ASCE Releases New Report on Benefits and Burdens of Infrastructure Investment in Disadvantaged Communities
February 05, 2024 —
The American Society of Civil EngineersWashington — The
American Society of Civil Engineers today released a new paper, Measuring the Benefits and Burdens of Infrastructure in Disadvantaged Communities. The report looks at how several communities across the country consider equity when investing infrastructure funds, and the impact of those projects on lower-income communities.
"Civil engineers are focused on improving quality of life by building systems that improve the public's health, safety, and well-being," said Marsia Geldert-Murphey, P.E., 2024 President, ASCE. "However, the decisions on how and where infrastructure is built can affect communities for decades after a project is complete. By looking at the benefits and burdens of past projects, infrastructure owners and developers can find better ways to consider the impact of infrastructure projects being designed now."
Some of the recommendations in the paper include encouraging government and other infrastructure stakeholders to use community engagement and transparent metrics when making decisions about proposed infrastructure investments. It also encourages post-project assessments and the use of existing resources to evaluate the positive and unexpected consequences of past infrastructure projects.
Measuring the Benefits and Burdens of Infrastructure in Disadvantaged Communities is
available here.
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 150,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
The Word “Estimate” in a Contract Matters as to a Completion Date
February 12, 2024 —
David Adelstein - Florida Construction Legal UpdatesLanguage in a contract matters. The word “estimates” or “estimated” matters particularly when it comes to a date certain such as a substantial completion or completion date. Remember this.
Here is an example.
In Parque Towers Developers, LLC v. Pilac Management, Ltd., 49 Fla.L.Weekly D190a (Fla. 3d DCA 2024), a trial court held that the developer did not complete the construction of five condominium units by the date in the purchase agreements. The developer appealed because “[t]he agreements contain no date certain for the completion of the units, but rather include a clause that ‘Seller estimates it will substantially complete construction of the Unit, in the manner specified in this Agreement, by December 31, 2017, subject to extensions resulting from ‘Force Majeure (the ‘Outside Date’).’” Parque Towers, supra. Another provision in the purchase agreements stated, “[w]henver this Agreement requires Seller to complete or substantially complete any item of construction, that item will be understood to be complete or substantially complete when so completed or substantially completed in Seller’s opinion. Id.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Court of Appeals Confirms that King County Superior Court’s Jury Selection Process Satisfies Due Process Requirements
December 04, 2023 —
Joshua Lane - Ahlers Cressman & Sleight PLLCRaymond Budd developed mesothelioma after working with a drywall product called “joint compound” from 1962 to 1972. He sued Kaiser Gypsum Company, Inc. and others for damages, contending that the company’s joint compound caused his illness. A jury returned a verdict in Budd’s favor and awarded him nearly $13.5 million. Kaiser appealed, claiming (1) insufficient randomness in the jury-selection process, (2) erroneous transcription of expert testimony, (3) lack of proximate causation, (4) lack of medical causation, (5) an improper jury instruction on defective design, (6) improper exclusion of sexual battery and marital discord evidence, (7) improper admission of post-exposure evidence, (8) improper exclusion of regulatory provisions, and (9) a failure to link its product to Budd’s disease. The Court of Appeals, Division 1, affirmed the verdict in favor of Budd.
Though all of the nine bases for error raised by Kaiser merit discussion, the jury-selection process issue is most probative here. Kaiser made three challenges against the jury selection process.
Read the full story...Reprinted courtesy of
Joshua Lane, Ahlers Cressman & Sleight PLLCMr. Lane may be contacted at
joshua.lane@acslawyers.com
National Engineering and Public Works Roadshow Highlights Low Battery Seawall Restoration Project in Charleston
April 29, 2024 —
Engineering and Public Works RoadshowCHARLESTON, SC — On Thursday, the nationwide Engineering and Public Works Roadshow stopped at the Low Battery Seawall Restoration Project in Charleston. The event highlighted the role engineers and public works professionals play in infrastructure projects like the local seawall improvements that increase coastal resiliency along the historic urban shoreline.
The event, which took place along the newly constructed battery wall section between King Street and Battery Place along Murray Boulevard, marked the latest stop of the Engineering and Public Works Roadshow – a joint effort by the American Council of Engineering Companies, the American Public Works Association, and the American Society of Civil Engineers to bring public attention to the essential role engineers and public works professionals play in making our modern world possible.
The battery project underscores the importance of innovative engineering solutions in addressing the challenges of climate change and rising sea levels. Thursday's event was also a chance to spotlight the engineering, construction, and public officials involved in the project, whose work often goes unrecognized.
About the Engineering and Public Works Roadshow: The Engineering and Public Works Roadshow is a series of nationwide events highlighting critical infrastructure projects and the skilled professionals who make them possible. It is an opportunity to learn about the importance of infrastructure investment, showcase the work of engineers and public works professionals, and celebrate these projects' positive impact on our communities. Learn more at www.infrastructureroadshow.org.
No Coverage for Roof Collapse During Hurricane
January 29, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Fifth Circuit affirmed the district court's determination that the insured's roof collapse was not covered. Exclusive Real Estate Inv., L.L.C. v. S.G.L. No. 1, Ltd., 2023 U.S. App. LEXIS 29368 (5th Cir. Nov. 3, 2023).
A building owned by Exclusive Real Estate partially collapsed during a rain-storm. The insurer, SGL, inspected the roof and determined that there was no coverage. Exclusive sued SGL for breach of contract and bad faith. SGL moved for summary judgment, which was granted by the district court. Exclusive appealed.
The poicy covered "direct physical loss to the property" caused by windstorms. Exclusions, however, precluded coverage for losses "caused by rain, snow, sleet, sand or dust unless the direct force of wind or hail damages the building causing an opening in a roof or wall and the rain, snow, sleet, sand or dust enters through this opening."
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Competent, Substantial Evidence Carries Day in Bench Trial
February 26, 2024 —
David Adelstein - Florida Construction Legal UpdatesA number of construction disputes, if tried, are tried through a bench trial meaning the judge is serving in the role of the jury in the construction trial. In a bench trial, two points are important. First, “the factual findings of the judge are entitled to the weight of a jury verdict.” Q.G.S. Development, Inc. v. National Lining Systems, Inc., 2024 WL 357984 (Fla. 3d DCA 2024) (internal quotation and citation omitted). Second, “[t]he appellate court is only authorized to reverse if such findings are not supported by competent, substantial evidence.” Id. These two points need to be appreciated when participating in any construction dispute that will be resolved through a bench trial.
A recent construction dispute highlights these two points. In Q.G.S. Development, a contractor was hired to refurbish a golf course which included constructing a lake. The contractor was going to construct the lake, prepare the subgrade, perform dewatering, and it hired a subcontractor to install a reservoir liner at the bottom of the lake.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Cyber Thieves Phish Away a $735K Payment to a Minnesota Contractor
May 06, 2024 —
Richard Korman - Engineering News-RecordThe contractor's project manager asked for money due, $735,000 under Payment Application 13, to be sent by the owner electronically. "Hi Rick," the project manager, whose first name is Jalen, wrote in an email dated Aug. 15. "Can we have payments remitted electronically as we currently have numerous uncleared checks on hold?"
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story...
Navigating the Construction Burrito: OCIP Policies in California’s Construction Defect Cases
November 16, 2023 —
Alexa Stephenson & Ivette Kincaid - Kahana FeldIn the early 2000’s, Owner-Controlled Insurance Programs (OCIP) or WRAPS, were traditionally used in large commercial projects of over $50 million in construction costs. As construction defect lawsuits became more prevalent, subcontractors found themselves unable to meet the insurance requirements of their contracts with developers and general contractors because they could not find insurance companies that were willing to insure the risk. This presented a problem for developers and general contractors and left them with no option but to look into new insurance products that would insure them and all subcontractors who worked on the project. OCIPs became in some instances the only insurance option for developers, general contractors, and subcontractors to build single-family or multi-family projects in California and other western states.
OCIPS or WRAPS, often likened to the layers of a savory burrito, offer both enticing benefits and potential pitfalls. Just as a burrito’s ingredients can harmonize or clash, OCIP policies can shape the outcome of legal battles, impacting contractors, developers, and insurers alike.
Pros – Savoring the OCIP Burrito:
1. Wrapped Protection: Much like a well-folded burrito envelops its contents, OCIP policies offer comprehensive coverage for construction projects. Developers, general contractors, and subcontractors find comfort in knowing that their liability risks are bundled into a single policy, ensuring all enrolled parties have coverage in the event of a claim.
Reprinted courtesy of
Alexa Stephenson, Kahana Feld and
Ivette Kincaid, Kahana Feld
Ms. Stephenson may be contacted at astephenson@kahanafeld.com
Ms. Kincaid may be contacted at ikincaid@kahanafeld.com
Read the full story...