Competent, Substantial Evidence Carries Day in Bench Trial
February 26, 2024 —
David Adelstein - Florida Construction Legal UpdatesA number of construction disputes, if tried, are tried through a bench trial meaning the judge is serving in the role of the jury in the construction trial. In a bench trial, two points are important. First, “the factual findings of the judge are entitled to the weight of a jury verdict.” Q.G.S. Development, Inc. v. National Lining Systems, Inc., 2024 WL 357984 (Fla. 3d DCA 2024) (internal quotation and citation omitted). Second, “[t]he appellate court is only authorized to reverse if such findings are not supported by competent, substantial evidence.” Id. These two points need to be appreciated when participating in any construction dispute that will be resolved t
Insurer Wrongfully Denies Coverage When Household Member Fails to Submit to EUO
May 06, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe court determined that coverage for a loss by fire could not be denied when the insured's son failed to appear for a examination under oath (EUO). Adekola v. Allstate Vehicle & Prop. Ins. Co., 2024 U.S. Dist. LEXIS 27125 (E.D. Pa. Feb. 16, 2024).
Plaintiff had a homeowners policy with Allstate. Plaintiff - Michele Adekola - was the named insured under the policy. After the fire, Allstate provided payments for temporary housing. Allstate requested examinations under oath of Plaintiff and her son, Nico. Plaintiff and her son were examined by Zoom. Allstate then sought to examine Plaintiff's other son, Lemmeco, but these effort
The (Jurisdictional) Rebranding of The CDA’s Sum Certain Requirement
April 15, 2024 —
Jordan A. Hutcheson and Stephanie Rolfsness - Watt TiederThe Contract Disputes Act (the “CDA”), 41 U.S.C.A. §§ 7101 et seq., which has provided the statutory framework for resolution of most contract disputes between the federal government and its contractors since 1978, has recently been the subject of changes in judicial interpretation, despite no corresponding statutory changes. The CDA’s implementing provisions in the Federal Acquisition Regulations (FAR), require that contractors submit a claim to the government in the form of written demand to a contracting officer requesting a final decision and seeking the payment of money in a sum certain prior to pursui
Perez Broke Records … But Should He Have Settled Earlier?
February 19, 2024 —
Sofya Uvaydov & John F. Watkins - Kahana FeldIn 2021, Mark Perez’ Labor Law 240(1) lawsuit made legal news by breaking the record of the highest appellate-sustained pain and suffering award in New York history. While that record was short-lived, it still maintains its place as New York’s highest-ever pain and suffering award for a brain injury. This January 17th, the Appellate Division, First Department revisited the litigation but, this time, in a dispute between Perez and his then-lawyer, Ben Morelli and the Morelli Law Firm. Mr. Perez claims breach of contract over a 10% additional contingency fee charge related to the Perez v. Live Nation appeal and breach of fiduciary duty by his counsel in failing to convey settlement offers during the lifetime of the case. The Morelli firm counters, among other things, that the prior settlement offers – a $30 million offer during the 2019 trial and intermediate sums during the appellate stage – were still lower than the ultimate $55 million settlement. No harm, Mr. Morelli argues, and thus no foul in failing to convey the of
American Arbitration Association Revises Construction Industry Rules and Mediation Procedures
April 08, 2024 —
Dennis Cavanaugh & Larry Grijalva - Construction Law ZoneThe American Arbitration Association (AAA), one of the longest-standing and experienced alternative dispute resolution (ADR) administrators, has unveiled a significant update to its Construction Industry Rules and Mediation procedures. This update, last revised in 2015, became effective March 1, 2024. Changes to the AAA Construction Industry Rules are significant as these rules are incorporated by default in American Institute of Architects standard construction forms, which are widely used in the industry.
Advancements in remote access technology drive a substantial number of new changes. Others are designed to streamline the arbitrator appointment process
Traub Lieberman Attorneys Lisa M. Rolle, Eric D. Suben, and Justyn Verzillo Secure Dismissal of All Claims in a Premises Liability Case
November 16, 2023 —
Lisa M. Rolle, Eric D. Suben & Justyn Verzillo - Traub LiebermanOn an appeal of an order denying Defendant’s motion to dismiss the complaint in a slip-and-fall action commenced in Kings County Supreme Court, Traub Lieberman attorneys Lisa M. Rolle, Eric D. Suben, and Justyn Verzillo successfully secured dismissal of all claims by the Appellate Division, Second Department, on behalf of Traub Lieberman’s client.
The lawsuit sought to recover damages arising out of injuries the Plaintiff allegedly sustained when she slipped and fell in the shower of a rental property owned by the Defendant, a limited liability company. Plaintiff alleged that the subject shower was defective, and the Defendant negligent, based on the absence of non-slip surfa
The Johnstown Dam Failure, as Seen in the Pages of ENR in 1889
April 08, 2024 —
Scott Lewis - Engineering News-RecordThe small headline of the Engineering News article shown here belies the gravity of the disaster: the deadliest dam failure in U.S. history. The South Fork Dam in Pennsylvania was a 72-ft-tall, 931-ft long earth and rockfill structure. After a stop-and-start construction process over a dozen years, it was completed in 1853. The dam went through several changes of ownership and was repaired inadequately. Fish screens were installed that obstructed the spillway and caused water to overtop and erode the structure. This mass of water uprooted trees, rocks, houses, rail cars and animals as it thundered down the valley before smashing into a stone railway embankment. Fires ignited by wrecked locomotives burned for three days. The death toll was 2,208.
Reprinted courtesy of
Scott Lewis, Engineering News-Record
Mr. Lewis may be contacted at lewisw@enr.com
Read the full story...
Be Sure to Bring Up Any Mechanic’s Lien Defenses Early and Often
November 27, 2023 —
Christopher G. Hill - Construction Law MusingsAs those of you who regularly read Musings are aware, mechanic’s liens are a big part of my law practice and a big issue here at this construction law blog. I’ve discussed the picky requirements of the mechanic’s lien statutes in Virginia and how the 90 and 150-day rules are strictly enforced. However, a recent case out of the City of Norfolk Virginia Circuit Court cautions that while failure to meet these strict requirements may invalidate a lien, it only does so if the owner or general contractor seeking to invalidate the lien argues the invalidity and/or presents evidence of that invalidity either pretrial or during trial.
In Premier Restoration LLC v. Barnes, the Court considered the following facts. The defendant homeowners had a house fire and the resulting damage was the subject of an insurance claim that was paid and checks sent to the homeowners. Premier filed a mechanic’s lien in response to Barnes’s failure to pay for Premier’s restoration construction services after Barnes’s home was destroyed by fire. Premier seeks a decree to enforce the lien, asking the court to order the sale of Barnes’s property to recover its damages or, alternatively, a judgment in its favor. With the Complaint seeking enforcement of the lien and damages for breach of contract, and this is a key point, Premier provided a copy of the mechanic’s lien along with the affidavit that is part of the statutory form swearing that the Owner was justly indebted to Premiere. The homeowners filed a counterclaim for unfinished work, including unfinished punch list work. After a trial during which no evidence regarding either the timeliness of the lien recording or whether any of the work sought to be encompassed in the lien was performed outside of the statutory 150-day window was presented by either side, the defendants filed a post-trial motion seeking to invalidate the lien as including sums for work outside of the 150-day window.
Read the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill ma
Repairs to Hurricane-damaged Sanibel Causeway Completed in 105 Days
February 12, 2024 —
Marigo Farr - EngineeTop 10 Insurance Cases of 2023
January 29, 2024 — Jeffrey J. Vita & Michael A. Amato - Saxe Doernberger & Vita, P.C.
Federal and state courts tackled many interesting insurance-related issues this past year. Perhaps no state had a more impactful year than Illinois, which held that construction defects could constitute an occurrence, that a LEG 3 “extension” attempting to preclude coverage for faulty or defective workmanship was ambiguous as a matter of law (applying Illinois law), and that ostensibly prohibitive “catch-all exclusions” can render policy language ambiguous in favor of coverage. Other courts wrestled with procedural inquiries, such as the legal duty of a broker in providing notice to an insurer or the ability of an insured to recoup its attorneys’ fees in pursuinIs Modular Construction Destined to Fail?
March 11, 2024 — Aarni Heiskanen - AEC Business
The construction sector is a harsh environment for innovation. I’ve been following the story of one Finnish innovative contractor, Lehto Group, over the years with enthusiasm. I was saddened to hear that the group’s three significant subsidiaries joined the ranks of many Finnish contractors who have filed for bankruptcy over the last six months.
Lehto developed industrialized building concepts and had its own production facilities. The company had a promising start but eventually ran into problems. Was the industrial approach a mistake, or were other factors contributing to the firm’s fall?
Three Contributing Factors
Lehto Group’s collapse was not a surprise to its competitors, who had observed warning signs years prior. The company’s order book plummeted in 2024 despite still employing around 500 workers. Rakennuslehti, the leading construction magazine in Finland, asked three expConstruction Contract Basics: No Damages for Delay
May 06, 2024 — Christopher G. Hill - Construction Law Musings
After WAY too long a hiatus, I am back with another in my series of “Construction Contract Basics” posts. In past posts, I’ve covered venue provisions, attorney fee provisions, and indemnity clauses. In this post, I’ll share a few thoughts (or “musings”) on the topic of so-called “no damages for delay” clauses. These clauses essentially state that a subcontractor’s only remedy for a delay caused by any factor beyond its control 9th Circuit Plumbs Through the Federal and State False Claims Acts
January 16, 2024 — Garret Murai - California Construction Law Blog
You may have heard of the False Claims Act and know that it penalizes companies and individuals in contract with the government who present false claims. The federal False Claims Act was signed into law by President Abraham Lincoln in 1863 to penalize profiteers during the Civil War who were selling the Union Army moth eaten blankets, boxes of sawdust instead of guns, and sometimes re-selling the Army calvary horses several times over. Since then, many states, including California, as well as municipalities, have enacted their own false claim statutes.
As currently written, the federal False Claims Act provides for statutory penalties against any person who:
- “[K]nowingly presents, or causes to be presented, a false or fraudulent claim for payment or approval”;
- “[K]nowingly makes, uses or causes to be made or used, a false record or statement material to a false or fraudulent claim”;
- “[H]as possession, custody, or control of property or money used, or to be used, by the Government an knowingly delivers, or causes to be delivered, less th
Sarah P. Long Expands Insurance Coverage Team at Payne & Fears
March 19, 2024 — Payne & Fears LLP
Sarah P. Long has joined Payne & Fears LLP as a Partner in the firm’s Insurance Coverage and Litigation Group. Sarah has represented clients in all aspects of insurance coverage and litigation and also focus on construction defect claims and litigation.
Before joining Payne & Fears, Sarah was a partner at Koeller, Nebe