Fatalities Edge Down: New Data Reveals a Promising Decline
April 27, 2026 —
Construction ExecutiveConstruction fatalities in the United States declined slightly in 2024, according to
new data released from the U.S. Bureau of Labor Statistics. The sector recorded just over 1,000 worker deaths last year—a modest decrease from the previous year but still among the highest totals of any industry.
Falls remained the leading cause of death, accounting for roughly one-third of all construction fatalities. Transportation incidents—including workers struck by vehicles or equipment—ranked second, followed by contact with objects or equipment and electrocutions.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Are “Financial Hardship” Damages Recoverable?
June 08, 2026 —
David Adelstein - Florida Construction Legal UpdatesIn a case out of the Civilian Board of Contract Appeals, F.O.G., LLC v. Department of the Interior, CBCA 8203, 2026 WL 1191881 (CBCA 2026) a contractor claimed damages that included “financial hardship” damages due to slow payments. The financial hardship damages included personal damages to the contractor’s president and his wife. Are these damages recoverable? Drumroll…The Board ruled that the contractor cannot recover such financial hardship damages.
As it relates the personal financial hardship damages, the Board ruled, “Neither [the contractor’s] president nor his wife are a party to this contract, are in privity of contract with [the government], or are the beneficiaries under this contract. [The contractor], therefore, cannot recover for any losses that either one has suffered individually and that [the contractor] claimed in this appeal.” F.O.G., LLC, supra.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
We’re Burning Tokens to Clean Up Bad PDFs
August 24, 2026 —
Aarni Heiskanen - AEC BusinessLast Thursday, researchers from Tampere and Aalto universities reported on preliminary results of two AI- and digitalization-related projects. One project demonstrated how AI can automate the Bill of Materials process; the other tried to quantify the impact of data-driven construction and AI. The conclusion was that AI-powered automation can dramatically increase productivity, but unevenly. However, the substantial benefits may come from better outcomes rather than project efficiency.
Various standards, company-specific practices, project-specific schemas, and traditions are designed for humans to comprehend. 2D drawings and text documents as PDF files, Excel sheets, and design and planning software have the information, but not the data in ideal form for automation.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Massachusetts Construction Industry Continues to Wait While Prompt Payment Law Is Put to the Test
March 31, 2026 —
Catherine Maronski - Construction Law ZoneEarlier this month, the Massachusetts Supreme Judicial Court (SJC) heard argument in J.C. Cannistraro, LLC v. Columbia Construction Co. et al., a dispute concerning the state’s Prompt Payment Act (PPA). Although a decision has yet to be issued, it could potentially pose widespread implications for high-value private construction projects moving forward – and perhaps backwards.
The PPA, G. L. c. 149, § 29E, enacted by the Massachusetts Legislature in 2010, has become a keystone in the construction industry. It was enacted to address, in part, downstream cash flow issues that tend to pervade construction projects by mandating a series of strict guidelines for submitting, and responding to, payment applications for private projects valued over $3,000,000. Amongst these requirements are set timeframes to respond to an application, as well as what must be contained in an application rejection. Critically, if an owner or upper-tier contractor fails to fully comply with all the statutory requirements in response to a proper payment application, the application is automatically “deemed to be approved” and payable. Significantly, however, this is not always the end of the line.
Read the full story...Reprinted courtesy of
Catherine Maronski, Robinson ColeMs. Maronski may be contacted at
cmaronski@rc.com
Surety Liability Is Coextensive with Its Bond Principal
April 14, 2026 —
David Adelstein - Florida Construction Legal UpdatesA recent Miller act payment bond case, U.S. f/u/b/o Whitetail General Constructors v. Northcon, Inc., 2026 WL 46671 (D.Mont. 2026), contains a short noteworthy discussion as to a surety’s liability being coextensive with that of its bond principal. If you are bonded, or you are pursuing a bond, you need to appreciate this, which is why this is a noteworthy discussion:
A “surety’s liability on a Miller Act bond must be at least coextensive with the obligations imposed by the Act if the bond is to have its intended effect.” “Therefore, ‘the liability of a surety and its principal on a Miller Act payment bond is coextensive with the contractual liability of the principal only to the extent that it is consistent with the rights and obligations created under the Miller Act.’” In other words, “[w]here a subcontract’s terms are consistent with the Miller Act’s provisions, the surety’s liability on the Miller Act bond is coextensive with the contractual liability of its princip[al].”
“The liability of a surety under the Miller Act is controlled by federal law, rather than state contract law[.]” The court may, however, “look to state law when interpreting contractual provisions” in a Miller Act case.
“[T]he measure of recovery under the Miller Act is generally determined by the terms of the subcontract [or underlying contract].”
Northcon, supra, at *4-5 (internal citations omitted).
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Data Center Construction and the AEC Partner of the Future
April 14, 2026 —
Aarni Heiskanen - AEC BusinessDuring my involvement in designing mobile phone production facilities, the speed of design and construction was critical. Any delay could directly translate into lost revenue. That same logic now applies to data centers, though the stakes are much higher. Instead of optimizing physical production lines, we are constructing infrastructure for digital production.
The global data center capacity is expected to nearly double by 2030, and with this level of demand, the traditional project-by-project delivery model begins to show its limitations.
Data centers are no longer isolated projects in the traditional sense. They are evolving into repeatable, scalable production systems, making them ideal environments for AEC process and business model innovation.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Seattle’s Residential Zoning Transformation: What Property Owners, Buyers, and Investors Should Understand
May 14, 2026 —
Lawrence S. Glosser - Ahlers Cressman & Sleight PLLCSeattle is in the midst of a significant transformation in residential land use policy. Longstanding neighborhood zoning patterns that historically favored detached single-family development are being reexamined in response to housing supply pressures, affordability concerns, and evolving state mandates.
For homeowners, purchasers, investors, and builders, these changes may create substantial new opportunities. They also create a heightened need for careful legal and practical due diligence.
While zoning reform can expand potential uses of property, it does not eliminate the many other constraints that may still govern what can actually be built.
Read the full story...Reprinted courtesy of
Lawrence S. Glosser, Ahlers Cressman & Sleight PLLCMr. Glosser may be contacted at
larry.glosser@acslawyers.com
Surety Requiring Collateral Security Under General Agreement of Indemnity
September 08, 2026 —
David Adelstein - Florida Construction Legal UpdatesIn order to procure bonds (payment and performance bonds), you need to sign a General Agreement of Indemnity (referred to as the “GAI”) with the surety (bonding company). It does not matter the surety issuing the bonds, the terms and conditions in the General Agreement of Indemnity are largely consistent. These terms and conditions are one-sided written in favor of the surety. This is because bonds are not insurance. When a surety issues such bonds, it is doing so under the premise that it will get reimbursed every penny that it incurs relative to its exposure- whether incurred in attorney’s fees, consulting costs, or remediating a default or claim under the applicable bond. The General Agreement of Indemnity is one of the most powerful contracts in construction and is a contract that is not to be taken lightly. It provides the surety numerous rights in the event of a claim.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com