OC Streetcar Project Mediation Sets $50M Payment to Walsh
July 20, 2026 —
Richard Korman - Engineering News-RecordWalsh Construction told a California state court judge last month that lawsuit mediation of its claims on an Orange County light-rail project—known as OC Streetcar—had produced a settlement of some claims under which the county agreed to pay the contractor almost an additional $50 million.
Read the full story...Reprinted courtesy of
Richard Korman, Engineering News-RecordMr. Korman may be contacted at
kormanr@enr.com
Ahlers Cressman & Sleight named one of the Top 50 Construction Law Firms
August 11, 2026 —
Ahlers Cressman & Sleight PLLCAhlers Cressman & Sleight PLLC is pleased to announce its fifth consecutive year of recognition by Construction Executive as one of The Top 50 Construction Law Firms.
Since its first publication in 2003, Construction Executive magazine has served as the leading source for news, market developments, and business issues impacting the construction industry. Construction Executive established the rankings by asking over 600 U.S. construction law firms to complete a survey. Constructive Executive’s data collection includes: 2025 revenues from the firm’s construction practice; the number of attorneys in the firm’s construction practice; the percentage of the firm’s total revenues derived from its construction practice; the number of states in which the firm is licensed to practice; the year in which the construction practice was established; and the number of construction industry clients served during the fiscal year 2025.
Read the full story...Reprinted courtesy of
Ahlers Cressman & Sleight PLLC
Ninth Circuit Holds That Policies Covering Environmental Claims Do Not Have Aggregate Limits
May 12, 2026 —
Lorelie S. Masters & Joseph T. Niczky - Hunton Insurance Recovery BlogIn the case of
County of San Bernardino v. Insurance Company of the State of Pennsylvania, the Ninth Circuit recently addressed the issue of whether general liability policies issued in the 1960s and 1970s included aggregate limits for claims arising under the premises-operations coverage in CGL policies. The difference between the policyholder’s interpretation of the policies’ limits clauses and the insurer’s interpretation was worth hundreds of millions of dollars in exposure for the insurer. The Court closely examined the policy language and extrinsic evidence from both the insurance industry’s drafting history and the parties before concluding that the policies were ambiguous. The Court construed that ambiguity in favor of the policyholder and ruled that aggregate limits did not apply to the claims at issue. The Court’s decision underscores the importance of carefully examining a policy’s limits, especially for older policies written before 1986 when the insurance industry revised the standard-form CGL policy to state the aggregate limits apply not only to products liability claims but to premises-operations claims as well. Decades of insurance industry drafting history confirms, as the policyholder’s submissions in this case indicate, that the industry well understood that operations claims like the environmental waste-disposal claims at issue here typically were not subject to aggregate limits.
Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews Kurth LLP and
Joseph T. Niczky, Hunton Andrews Kurth LLP
Ms. Masters may be contacted at lmasters@hunton.com
Mr. Niczky may be contacted at jniczky@hunton.com
Read the full story...
Fraud Allegations Stymie Additional Insured’s Request for a Defense
May 14, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe Federal District Court granted the insurer’s motion to dismiss the insured’s complaint seeking a defense of the underlying case alleging fraud. Renovation Realty, Inc. v. Colony Ins. Co., 2026 U.S. Dist. LEXIS 21409 (S.D. Cal. Jan. 30, 2026).
Mara Fortin sued Renovation Realty and others (“Fortin litigation”) from the fraudulent sale of a residence. The underlying complaint alleged Renovation “deliberately misrepresented of the residence as ‘completely remodeled’ and ‘meticulously maintained’.” The defendants, however, including Renovation, “knew from sources including a pre-renovation termite report documenting fungus and dry rot . . . that the Property harbored pre-existing material defects.”
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
California Enacts Change Order Fair Payment Act
March 24, 2026 —
Michael J. Baker - Snell & WilmerFor private works construction contracts entered on or after January 1, 2026, recent legislation establishes a claims and dispute resolution process for change orders. The law is codified at Civil Code § 8850. A synopsis of the pertinent provisions includes the following:
- Submitting a Claim. Contractors or subcontractors must submit a detailed, documented claim when requesting additional time or payment.
- Owner’s Response Time. The owner must meet and confer within thirty (30) days after receiving the claim. Within ten (10) days of meeting, the owner must provide a written statement identifying which portions of the claim are undisputed and which are disputed. An owner’s failure to respond is treated as disputing the entire claim.
Read the full story...Reprinted courtesy of
Michael J. Baker, Snell & WilmerMr. Baker may be contacted at
mjbaker@swlaw.com
Denis Serkin and Michael S. Zicherman Co-Edit/Author Lexology Panoramic: Construction 2027
August 03, 2026 —
Denis Serkin & Michael S. Zicherman - Peckar & Abramson, P.C.P&A partners
Denis Serkin and
Michael S. Zicherman served as co-editors and authors of Lexology’s Panoramic: Construction 2027 – US and Global guide. Formerly Getting the Deal Through, Lexology Panoramic provides members of the construction industry and construction-related legal and business providers with side-by-side comparison of key industry issues in 19 jurisdictions worldwide.
Reprinted courtesy of
Denis Serkin, Peckar & Abramson, P.C. and
Michael S. Zicherman, Peckar & Abramson, P.C.
Mr. Serkin may be contacted at dserkin@pecklaw.com
Mr. Zicherman may be contacted at mzicherman@pecklaw.com
Read the full story...
Motion for Summary Judgment Granted in Significant California Public Utilities Suit
May 12, 2026 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPCongratulations to Partner Mike D’Andrea and Associates Ruth Rasiah and Kaylah Abdullah in the Los Angeles office for obtaining a complete dismissal of their clients in a significant claim involving California’s Public Utilities regulations.
After lengthy litigation, BWB&O’s Motion for Summary Judgment was granted against Claimant, Spectrum (Charter Communications), which resulted in a complete dismissal of the action against BWB&O’s clients. At issue was whether California’s Public Utilities Code shifted the common law duty to maintain certain utility equipment in residential areas within Southern California. After significant briefing, the Superior Court found that BWB&O correctly argued that the Public Utilities Code required utility companies, like Spectrum, to fully maintain utility equipment, and that private residents are not responsible for utility maintenance (even if the physical equipment is located on private property).
Read the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
Colorado Court Affirms Attorneys’ Fee Award Against Plaintiff’s Counsel for Pursuing Unsupported CCPA Claims
August 03, 2026 —
David McLain - Colorado Construction Litigation BlogThe Colorado Court of Appeals recently affirmed a trial court’s award of more than $241,000 in attorney fees against a plaintiffs’ attorney who continued to pursue unsupported claims arising out of a residential construction dispute. Although the opinion was not selected for official publication under C.A.R. 35(e) and therefore has no precedential value, it nevertheless provides an instructive reminder that Colorado courts are willing to impose significant financial consequences when claims lack substantial justification.
For builders, developers, contractors, insurers, and defense counsel, the case is worth reading, not because it announces new law, but because it demonstrates that Colorado’s fee-shifting statute remains a meaningful tool when unsupported claims continue long after they should have been abandoned.
Read the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at