The Deadline to File Suit on a Public Works Payment Payment Bond is Triggered by a Claimant’s Work on a Project Not by a Claimant’s Work Under a Contract
June 02, 2026 —
Garret D. Murai - California Construction Law BlogCalifornia law requires that prime contractors furnish a payment bond – providing for payment to lower-tiered subcontractors and suppliers – on state and local public works projects with a value in excess of $25,000. There are three conditions that must be satisfied when a claimant makes a claim against a payment bond on a public works project in California:
- First, generally, the claimant must have served a preliminary notice, unless the claimant is a first-tier subcontractor or supplier;
- The claimant must have “ceased to provide work” on the project; and
- The claimant must file suit against the payment bond no later than six (6) months after the period in which a stop payment notice must be given or, in other words, the earlier of 270 days after completion of the public works project or 210 days after a notice of completion or cessation was recorded on a public works project.
In
Tarlton & Sons, Inc. v. Great American Insurance Company, 111 Cal.App.5th 376 (2025), the 2nd District Court of Appeal examined whether a subcontractor timely filed a claim against a payment bond when a prime contractor was terminated and replaced by another prime contractor who the subcontractor continued to perform work for.
Read the full story...Reprinted courtesy of
Garret D. Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Lienor Dealing With “Show Cause” Summons by Condominium Unit Owner
September 01, 2026 —
David Adelstein - Florida Construction Legal UpdatesOne of the statutory vehicles to shorten a construction lienor’s statute of limitations to foreclose on a construction lien is through a “show cause” summons that essentially requires the lienor to foreclose on the lien within 20 days from receipt of the “show cause” summons. This is a statutory procedure under Florida’s Lien Law in
Fla. Stat. s. 713.21(4). If a lienor receives a “show cause” summons and lawsuit, the lienor should, without delay, counterclaim or file a separate lien foreclosure lawsuit within the 20-day period without exception. This is provided the lienor wants to move forward with its lien. If a lienor does not, the lien will be discharged of record. If you are a lienor and receive a “show cause” summons, please immediately consult with construction counsel that can best advise you and perfect your lien rights.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
2026 Colorado Super Lawyers Recognizes 11 Snell & Wilmer Attorneys
May 05, 2026 —
Snell & WilmerDENVER – Snell & Wilmer is pleased to announce that eleven attorneys in its Denver office have been selected for inclusion in the 2026 Colorado Super Lawyers publication. Of those eleven, four were recognized as Rising Stars.
Super Lawyers is a listing of lawyers from more than 70 practice areas who have attained a high degree of peer recognition and professional achievement. The selection process is multi-phased and includes independent research, peer nominations, and peer evaluations. The final published list represents no more than 5 percent of the lawyers in the state.
Read the full story...Reprinted courtesy of
Snell & Wilmer
The Most Expensive Signature to Not Get: Why Change Orders Matter
August 16, 2026 —
Kathryne E. Baldwin - Wilke FleuryGeorge Bernard Shaw has a quote we use a lot in my family: “The single biggest problem in communication is the illusion that it has taken place.” This is pertinent to contractors and homeowners alike because the cost of failing to get proper signatures on documents like construction contracts, and particularly, change orders, is heavy. Both contractors and homeowners are in the same boat as far as wanting to complete a job as swiftly as possible: contractors go on to their next job and homeowners can return to peace in their home. This is prime territory for either party to suggest the work be completed today and the contract or change order executed tomorrow, or even later. However, without a contract, there is no memorialization of the communication between the parties, which can lead to confusion and missed expectations on both sides.
Construction plans are rarely as neat and tidy as they originally seem to be. A contractor may uncover unforeseen conditions, an owner may request additional work or changes that require additional work, or weather interferes with project schedules or the work itself. Unfortunately, the signature that never gets collected can become one of the most expensive omissions on a project – for both sides.
Read the full story...Reprinted courtesy of
Kathryne E. Baldwin, Wilke FleuryMs. Baldwin may be contacted at
kbaldwin@wilkefleury.com
Nordics Are Europe’s Next Data Center Hub
October 05, 2026 —
Aarni Heiskanen - AEC BusinessOn September 9, 2026, Google announced its largest single investment in Europe. The company commits at least €13 billion to Finnish data centers and energy infrastructure in 2027 and 2028, expanding the existing Hamina campus and adding three new sites in Kajaani, Muhos, and Vaala. For the construction sector, this is great news: thousands of hectares, dozens of buildings, and a construction program that will extend well beyond the two-year investment window.
Four Sites, One Regional Cluster
Google is not a newcomer in Finland. Back in 2009, it converted a former paper mill in Hamina into a seawater-cooled data center. It has invested around €4.5 billion there over 15 years, and the site’s waste heat already feeds Hamina’s district heating network. The new program shifts the center of gravity north, to the border of North Ostrobothnia and Kainuu.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Insurer Granted Summary Judgment on Claim for Roof Damage Caused by Windstorm
May 26, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer successfully moved for summary judgment, eliminating the insured’s claim for roof damage due to windstorm. Mulas v. Westchester Surplus Lines Ins. Co., 2026 U.S. Dist. LEXIS 20537 (Jan. 30, 2026).
The insureds’ commercial property sustained windstorm damage during Hurricane Ian. Westchester denied the claim. The insureds believed Westchester wrongfully denied coverage for roof damage and various interior damage to property. The insureds also argued that Westchester’s actual cash value (ACV) payment did not reflect the fully insured loss.
The insureds sued and Westchester moved for summary judgment. Westchester argued the roof damage was not covered because Hurricane Ian did not cause the damage. Westchester hired an engineer who determined the roof damage was not caused by wind from Hurricane Ian. Westchester pointed out that the insureds’ expert also found no wind damage on the roof. The insureds offered no other evidence suggesting the hurricane caused roof damage. Therefore, the insureds could not show that Westchester breached the policy by denying coverage.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
New York Orders Moratorium on Large Data Center Permits
July 27, 2026 —
Levi W. Barrett - Peckar & Abramson, P.C.Levi W. Barrett, Co-Managing Partner of Peckar & Abramson’s New Jersey office, Co-Chair of the firm’s
Construction Contracts & Risk Management team, and Executive Committee Member, was recently quoted in “New York Orders Moratorium on Large Data Center Permits,” an article written by
Engineering News-Record (ENR). The article examines New York Governor Kathy Hochul’s executive order temporarily halting state environmental permit reviews for certain large-scale data center projects while regulators develop a comprehensive framework to address the sector’s energy demands, water consumption, environmental impacts, and effects on local communities. It also explores the broader implications of the moratorium for developers, contractors, investors, and other stakeholders, as well as the ongoing debate between economic development, AI-driven infrastructure growth, and environmental and utility ratepayer concerns.
Read the full story...Reprinted courtesy of
Levi W. Barrett, Peckar & Abramson, P.C.Mr. Barrett may be contacted at
lbarrett@pecklaw.com
Global Insights Center: Monthly Newsletter
June 15, 2026 —
Global Insights Center Staff - The HartfordMay in Review
Last month, inflation moved higher, with Consumer Price Index (CPI) inflation rising to 3.8% year over year, up from 3.3% the prior month. The increase was driven primarily by energy prices, particularly gasoline, reflecting ongoing disruptions tied to the Middle East conflict.
Labor market data were broadly stable. The unemployment rate remained unchanged at 4.3%, wage growth increased modestly to 3.6%, while job growth continued to be geographically concentrated in the Southern states, particularly cities in Texas. On an occupational basis, healthcare once again led job gains, especially in home health services, a trend we have consistently highlighted. Business formations increased during the month, with notable strength in e commerce and digital services firms. Manufacturing activity also improved, particularly in semiconductors, IT equipment, and natural gas–related energy infrastructure.
Read the full story...Reprinted courtesy of
Global Insights Center Staff, The Hartford