Segal McCambridge Recognized in 2026 Chambers USA Rankings
June 15, 2026 —
Segal McCambridgeLos Angeles, CA, June 8, 2026 -
Segal McCambridge is pleased to announce that the firm has been recognized as a leader by Chambers USA in California. The firm is listed in the Chambers-ranked department, receiving a
Band 5 ranking for construction in California. The ranking further reinforces the firm's commitment to supporting California's construction market, from owners to developers and contractors, in high-stakes disputes statewide.
"Chambers' research-driven process and independence make this acknowledgment especially meaningful. We're proud of this ranking and grateful to our clients and colleagues whose consistent trust and collaboration make our work possible," said Jason P. Eckerly, Managing Shareholder of Segal McCambridge.
Chambers and Partners is widely regarded as one of the legal industry's most respected and independent ranking organizations. Operating across 200 jurisdictions and relied on in more than 70 countries, Chambers has, since 1990, conducted rigorous research to identify leading lawyers and law firms through a methodology that combines analysis of firm capability, achievement, and market presence through interviews and assessment of recent matters across more than 1,400 U.S. ranking tables, covering all 50 states, Washington, DC, and nationwide.
About Segal McCambridge
Segal McCambridge has built a reputation as a national law firm of accomplished trial attorneys for almost four decades. Founded in 1986, the firm has grown from a four-lawyer shop in Chicago to a firm with more than 20 offices nationwide. The firm routinely counsels and defends clients, including Fortune 500 companies, corporations, and individuals, across the United States in complex litigation matters, including, but not limited to: asbestos, class action, construction, employment, environmental, food and beverage, insurance coverage and bad faith, life sciences, product liability, professional liability, technology and cyber risk, transportation, and warranty. For more information, visit: www.segalmccambridge.com.
Building the Research and Healthcare Facilities of Tomorrow Without Impacting the Progress of Today
August 16, 2026 —
Jason Tobias - Construction ExecutiveResearch labs run experiments that canât be paused. Hospitals treat patients around the clock. Yet these same facilities constantly need upgradesânew infrastructure, modernized systems, renovated spacesâto meet the demands of twenty-first century science and medicine. The challenge for construction teams isnât just building. Itâs building without ever turning the lights off.
This unique dynamic creates an environment where construction activities are happening adjacent to sensitive testing and treatment, a complex setting where disruptions can have serious consequences.
Skanska continues to successfully navigate these challenges across multiple sectors, including from occupied lab space at the
North Carolina Department of Environmental Qualityâs (NCDEQ) Reedy Creek Laboratory in Raleigh to hospital corridors alongside staff and patients in various hospital locations across the country.
Reprinted courtesy of
Jason Tobias, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
U.S. Supreme Court Decision Alters Course of $745M Louisiana Coastal Damage Judgment
June 15, 2026 —
Jennifer Kretschmann & Jennifer E. Michel - Lewis BrisboisThe U.S. Supreme Court has issued a unanimous decision allowing oil and gas companies to move Louisiana coastal erosion lawsuits from state court to federal court under the federal officer removal statute. While the ruling is procedural, it carries significant implications for environmental- and energy-related risks. The case,
Chevron U.S.A. Inc. v. Plaquemines Parish, Louisiana, Slip Op. 24-813 (April 17, 2026), addressed a threshold jurisdictional question but has broader significance for environmental and climate related litigation. State courts are often viewed as more favorable forums for plaintiffs asserting environmental damage claims, particularly those brought by governmental entities.
The opinion issued on April 17, 2026 is the latest development in long-running Louisiana coastal litigation that began more than a decade ago. Starting in 2013, Louisiana parishes filed 42 lawsuits against oil and gas companies alleging environmental damage related to historic oil field operations. The parishes alleged that oil and gas companies violated state coastal management laws by failing to properly restore impacted areas. Chevron sought to remove the cases from state court under 28 U.S.C. § 1442(a)(1), known as federal officer removal, which provides federal jurisdiction over âany person acting under [an] officerâ of the United States "for or relating to any act under color of such office." The Fifth Circuit rejected the argument and remanded the case, and others like it, to state court. Trial began in March 2025 in Point Ă la Hache, Louisiana. On April 4, 2025, the jury awarded a total of $745 million to compensate for land loss, contamination and abandoned equipment. On June 16, 2025, the U.S. Supreme Court agreed to review the question of whether a federal contractor can remove to federal court when sued for oil-production activities undertaken to fulfill a federal oil-refinement contract.
Reprinted courtesy of
Jennifer Kretschmann, Lewis Brisbois and
Jennifer E. Michel, Lewis Brisbois
Ms. Kretschmann may be contacted at Jennifer.Kretschmann@lewisbrisbois.com
Ms. Michel may be contacted at Jenny.Michel@lewisbrisbois.com
Read the full story...
FERC Issues Show-Cause Orders: Impacts on California and Other Regional Power Markets
July 13, 2026 —
Stephen J. Humes, Alicia M. McKnight & Jason Drogin Atwood - Gravel2Gavel Construction & Real Estate Law BlogAt an open meeting on June 18, 2026, the Federal Energy Regulatory Commission (FERC) issued show-cause orders under Section 206 of the Federal Power Act to the six FERC-jurisdictional RTOs/ISOsâPJM Interconnection, ISO New England, Midcontinent Independent System Operator, Southwest Power Pool, New York Independent System Operator and California Independent System Operatorâalong with their transmission owners (TOs), directing each region and the TOs to justify or revise tariff provisions governing how data centers and other large loads connect to and receive transmission service from the grid. These show-cause orders will impact several power markets across the country, including California.
Reprinted courtesy of
Stephen J. Humes, Pillsbury,
Alicia M. McKnight, Pillsbury and
Jason Drogin Atwood, Pillsbury
Mr. Humes may be contacted at stephen.humes@pillsburylaw.com
Ms. McKnight may be contacted at alicia.mcknight@pillsburylaw.com
Mr. Atwood may be contacted at jason.atwood@pillsburylaw.com
Read the full story...
Sometimes a General Damages Assessment is Enough. . .
July 06, 2026 —
Christopher G. Hill - Construction Law MusingsIt has been a while since I last posted here at
Construction Law Musings. Life, law practice, and âbloggerâs blockâ have taken their toll on the posting schedule. Hopefully this will be one of several upcoming posts now that the litigation schedule has lightened a bit over the summer.
Todayâs post is about damages. Specifically damage to a homeownerâs roof and her legal damages therefor. That last is of course a sentence that only a
construction attorney (or other litigator) could possibly craft and have it make sense. Now, on with the case. . .In
Hardesty Construction, Inc. v. Weedon, the facts are as follows:
Ms. Weedon had hail damage to the roof of her home. She hired Hardesty Construction to repair and replace the roof. After the first roof was installed and failed inspection, a second roof was installed. The issue was that the first roof had a warranty and the second roof, installed similarly to the first (and allegedly with the same construction issues according to Ms. Weedonâs expert), was not provided with the promised warranty. As one may expect, Weedon sued Hardesty and Hardesty Construction for fraudulent inducement and breach of contract. At trial, Weedon testified, without objection, that her home was worth $40,000 less because of Hardesty Constructionâs work, which was based partially on quotes Weedon received to fix the roof. The Circuit Court granted Hardesty Constructionâs motion to strike Weedonâs fraudulent inducement claim, but not her other claims. A jury awarded Weedon $30,253.30 on her breach of contract claim. Hardesty Construction appealed, arguing the Circuit Court erred in (a) allowing the jury to consider Weedonâs valuation testimony because it was not based on her personal knowledge and (b) denying its motion to strike based on insufficient evidence as to damages. Weedon assigned cross-error in the Circuit Courtâs decision to grant the motion to strike her fraudulent inducement claim against Samual Hardesty.
Read the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
What Massachusetts Contractors and Developers Can Learn from Cannistraro v. Columbia Construction
July 13, 2026 —
Anthony LaPlaca & Luke Marston - The Construction SeytIntroduction
On June 26, 2026 the Massachusetts Supreme Judicial Court issued its decision in J.C. Cannistraro, LLC v. Columbia Construction Co.âa holding that sits at the intersection of Prompt Pay Act compliance and the Massachusetts Arbitration Act.
[1]
Most already know that the Massachusetts Prompt Pay Act (PPA) imposes strict timing and certification requirements for rejecting payment applications and proposed change orders on projects valued at $3 million or more. Most notably, the PPA requires the paying party to give the payee written notice of its approval or rejection of progress applications and proposed changes within 15 days of receipt, which notice must include a âfactual and contractual basis for the rejectionâ and must be âcertified as made in good faith.â
[2] In the absence of a timely certified notice, payment is âdeemed to be approvedâ unless the payor properly rejects payment before it comes due.
[3]
Reprinted courtesy of
Anthony LaPlaca, Seyfarth Shaw LLP and
Luke Marston, Seyfarth Shaw LLP
Mr. LaPlaca may be contacted at alaplaca@seyfarth.com
Mr. Marston may be contacted at lmarston@seyfarth.com
Read the full story...
New Executive Order on AI Innovation and Security: Key Takeaways for the Construction Industry
June 15, 2026 —
Richard R. Volack & Denis Serkin - Peckar & Abramson, PCOn June 2, 2026, President Trump signed an Executive Order titled âPromoting Advanced Artificial Intelligence Innovation and Security.â At its core, the Order is a cybersecurity and national-security measure rather than a broad regulation of how private companies develop or use AI. It directs federal agencies to harden government systems against AI-enabled cyber threats, establishes voluntary frameworks for collaboration between the federal government and the AI and critical-infrastructure sectors, and strengthens criminal enforcement against the malicious use of AI.
Notably, the Order expressly disclaims any intent to create a âmandatory governmental licensing, preclearance, or permittingâ regime for the âdevelopment, publication, release, or distribution of new AI models.â Instead, the Executive Order seeks to âpromote AI innovation and securityâ by working with the private sector to modernize government and private-sector information systems and harden them against external threats, protect intellectual property from exploitation or theft, and cultivate American AI capabilities.
Reprinted courtesy of
Richard R. Volack, Peckar & Abramson, PC and
Denis Serkin, Peckar & Abramson, PC
Mr. Volack may be contacted at rvolack@pecklaw.com
Mr. Serkin may be contacted at dserkin@pecklaw.com
Read the full story...
White and Williams LLP Secures $42.4 Million Award for Ventana DBS LLC in Philadelphia Marriott Construction Litigation
July 27, 2026 —
Craig O'Neill, Lindsay Liebman, Kristen Nichols Wright, Zachary Roth & William Taylor - White and WilliamsWhite and Williams LLP's Construction and Surety Practice attorneys secured a significant victory for client Ventana DBS LLC in a complex commercial construction dispute before the Philadelphia Court of Common Pleas, Commerce Division. The trial team, led by Bill Taylor, retired Partner, and Craig O'Neill, Co-Chair of the Construction and Surety Practice Group, with support from Lindsay Liebman, Counsel, Zachary Roth, Partner, Kristen Nichols Wright, Associate, and Sue Ferrante, Legal Secretary, obtained a $42.4 million award on Ventana's claims for unpaid work, delay costs, CASPA penalties and interest, attorneysâ fees and other project-related costs arising from the construction of the Marriott W/Element Hotel Project in Philadelphia.
To achieve this result, the White and Williams team managed an extensive discovery period over the course of four-years of litigation, conducted over sixty depositions, participated in court-ordered mediation and arbitration proceedings, and successfully represented Ventana during a bifurcated trial that spanned over the course of a year.
Reprinted courtesy of
Craig O'Neill, White and Williams,
Lindsay Liebman, White and Williams,
Kristen Nichols Wright, White and Williams,
Zachary Roth, White and Williams and
William Taylor, White and Williams
Mr. O'Neill may be contacted at oneillc@whiteandwilliams.com
Ms. Liebman may be contacted at liebmanl@whiteandwilliams.com
Ms. Wright may be contacted at wrightk@whiteandwilliams.com
Mr. Roth may be contacted at rothz@whiteandwilliams.com
Mr. Taylor may be contacted at taylorw@whiteandwilliams.com
Read the full story...