Insured’s Failure to Determine Depreciation When Presenting Claim for Replacement Cost Value
August 16, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe Third Circuit affirmed the district court’s granting of summary judgment to the insurer when the insured submitted replacement cost value of the loss but did not include a determination of depreciation. Kimmel v. Massachusetts Bay Ins. Co., 2026 U.S. App. LEXIS 16569 (3d Cir. June 9, 2026).
A lightning strike downed a tree on the insured’s property, causing extensive damage to the home. The insured had a homeowner’s policy with Massachusetts Bay Insurance Company (MBIC). MBIC denied the claim, determining that much of the claimed damage already existed and that several policy exclusions otherwise barred coverage. The insured filed suit for breach of contract and bad faith.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Every High-Tech Building Has Many Lifespans
August 16, 2026 —
Aarni Heiskanen - AEC BusinessWhen I worked as an architect, our team designed a laboratory for fuel research. The facility included a large research hall where various boilers and other devices were tested and analyzed. The setup required extensive floor channeling under the thick concrete floor. We suggested building a modular system that would allow flexibility in the future, when requirements would certainly change. They did not want that because of budget constraints.
The high-tech construction trend is spreading. Data centers, semiconductor fabs, battery plants, and life science facilities share one property that sets them apart from ordinary buildings. The technology inside turns over faster than the structure around it. Server generations change every three to five years. Rack densities have risen from 10 or 20 kW to 130 kW and beyond in just a few years.
A high-tech facility is really several buildings with different lifespans inside one envelope, and we keep designing them as if they were one. The failure is not that things become obsolete. It is that we never say when each layer is expected to.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
LA Scores Major Victory in a High-Exposure Premises Liability Action
July 06, 2026 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPOur firm is proud to announce a decisive defense victory obtained by Partner
Daniel Crespo and Associate
Lauren Landau for our client in a high-exposure premises liability action arising from a 2022 incident at an active school construction site in Perris, California. On March 10, 2026, the Riverside County Superior Court granted Summary Judgment in full for our client, dismissing all claims brought by Plaintiff, who alleged she tripped and fell over a curb while picking up her daughter from school and sustained ankle and wrist injuries as a result.
Through meticulous preparation and the strategic use of construction plans, contractual documents, and onsite surveillance video evidence, our team demonstrated that our client had no ownership, possession, or control over the portion of the existing sidewalk where the incident occurred, with construction plans unambiguously designating the area as pre-existing concrete outside our client’s scope of work, and the Construction Services Agreement expressly reserving control over all existing site improvements to the school district.
Read the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
Course of Construction Exclusions and the CGL Policy
July 20, 2026 —
Anna M. Perry, Rachel S. Kindseth & Nina Catanzaro - Saxe Doernberger & Vita, P.C.I. Course of Construction Exclusions
Course of Construction (“COC”) exclusions are found on General Liability and excess liability policies, typically a wrap-up or project specific policy, and generally exclude “all property damage occurring during the course of construction.” Insurers claim COC exclusions are not problematic because they are intended to prevent an overlap in coverage between the general liability policy and first-party property Builder’s Risk policy. However, because General Liability policies and Builder’s Risk policies provide coverage for different risks, COC exclusions can create a gap in coverage for owners and contractors. Therefore, any exclusion on a wrap-up or project specific policy that limits coverage for property damage liability should be scrutinized, and amendments sought when warranted and commercially achievable, for owners, developers and contractors because General Liability policies do not cover the same risk as that of a Builder’s Risk policy.
General liability policies provide defense and indemnity to the insured(s) for claims made by a third-party against the insured. Broad COC exclusions serve to preclude coverage for all property damage, not just property damage to the insured project. This includes property damage to property other than the insured project, e.g. an adjacent property. On the other hand, Builder’s Risk policies provide first-party property coverage for direct physical loss to the project during the course of construction. The Builder’s Risk policy will not provide coverage for property other than the project itself (e.g., adjacent property) and it will not provide a defense or indemnity in the event the owner of the damaged property brings a claim against a potentially at-fault party.
Reprinted courtesy of
Anna M. Perry, Saxe Doernberger & Vita, P.C.,
Rachel S. Kindseth, Saxe Doernberger & Vita, P.C. and
Nina Catanzaro, Saxe Doernberger & Vita, P.C.
Ms. Perry may be contacted at APerry@sdvlaw.com
Ms. Kindseth may be contacted at rkindseth@sdvlaw.com
Ms. Catanzaro may be contacted at NCatanzaro@sdvlaw.com
Read the full story...
The “Pay When Paid” Clause in California Construction—Strategies as the Battle Continues
August 03, 2026 —
William L. Porter - Porter Law GroupIt is well known in California Construction circles that the “Pay If Paid” clause is illegal in this state. There is a great distinction, though, between this clause and a similar clause, known as a “Pay When Paid” clause. A pay if paid clause allows a contractor to tell a subcontractor that if the contractor is unpaid for the subcontractor’s work, then the contractor has no legal obligation to pay the subcontractor, ever. For a great variety of reasons, the California Supreme Court, in the case of Wm. R. Clarke Corp v. Safeco Ins. Co. of America (1997) 15 Cal.4th 882, declared this type of clause illegal in California Construction.
Although the pay if paid clause is illegal in California, the pay when paid clause is still perfectly legal and is found in many subcontracts that contractors issue to their subcontractors. The pay when paid clause allows a contractor to delay paying its subcontractors until the dispute between the contractor and the property owner over payment has been resolved and the contractor is paid by the property owner. Although seemingly reasonable (since it merely delays payment until the contractor is paid by the owner, thereby providing a funding source to pay subcontractors), significant problems still arise.
Read the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Traub Lieberman Wins Affirmation of Judgment on Pleadings Before the Seventh Circuit
August 16, 2026 —
Dana A. Rice & Adam P. Joffe - Traub LiebermanTraub Lieberman Partners Dana Rice and Adam Joffe obtained affirmation of judgment from the Seventh Circuit Court of Appeals in favor of an Insurance Company. The Insurance Company filed suit seeking a declaration that it had no duty to defend or indemnify its Insured, a Roofing Contractor, in an underlying lawsuit. The Insurance Company issued a commercial general liability policy with a one-year policy term. The policy included an exclusion that barred coverage for any losses arising out of work the insured completed before the date the policy incepted.
Reprinted courtesy of
Dana A. Rice, Traub Lieberman and
Adam P. Joffe, Traub Lieberman
Mr. Rice may be contacted at drice@tlsslaw.com
Mr. Joffe may be contacted at ajoffe@tlsslaw.com
Read the full story...
My Current Love-Hate Relationship with AI
June 08, 2026 —
Garret D. Murai - California Construction Law BlogIt’s early in the relationship, I know. But still, there are some things that bug me. Yet, I also know that it’s a relationship in which leaving is not an option, and even if I could, it’s not to the point where it’s so bad that I would do so. So, if you would, let me gripe a bit.
While there’s been much discussion about AI and, at least in my neck of the woods, a fair amount of discussion about how lawyers can, should, and must use AI or risk becoming discarded into the dustbin of history, much less has been written about clients’ use of AI.
Increasingly, I’ve gotten the sense that my clients are using AI. For example, I had a client ask for confirmation that if he disagreed with an administrative decision that he could file a writ of mandate, and if so, whether that deadline was 30, 60 or 90 days after the administrative decision. The answer to the first question was yes, and as to the second question, the answer was 90 days. This was from a client who, smart as he is, probably didn’t know this off the top of his head.
Read the full story...Reprinted courtesy of
Garret D. Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Integration Can Inoculate in Utah
July 20, 2026 —
Mark O. Morris - Snell & WilmerThe Utah Court of Appeals recently reaffirmed, in the construction context, Utah’s strict approach to enforcing integration clauses to preclude parol evidence and other legal theories that would vary the written terms of a contract. In Reid v. All Surface LC, 2025 UT App 134, decided last September, the court affirmed in all respects the trial court’s grant of summary judgment based on the strength of an integration clause against a homeowner who sued a contractor for breach of contract, breach of the covenant of good faith and fair dealing, fraud, negligent misrepresentation, civil conspiracy, negligence, and breach of the implied warranty of habitability. More recently, however, the same court rejected those same arguments in Tidwell v. Jensen, 2026 UT App 13 as to tort claims arising from a used car sale.
The facts in Reid were sympathetic to the plaintiff. After being told she had a mold issue near a defective basement shower, the plaintiff solicited bids. A remediation contractor advised that while it could address the mold, the shower replacement should be handled by someone else. The plaintiff contacted All Surface LC, a shower replacement contractor. During an interview, the sales representative stated that All Surface could “do full mold remediation, tear everything out, and reframe the shower.” The plaintiff ultimately retained All Surface, expecting it would both resolve the mold issues and replace the shower.
Read the full story...Reprinted courtesy of
Mark O. Morris, Snell & WilmerMr. Morris may be contacted at
mmorris@swlaw.com