FERC Issues Show-Cause Orders: Impacts on California and Other Regional Power Markets
July 13, 2026 —
Stephen J. Humes, Alicia M. McKnight & Jason Drogin Atwood - Gravel2Gavel Construction & Real Estate Law BlogAt an open meeting on June 18, 2026, the Federal Energy Regulatory Commission (FERC) issued show-cause orders under Section 206 of the Federal Power Act to the six FERC-jurisdictional RTOs/ISOs—PJM Interconnection, ISO New England, Midcontinent Independent System Operator, Southwest Power Pool, New York Independent System Operator and California Independent System Operator—along with their transmission owners (TOs), directing each region and the TOs to justify or revise tariff provisions governing how data centers and other large loads connect to and receive transmission service from the grid. These show-cause orders will impact several power markets across the country, including California.
Reprinted courtesy of
Stephen J. Humes, Pillsbury,
Alicia M. McKnight, Pillsbury and
Jason Drogin Atwood, Pillsbury
Mr. Humes may be contacted at stephen.humes@pillsburylaw.com
Ms. McKnight may be contacted at alicia.mcknight@pillsburylaw.com
Mr. Atwood may be contacted at jason.atwood@pillsburylaw.com
Read the full story...
Breaking Ground On New California Public Works Prevailing Wage Requirements
April 27, 2026 —
Heather Frisch, Christopher Bouquet & Ashley Stein - The Construction SeytSeyfarth Synopsis: As of January 1, 2026, AB 889 bulldozed California’s Prevailing Wage law, which impacts public works employers—including public agencies, the contractors that work for them, and private owners and developers whose projects may be subject to public works requirements. The amended law reframes the calculation of fringe benefits for individuals who work on public works project and mandates annualization of such benefits, demolishes the practice of frontloading these benefits, and requires employers to maintain inspection-ready records of compliance.
This year, AB 889 significantly revised California’s prevailing wage law, codified at Labor Code section 1773.1, to clarify the state’s prevailing wage regulations and streamline enforcement. Accordingly, as of January 1, 2026, California public works employers are required to annualize employees’ fringe benefits and maintain specific documentation demonstrating statutory compliance. These new obligations impact public agencies and their contractors, as well as private owners and developers whose projects may be subject to public works requirements. Continue reading for the blueprint of how to comply with the state’s amended prevailing wage law.
Reprinted courtesy of
Heather Frisch, Seyfarth Shaw LLP,
Christopher Bouquet, Seyfarth Shaw LLP and
Ashley Stein, Seyfarth Shaw LLP
Ms. Frisch may be contacted at hfrisch@seyfarth.com
Mr. Bouquet may be contacted at cbouquet@seyfarth.com
Ms. Stein may be contacted at astein@seyfarth.com
Read the full story...
Insurer Dispenses with Bad Faith Claim on Summary Judgment
June 22, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted the insurer’s motion for partial summary judgment because the insured failed to present evidence that the insurer failed to conduct a reasonable investigation. PSY Burger, LLC v. State Farm General Insurance Company, 2026 U.S. Dist. LEXIS 66991(C.D. Cal. March 20, 2026).
The insured’s commercial property suffered heavy damage from tropical storm Hilary. State Farm denied coverage to repair the damage. The insured sued State Farm alleging breach of contract and bad faith due to an inadequate investigation. Apparently, the insured did not retain an expert to opine on claims handling.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Traub Lieberman Wins Affirmation of Judgment on Pleadings Before the Seventh Circuit
August 16, 2026 —
Dana A. Rice & Adam P. Joffe - Traub LiebermanTraub Lieberman Partners Dana Rice and Adam Joffe obtained affirmation of judgment from the Seventh Circuit Court of Appeals in favor of an Insurance Company. The Insurance Company filed suit seeking a declaration that it had no duty to defend or indemnify its Insured, a Roofing Contractor, in an underlying lawsuit. The Insurance Company issued a commercial general liability policy with a one-year policy term. The policy included an exclusion that barred coverage for any losses arising out of work the insured completed before the date the policy incepted.
Reprinted courtesy of
Dana A. Rice, Traub Lieberman and
Adam P. Joffe, Traub Lieberman
Mr. Rice may be contacted at drice@tlsslaw.com
Mr. Joffe may be contacted at ajoffe@tlsslaw.com
Read the full story...
Managing Rising Costs and Shifting Legal Risk for Florida High-Rise and Condominium Projects
May 05, 2026 —
Stephen Hauptman - Ball Janik LLPFlorida's construction defect landscape is experiencing a major shift. The convergence of material and labor cost volatility, regulatory tightening, and increasingly complex litigation strategies is forcing associations, developers, and their counsel to rethink how they approach risk management and dispute resolution. For those managing large-scale condo and high-rise projects, the stakes have never been higher.
The Cost Volatility Trap
Construction material prices rose at a "staggering" 12.6% annualized rate during the first two months of 2026, according to
recent industry analysis. Tariff impacts are projected to lead to more increases of 5.4% to 6.8%, depending on property type. For associations facing construction defect claims, this volatility creates a cascading problem: repair scopes defined two years ago are now dramatically underpriced, and damage calculations that appeared reasonable at discovery are obsolete by the time of settlement.
Courts and mediators are increasingly scrutinizing how cost estimates were developed and whether they account for existing market circumstances. Associations must now commission updated repair assessments more frequently, a practice that increases investigation costs but strengthens the credibility of damage claims. Conversely, defendants are weaponizing cost inflation as a defense, arguing that claimed damages are speculative or inflated. The practical result: repair sequencing and phasing strategies have become critical litigation tools. Associations that can demonstrate a rational, cost-effective repair plan tied to current market data are more favorably placed in settlement negotiations.
Regulatory Pressure and Deliberate Timing
Florida's 2026 condo compliance regime has significantly changed the defect claims landscape. Elevated transparency requirements, stricter reserve funding mandates, and tightened building safety inspection protocols mean that associations now face dual pressures: Comply with new regulations while simultaneously handling construction defect exposure.
This regulatory environment is changing investigation and documentation strategy. Associations that delay defect investigation to avoid triggering reserve funding obligations or disclosure requirements are taking on considerable legal risk. Recent case law such as the Third District Court of Appeal's reaffirmation of Chapter 558's pre-suit mediation requirements, underscores Florida's intent to resolve disputes early. Associations that move deliberately and record carefully during the pre-suit phase gain leverage in mediation and reduce the risk of expensive litigation.
Timing also intersects with repair sequencing. Associations must now balance the urgency of compliance inspections against the strategic advantage of phased repairs. Some associations are using compliance deadlines as a forcing mechanism to accelerate settlement discussions, while others are sequencing repairs to demonstrate good-faith remediation efforts before litigation commences.
The Emerging Risk Transfer Challenge
As construction defect claims grow more complex and costly, the traditional risk transfer systems, such as design-build warranties, contractor bonds, and insurance, are proving inadequate. Developers and general contractors are increasingly shifting risk to subcontractors and material suppliers, fragmenting liability and complicating recovery efforts for associations. Permitting and approval friction is also creating new litigation pressure points. Delays in municipal approvals, changes to building code interpretations, and disputes over remedial work compliance continue to spawn collateral claims that go beyond the original defect. Associations must now anticipate not only defect liability but also regulatory compliance disputes with municipalities, creating a dual-front legal challenge.
For large communities, this means reconsidering the entire risk architecture. Insurance carriers are tightening coverage, and traditional indemnification chains are breaking down. Forward-thinking associations are engaging counsel earlier in the development process to negotiate clearer risk allocation provisions and more robust insurance requirements.
Taking a Data-Driven Approach
Managing rising costs and shifting legal risk in Florida's high-rise and condo market requires a more sophisticated, data-driven approach. Associations must commission frequent cost updates, move deliberately through pre-suit investigation and mediation, and challenge traditional assumptions about risk transfer. Developers and their counsel should view regulatory compliance not as a burden but as an opportunity to demonstrate good-faith risk management and strengthen settlement positioning.
The firms and associations that succeed in 2026 will be those that treat cost volatility, regulatory change, and litigation strategy not as separate challenges but as linked elements of a coherent risk management framework.
Stephen Hauptman is special counsel in Ball Janik LLP’s Fort Lauderdale office. He may be reached at shauptman@balljanik.com.
Hidden Risks Behind Today’s Stadium Construction Boom
July 20, 2026 —
Thomas Strong, Andrew Canning & Marc Gnesin - Construction ExecutiveAfter a decade-plus lull, professional sports leagues, universities and municipalities are once again spending heavily on new
stadiums and major renovations. In the NFL alone, multiple marquee projects are underway or planned, representing more than $10 billion in facilities and mixed-use entertainment districts, rivaling or exceeding the scale of development during the last stadium-build cycle of the early 2000s.
Beneath the excitement of architectural ambition and civic pride lies a risk landscape that has fundamentally changed since the last wave of stadium construction. Teams, cities and contractors that rely on outdated assumptions may find themselves exposed to cost overruns, schedule delays and liabilities that are far more difficult to unwind once construction is underway.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Preventing Common and Costly Water Intrusion Events in Construction
July 13, 2026 —
Andrew Swift - Construction ExecutiveWater leaking into a building is a leading cause of
damage and loss in the construction industry. On one jobsite, heavy rains flooded a sub-basement, damaging a new electrical transformer—all because a roof drain was not property connected. On another jobsite, a drinking-fountain supply line broke in a multistory building that was undergoing renovation, causing water to run—undetected—for an entire weekend, resulting in water damage to all lower floors, where construction had been finished.
Those loss scenarios could have been prevented with a comprehensive and effective water damage prevention plan (WDPP). This includes routine site inspections to identify uncontrolled water damage exposures and basic maintenance to make sure drains are clean of debris and divert them to a catch basin or low point away from the building. An effective WDPP plan also incorporates technology such as backflow preventers on sewer connections and water sensing technology to monitor the most vulnerable exposures.
Reprinted courtesy of
Andrew Swift, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Tracy Cowan Honored as “Icon” in Missouri Lawyers Media’s First-Ever “Illinois Legal Leaders” Awards
September 15, 2026 —
Lewis BrisboisSt. Louis Managing Partner Tracy Cowan has been named an “Icon” by Missouri Lawyers Media in its inaugural “Illinois Legal Leaders” awards program.
Mr. Cowan was among 14 people who earned “Icon” status in the awards program. This category honors “senior leaders with 30 years or more of legal practice” and is one of three groups recognized. The other two include “Up & Coming Lawyers,” for attorneys with 10 or fewer years in legal practice, and “Leaders in the Law,” which recognizes members of the bar who have significantly contributed to the practice of law in the state, the local legal community, and the broader community.
Read the full story...Reprinted courtesy of
Lewis Brisbois