Supply Chain Is a Legal Exposure—Not Just a Force Majeure Problem
September 08, 2026 —
Owen Newman - Construction ExecutiveThis is not another force majeure article. The supply-chain related legal exposure that contractors are carrying today—in sanctions risk, specification non-compliance, warranty exposure and regulatory volatility—extends well beyond what even a well-drafted force majeure clause protects.
An engineering, procurement and construction contractor on a gas-fired power plant discovers during commissioning that transformer oil in a critical unit contains Russian-origin naphthenic base oil, which is a prohibited source under Office of Foreign Assets Control sanctions. The contractor didn’t source it. A subsupplier two tiers below made the substitution when disruptions in the Strait of Hormuz tightened the primary supply chain for this specialty product and no one in the purchase-order chain flagged it. The procurement decision is long done and the documentation trail that should have caught it doesn’t exist.
Reprinted courtesy of
Owen Newman, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...Mr. Newman may be contacted at
oknewman@duanemorris.com
Every High-Tech Building Has Many Lifespans
August 16, 2026 —
Aarni Heiskanen - AEC BusinessWhen I worked as an architect, our team designed a laboratory for fuel research. The facility included a large research hall where various boilers and other devices were tested and analyzed. The setup required extensive floor channeling under the thick concrete floor. We suggested building a modular system that would allow flexibility in the future, when requirements would certainly change. They did not want that because of budget constraints.
The high-tech construction trend is spreading. Data centers, semiconductor fabs, battery plants, and life science facilities share one property that sets them apart from ordinary buildings. The technology inside turns over faster than the structure around it. Server generations change every three to five years. Rack densities have risen from 10 or 20 kW to 130 kW and beyond in just a few years.
A high-tech facility is really several buildings with different lifespans inside one envelope, and we keep designing them as if they were one. The failure is not that things become obsolete. It is that we never say when each layer is expected to.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
No Bad Faith Despite Insurer’s Appraisal Award Exceeding Initial Payment
August 03, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court granted the insurer’s motion for summary judgment, finding no bad faith despite the appraisal award exceeding the amount the insurer initially paid. Jazi Kat 4659 Rockridge LLC, et al. v. Travelers Cas. Ins. Co. of Am., et al., 2026 U.S. Dist. LEXIS 105634 (D. Ariz. May 13, 2026).
Plaintiffs sued Travelers for breach of contract and bad faith, alleging that Travelers failed to pay money plaintiffs were owed under the policy. Plaintiffs held a commercial property policy for two properties. A fire destroyed one of the properties. Travelers adjusted the claim and issued two payments. Plaintiffs disagreed with the amount of the payments and demanded an appraisal. Travelers agreed to the appraisal.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
PJM’s Reliability Backstop Procurement Proposal—Fast-Track Capacity to Meet Rising Large-Load Demand
May 12, 2026 —
Stephen J. Humes, Alicia M. McKnight, Jason Drogin Atwood & Andrew H. Jacobs - Gravel2GavelIn January, we discussed the Statement of Principles jointly signed by the National Energy Dominance Council and governors across the mid-Atlantic region—framing accelerating demand (especially from large-scale data centers) as an emergency reliability issue for PJM Interconnection, L.L.C. (PJM), the nation’s largest power grid operator. That policy signal is now becoming a near-term, accelerated procurement and contracting exercise. On April 8, 2026, PJM notified stakeholders of a critical issue fast path reliability backstop procurement process. PJM subsequently released a request for information (RFI) with respect to a proposed Reliability Backstop Procurement (RBP)—a one-time mechanism intended to attract significant new capacity to address projected reliability shortfalls driven by large-load growth.
RBP compresses what is often a multiyear market and regulatory conversation into a fast-moving set of commercial choices. Developers, large loads, utilities and capital providers should be preparing now for (i) an accelerated bilateral contracting window and (ii) a standardized PJM-led backstop procurement if bilateral deals do not clear enough capacity.
Reprinted courtesy of
Stephen J. Humes, Pillsbury,
Alicia M. McKnight, Pillsbury,
Jason Drogin Atwood, Pillsbury and
Andrew H. Jacobs, Pillsbury
Mr. Humes may be contacted at stephen.humes@pillsburylaw.com
Ms. McKnight may be contacted at alicia.mcknight@pillsburylaw.com
Mr. Atwood may be contacted at jason.atwood@pillsburylaw.com
Mr. Jacobs may be contacted at andrew.jacobs@pillsburylaw.com
Read the full story...
Pulling the Plug, Preserving the Product: Protecting Rights to a Modular Subcontractor’s Work Post-Termination
June 08, 2026 —
Paul Williamson - ConsensusDocsVolumetric Modular Construction (VMC) is a building method where a structure is divided into large components or modules, fabricated in an offsite factory and then transported to a construction site for assembly.[
1] Proponents of VMC hail it as a cost-efficient alternative to traditional building methods that leads to more consistent quality and shorter construction duration.[
2] Due to a growing labor shortage, high demand for compressed project schedules, and stagnant construction productivity rates, the construction industry is embracing VMC.[
3] A recent report on the market size of prefabricated construction estimates that from 2026 to 2031, VMC will grow at a compound annual growth rate of 7.16% and become a 413.11-billion-dollar industry.[
4]
As VMC becomes more prevalent, owners, general contractors, and subcontractors must consider how to effectively contract for modular construction. One important consideration, which this article focuses on, is navigating termination of a modular subcontractor.
Read the full story...Reprinted courtesy of
Paul Williamson, Peckar & Abramson, P.C.Mr. Williamson may be contacted at
pwilliamson@pecklaw.com
AI Data Centers Become City-Scale Infrastructure, Prompting New Industry Playbook
August 11, 2026 —
Bryan Gottlieb - Engineering News-RecordAI data centers are no longer just buildings. They are increasingly reaching power-demand levels more commonly associated with municipalities, prompting industry groups to launch a new framework they say is needed to keep pace with rapidly changing power, cooling and reliability requirements.
Read the full story...Reprinted courtesy of
Bryan Gottlieb, Engineering News-RecordMr. Gottlieb may be contacted at
gottliebb@enr.com
Presumption of Prejudice Applies to All Affirmative Defenses Regarding Insured’s Failure to Comply with Post-Loss Policy Conditions
June 23, 2026 —
David Adelstein - Florida Construction Legal Updatesn a recent property insurance coverage dispute, an issue on appeal pertained to the “prejudice” jury instruction associated with the insured’s failure to comply with post-loss policy conditions. The trial court found that the prejudice only pertained to prompt notice and not other post-loss policy conditions. This was reversed on appeal as prejudice applied to ALL the post loss policy conditions that the insured failed to comply with, not just the prompt notice requirement. The prejudice presumption applies to all affirmative defenses regarding an insured’s failure to comply with post-loss policy conditions.
Consider this discussion when dealing with an insurer raising prejudice as an affirmative defense to do an insured’s failure to comply with post-loss policy conditions, and the associated burdens of proof:
On appeal, [the insurer] contends the trial court erred by instructing the jury that the presumption of prejudice was inapplicable to all of its post-loss obligation defenses except prompt notice. We agree.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Sometimes a General Damages Assessment is Enough. . .
July 06, 2026 —
Christopher G. Hill - Construction Law MusingsIt has been a while since I last posted here at
Construction Law Musings. Life, law practice, and “blogger’s block” have taken their toll on the posting schedule. Hopefully this will be one of several upcoming posts now that the litigation schedule has lightened a bit over the summer.
Today’s post is about damages. Specifically damage to a homeowner’s roof and her legal damages therefor. That last is of course a sentence that only a
construction attorney (or other litigator) could possibly craft and have it make sense. Now, on with the case. . .In
Hardesty Construction, Inc. v. Weedon, the facts are as follows:
Ms. Weedon had hail damage to the roof of her home. She hired Hardesty Construction to repair and replace the roof. After the first roof was installed and failed inspection, a second roof was installed. The issue was that the first roof had a warranty and the second roof, installed similarly to the first (and allegedly with the same construction issues according to Ms. Weedon’s expert), was not provided with the promised warranty. As one may expect, Weedon sued Hardesty and Hardesty Construction for fraudulent inducement and breach of contract. At trial, Weedon testified, without objection, that her home was worth $40,000 less because of Hardesty Construction’s work, which was based partially on quotes Weedon received to fix the roof. The Circuit Court granted Hardesty Construction’s motion to strike Weedon’s fraudulent inducement claim, but not her other claims. A jury awarded Weedon $30,253.30 on her breach of contract claim. Hardesty Construction appealed, arguing the Circuit Court erred in (a) allowing the jury to consider Weedon’s valuation testimony because it was not based on her personal knowledge and (b) denying its motion to strike based on insufficient evidence as to damages. Weedon assigned cross-error in the Circuit Court’s decision to grant the motion to strike her fraudulent inducement claim against Samual Hardesty.
Read the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com