Data Center Construction: Contractors Must Step Up
May 26, 2026 —
Aarni Heiskanen - AEC BusinessI attended the
Datacenter Forum 2026 in Helsinki last week. Over 400 people packed the room. Walking out, I had one overriding thought: Is construction operating in a different century from the technology it is being asked to house?
Is Our Industry on Par?
Ciarán Forde, Senior Vice President at CTS Nordics, opened the forum with a statement that set the tone for everything that followed: data centers are no longer just a technical challenge; they are a national strategy. Before AI, Ciarán had worked in telecoms, where data centers were already complex. But now, he said flatly, everything has changed, and the industry must rethink everything.
The numbers behind the claim are staggering. Current AI data center racks run at 40 to 100 kW. In three years, 800 kW per rack is on the roadmap. And the development cycle for a new chip is roughly one year, which means deployments begin aging out almost as soon as they are commissioned.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Ahlers Cressman & Sleight named one of the Top 50 Construction Law Firms
August 11, 2026 —
Ahlers Cressman & Sleight PLLCAhlers Cressman & Sleight PLLC is pleased to announce its fifth consecutive year of recognition by Construction Executive as one of The Top 50 Construction Law Firms.
Since its first publication in 2003, Construction Executive magazine has served as the leading source for news, market developments, and business issues impacting the construction industry. Construction Executive established the rankings by asking over 600 U.S. construction law firms to complete a survey. Constructive Executive’s data collection includes: 2025 revenues from the firm’s construction practice; the number of attorneys in the firm’s construction practice; the percentage of the firm’s total revenues derived from its construction practice; the number of states in which the firm is licensed to practice; the year in which the construction practice was established; and the number of construction industry clients served during the fiscal year 2025.
Read the full story...Reprinted courtesy of
Ahlers Cressman & Sleight PLLC
Doctrine of Substantial Performance When It Comes to Payment
July 27, 2026 —
David Adelstein - Florida Construction Legal UpdatesA recent non-construction case touches upon the doctrine of substantial performance when it comes to payment. In this case, a club was to make two payments to secure a rapper’s attendance. The first payment was made. The second payment was made but was a few hundred dollars short of the agreed amount. The rapper did not show up. The club claimed it substantially performed its obligations. At first glance, the argument makes sense because the second payment fell only a few hundred dollars short. But that wasn’t the case when it comes to pre-commencement payment obligations:
Substantial performance applies only when the variance from the contract terms “is inadvertent or unintentional and unimportant so that the work actually performed is substantially what was called for in the contract.” However, when one party agrees to pay the other on or before a specific date, time is of the essence, and the payor is required to pay the payee on or before that date. “There is almost always no such thing as ‘substantial performance’ of payment between commercial parties when the duty is simply the general one to pay. Payment is either made in the amount and on the date due, or it is not.”
Big Gate Records, LLC v. Washington, 51 Fla.L.Weekly D1281a (Fla. 2nd DCA 2026) (internal citations omitted).
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
GRSM Team Obtains Defense Verdict for Homeowners’ Association in Orange County Superior Court
July 20, 2026 —
Gordon Rees Scully MansukhaniA Gordon Rees Scully Mansukhani multi-state team, including Partners Christine Barker, Sean Ferron, and Keith Cramer, obtained a defense verdict on behalf of a homeowners’ association (HOA) in an Orange County Superior Court bench trial spanning two months.
The case began in 2022 when a homeowner sued after the Architectural Review Committee and HOA Board of Directors declined his teardown-and-rebuild plans due to view and aesthetic concerns. After a motion for summary judgment ruling in which the court found that the existing covenants, conditions, and restrictions (CC&Rs) did not protect views, the HOA held a special election to add explicit view protections to the CC&Rs. At the February 2025 trial call, the plaintiff sought leave to file a third amended complaint challenging the validity of that vote, drastically reframing the case from CC&R enforcement to one of election validity. A second plaintiff then filed a parallel action toward the end of the limitations period, and the two cases were consolidated.
Read the full story...Reprinted courtesy of
Gordon Rees Scully Mansukhani
Pay-If-Paid: What You Need to Know Before Signing on the Dotted Line
August 03, 2026 —
Christian Fernandez & Matthew Racioppo - Snell & WilmerBuried deep in the fine print of a subcontract, a pay-if-paid clause may be looming. If you are a subcontractor or supplier, misreading these clauses can put your cash flow at risk. If you are an owner or general contractor, drafting them incorrectly can leave you with obligations you never intended — or unenforceable protections you were counting on.
It is more important than ever to understand when pay-if-paid clauses hold up and when they do not, as well as recent litigation and drafting trends. Whether you are negotiating a new agreement, reviewing your standard form contracts, or staring down a payment dispute, understanding how Arizona law treats pay-if-paid clauses is essential. In this article, we break down key considerations, walk through the legal standards Arizona courts apply, and offer practical tips to consider to help you protect your payment rights on the next project.
Reprinted courtesy of
Christian Fernandez, Snell & Wilmer and
Matthew Racioppo, Snell & Wilmer
Mr. Fernandez may be contacted at cfernandez@swlaw.com
Mr. Racioppo may be contacted at mracioppo@swlaw.com
Read the full story...
My Current Love-Hate Relationship with AI
June 08, 2026 —
Garret D. Murai - California Construction Law BlogIt’s early in the relationship, I know. But still, there are some things that bug me. Yet, I also know that it’s a relationship in which leaving is not an option, and even if I could, it’s not to the point where it’s so bad that I would do so. So, if you would, let me gripe a bit.
While there’s been much discussion about AI and, at least in my neck of the woods, a fair amount of discussion about how lawyers can, should, and must use AI or risk becoming discarded into the dustbin of history, much less has been written about clients’ use of AI.
Increasingly, I’ve gotten the sense that my clients are using AI. For example, I had a client ask for confirmation that if he disagreed with an administrative decision that he could file a writ of mandate, and if so, whether that deadline was 30, 60 or 90 days after the administrative decision. The answer to the first question was yes, and as to the second question, the answer was 90 days. This was from a client who, smart as he is, probably didn’t know this off the top of his head.
Read the full story...Reprinted courtesy of
Garret D. Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
No Bad Faith Despite Insurer’s Appraisal Award Exceeding Initial Payment
August 03, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court granted the insurer’s motion for summary judgment, finding no bad faith despite the appraisal award exceeding the amount the insurer initially paid. Jazi Kat 4659 Rockridge LLC, et al. v. Travelers Cas. Ins. Co. of Am., et al., 2026 U.S. Dist. LEXIS 105634 (D. Ariz. May 13, 2026).
Plaintiffs sued Travelers for breach of contract and bad faith, alleging that Travelers failed to pay money plaintiffs were owed under the policy. Plaintiffs held a commercial property policy for two properties. A fire destroyed one of the properties. Travelers adjusted the claim and issued two payments. Plaintiffs disagreed with the amount of the payments and demanded an appraisal. Travelers agreed to the appraisal.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Sixth Circuit Revives Builder’s Risk Coverage, Refusing to Let Insurer Escape on a Technicality
July 27, 2026 —
Kevin V. Small & Adriana A. Perez - Hunton Insurance Recovery BlogIn 3371 Reading, LLC v. Liberty Mutual Group, the Sixth Circuit did something courts do not always do in coverage disputes: it refused to let an insurer avoid liability based on a technical policy condition that could never actually be satisfied.
The decision is a straightforward reminder of two core principles. First, policies must be interpreted from the standpoint of a reasonably prudent insured. Second, hyper-technical conditions cannot be used to deny coverage where compliance is never possible.
Reprinted courtesy of
Kevin V. Small, Hunton Andrews Kurth LLP and
Adriana A. Perez, Hunton Andrews Kurth LLP
Mr. Small may be contacted at ksmall@hunton.com
Ms. Perez may be contacted at pereza@hunton.com
Read the full story...