 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, relistings reached highest total in a decade, Florida State Legislature passes bill to increase the stateâs housing supply, data center construction adapts to changes and more!
- The data center construction frenzy and a new, potentially larger highway bill were top of mind for builders during the latest round of contractor earnings calls and financial reports. (Joe Bousquin, Construction Dive)
- Tariffs and associated policy uncertainty have increased construction costs and delayed leasing and investment choices. (J.P. Morgan)
- Relistings hit the highest January figure since Redfin began tracking this metric a decade ago. (Diana Olick, CNBC).
Read the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Managing Rising Costs and Shifting Legal Risk for Florida High-Rise and Condominium Projects
May 05, 2026 —
Stephen Hauptman - Ball Janik LLPFlorida's construction defect landscape is experiencing a major shift. The convergence of material and labor cost volatility, regulatory tightening, and increasingly complex litigation strategies is forcing associations, developers, and their counsel to rethink how they approach risk management and dispute resolution. For those managing large-scale condo and high-rise projects, the stakes have never been higher.
The Cost Volatility Trap
Construction material prices rose at a "staggering" 12.6% annualized rate during the first two months of 2026, according to
recent industry analysis. Tariff impacts are projected to lead to more increases of 5.4% to 6.8%, depending on property type. For associations facing construction defect claims, this volatility creates a cascading problem: repair scopes defined two years ago are now dramatically underpriced, and damage calculations that appeared reasonable at discovery are obsolete by the time of settlement.
Courts and mediators are increasingly scrutinizing how cost estimates were developed and whether they account for existing market circumstances. Associations must now commission updated repair assessments more frequently, a practice that increases investigation costs but strengthens the credibility of damage claims. Conversely, defendants are weaponizing cost inflation as a defense, arguing that claimed damages are speculative or inflated. The practical result: repair sequencing and phasing strategies have become critical litigation tools. Associations that can demonstrate a rational, cost-effective repair plan tied to current market data are more favorably placed in settlement negotiations.
Regulatory Pressure and Deliberate Timing
Florida's 2026 condo compliance regime has significantly changed the defect claims landscape. Elevated transparency requirements, stricter reserve funding mandates, and tightened building safety inspection protocols mean that associations now face dual pressures: Comply with new regulations while simultaneously handling construction defect exposure.
This regulatory environment is changing investigation and documentation strategy. Associations that delay defect investigation to avoid triggering reserve funding obligations or disclosure requirements are taking on considerable legal risk. Recent case law such as the Third District Court of Appeal's reaffirmation of Chapter 558's pre-suit mediation requirements, underscores Florida's intent to resolve disputes early. Associations that move deliberately and record carefully during the pre-suit phase gain leverage in mediation and reduce the risk of expensive litigation.
Timing also intersects with repair sequencing. Associations must now balance the urgency of compliance inspections against the strategic advantage of phased repairs. Some associations are using compliance deadlines as a forcing mechanism to accelerate settlement discussions, while others are sequencing repairs to demonstrate good-faith remediation efforts before litigation commences.
The Emerging Risk Transfer Challenge
As construction defect claims grow more complex and costly, the traditional risk transfer systems, such as design-build warranties, contractor bonds, and insurance, are proving inadequate. Developers and general contractors are increasingly shifting risk to subcontractors and material suppliers, fragmenting liability and complicating recovery efforts for associations. Permitting and approval friction is also creating new litigation pressure points. Delays in municipal approvals, changes to building code interpretations, and disputes over remedial work compliance continue to spawn collateral claims that go beyond the original defect. Associations must now anticipate not only defect liability but also regulatory compliance disputes with municipalities, creating a dual-front legal challenge.
For large communities, this means reconsidering the entire risk architecture. Insurance carriers are tightening coverage, and traditional indemnification chains are breaking down. Forward-thinking associations are engaging counsel earlier in the development process to negotiate clearer risk allocation provisions and more robust insurance requirements.
Taking a Data-Driven Approach
Managing rising costs and shifting legal risk in Florida's high-rise and condo market requires a more sophisticated, data-driven approach. Associations must commission frequent cost updates, move deliberately through pre-suit investigation and mediation, and challenge traditional assumptions about risk transfer. Developers and their counsel should view regulatory compliance not as a burden but as an opportunity to demonstrate good-faith risk management and strengthen settlement positioning.
The firms and associations that succeed in 2026 will be those that treat cost volatility, regulatory change, and litigation strategy not as separate challenges but as linked elements of a coherent risk management framework.
Stephen Hauptman is special counsel in Ball Janik LLPâs Fort Lauderdale office. He may be reached at shauptman@balljanik.com.