Data Center Construction: Contractors Must Step Up
May 26, 2026 —
Aarni Heiskanen - AEC BusinessI attended the
Datacenter Forum 2026 in Helsinki last week. Over 400 people packed the room. Walking out, I had one overriding thought: Is construction operating in a different century from the technology it is being asked to house?
Is Our Industry on Par?
Ciarán Forde, Senior Vice President at CTS Nordics, opened the forum with a statement that set the tone for everything that followed: data centers are no longer just a technical challenge; they are a national strategy. Before AI, Ciarán had worked in telecoms, where data centers were already complex. But now, he said flatly, everything has changed, and the industry must rethink everything.
The numbers behind the claim are staggering. Current AI data center racks run at 40 to 100 kW. In three years, 800 kW per rack is on the roadmap. And the development cycle for a new chip is roughly one year, which means deployments begin aging out almost as soon as they are commissioned.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
New Survey Reveals Overwhelmingly Optimistic Results on the Use of AI in Construction
May 14, 2026 —
Construction ExecutiveOn December 5, 2025,
CMiC and
Dodge released a
survey asking over 6,000 companies across various sectors of the construction industry their stance on artificial intelligence—whether they use it or not; whether they like it or not; whether they have or are planning to implement it or not; and so on. Considering its reputation for skepticism and reluctance when it comes to adopting new forms of technology, the construction industry pleasantly surprised CMiC and Dodge with its answers to these questions, with 87% of contractors believing AI will have a meaningful impact on construction.
“The research indicates the construction industry is nearing a tipping point for AI adoption,” says Steve Jones, senior director of industry insights at Dodge Construction Network, who sat down with Construction Executive to delve further into the survey questions and answers and what the industry’s current position on them means for AI’s future role in construction.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
A Green Light for Housing? What Executive Order 14394 Means for Your Next Project
May 26, 2026 —
Bennett Houck, Miranda Martinez & Byron Sarhangian - Snell & WilmerOn March 13, 2026, President Trump signed Executive Order 14394, “Removing Regulatory Barriers to Affordable Home Construction” (the “Order”). The Order directs federal agencies to reduce regulatory burdens on residential development, streamline environmental permitting, and encourage state and local governments to adopt housing-friendly policies.
The Order includes several key provisions that developers and homebuilders should be aware of moving forward.
Key Provisions
The Order targets four main areas:
1. Federal Environmental Regulations
First, it directs the Secretary of the Army and Environmental Protection Agency (EPA) to revise permitting standards, including stormwater permits, wetlands permits under Section 404 of the Clean Water Act, and related construction-site requirements. The Order also targets energy-efficiency mandates for U.S. Department of Housing and Urban Development (HUD) and U.S. Department of Agriculture (USDA) financed housing. For developers and homebuilders, these revisions could reduce project delays and compliance costs associated with stormwater management, wetlands mitigation, and energy-efficiency upgrades, expenses that often add significant time and cost to residential development projects.
Reprinted courtesy of
Bennett Houck, Snell & Wilmer,
Miranda Martinez, Snell & Wilmer and
Byron Sarhangian, Snell & Wilmer
Mr. Houck may be contacted at bhouck@swlaw.com
Ms. Martinez may be contacted at mimartinez@swlaw.com
Mr. Sarhangian may be contacted at bsarhangian@swlaw.com
Read the full story...
We Won’t Permit That Excuse!
June 23, 2026 —
Curt Martin & Richard Eiszner - ConsensusDocsA Texas appellate court recently ruled that a building permit wasn’t a condition precedent for a construction project. That caught our attention. Can you build a commercial project without a permit?
But as we read the case, we see the court’s reasoning. And it reminds us of an important legal principle that should inform our contract drafting and negotiation.
The case was a civil suit brought by the project owner against its tenant improvement contractor for work on a medical spa. The owner claimed that the contractor didn’t perform the work properly and didn’t finish construction. The contractor argued that delays and problems were caused by the owner, alleging numerous failures, including the owner’s failure to secure a building permit.
Reprinted courtesy of
Curt Martin, Peckar & Abramson, P.C. and
Richard Eiszner, Peckar & Abramson, P.C.
Mr. Martin may be contacted at cmartin@pecklaw.com
Mr. Eiszner may be contacted at reiszner@pecklaw.com
Read the full story...
Delay Matters: Florida’s Fourth DCA Reverses Hurricane Irma Dismissal
June 08, 2026 —
Andrea DeField, Machaella Reisman & Cary D. Steklof - Hunton Insurance Recovery BlogThe mantra “delay, deny, defend” is frequently referenced in discussions of insurance claims handling, though insurers will invariably disavow these tactics. While it would be facially improper for an insurer to delay a coverage decision to gain a tactical advantage, empirical examples nonetheless exist. This very dynamic was addressed by Florida’s Fourth District Court of Appeals when it handed policyholders a win in
Hypoluxo Mariner’s Cay Condo. Assoc’n, Inc. v. Underwriters at Lloyd’s London, No. 4D2024‑2250 (Fla. 4th DCA Apr. 1, 2026), reversing a trial court order dismissing a condominium association’s Hurricane Irma coverage lawsuit against its property insurer.
Delay to Run the Statute of Limitations
Following Hurricane Irma, a condominium association suffered roof and exterior envelope damage, reported an insurance claim, and submitted a sworn proof of loss to its property insurer in compliance with Florida Statute § 627.70132 (2020). The statute establishes a timeframe within which a policyholder must submit a claim for hurricane damage.
Reprinted courtesy of
Andrea DeField, Hunton Andrews Kurth LLP,
Machaella Reisman, Hunton Andrews Kurth LLP and
Cary D. Steklof, Hunton Andrews Kurth LLP
Ms. DeField may be contacted at adefield@hunton.com
Ms. Reisman may be contacted at reismanm@hunton.com
Mr. Steklof may be contacted at csteklof@hunton.com
Read the full story...
"Resilient Rebuild Hub" Helps Wildfire-Impacted Homeowners Build Back Stronger
September 21, 2026 —
California Nevada Cement AssociationNEWPORT BEACH, Calif., Sept. 21, 2026 /PRNewswire/ -- When homeowners in a fire-ravaged Pacific Palisades neighborhood banded together last year to rebuild with fire-hardened materials rather than standard wood framing, they weren't just rebuilding houses: they were rewriting the playbook for how California communities can rebuild after wildfire. Today, the Building with Resilience effort is making that playbook available to every homeowner facing the same decision with the launch of its new Resilient Rebuild Hub for exploring fire resistant, non-combustible construction options.
The Resilient Rebuild Hub helps homeowners understand options for fire-resistant, concrete-based construction and connect with architects, engineers, and contractors who can build them. This includes six noncombustible building systems:
- Insulated Concrete Forms (ICF): stackable, high-density foam blocks filled with concrete which save 20-50% on monthly heating and cooling costs, reduce outside noise by up to 80%, offer exceptional earthquake performance and 4-hour fire resistance rating.
- Insulated Composite Concrete Forms (ICCF): similar formwork to ICF construction with composite materials that enhance strength, simplify installation, and improve long-term performance.
- Concrete Masonry: strong, durable wall systems used for decades across California and the U.S.
- Precast Insulated Sandwich Panels: a complete building enclosure system consisting of two layers of concrete separated by a continuous layer of rigid insulation.
- 3D Shotcrete: air-sprayed concrete for strong, fast, and versatile wall systems that enable a high degree of artistic freedom together with unparalleled fire resistance.
- 3D Concrete Printing: the cutting edge of residential construction, a large-scale robotic 3D printer "squeezes" a specialized concrete mixture layer by layer to allow for organic, curved designs that are often too expensive or impossible to build with traditional methods.
The Resilient Rebuild Hub is available now at buildingwithresilience.com/how-to-build. Each part is free to access and includes case studies, technical resources, and a directory of architects, engineers, and contractors experienced in each building method.
CNCA is a not-for-profit organization committed to developing sustainable and economical construction solutions for California and Nevada with an emphasis on the use of cement and concrete. For more information, visit www.cncement.org.
CalCIMA is a trade association for the construction and essential mineral industries in California, including aggregate, essential and rare earth minerals, ready mixed concrete, and asphalt producers. In all, there are about 70 producer member companies that include 500 production sites in every county of California. Our members also include more than 100 suppliers and service providers to the industry.
Founded in 1930, the National Ready Mixed Concrete Association (NRMCA) is the leading industry advocate with a mission to provide exceptional value for our members by responsibly representing and serving the entire ready mixed concrete industry through leadership, promotion, education and partnering to ensure ready mixed concrete is the building material of choice.
Sometimes a General Damages Assessment is Enough. . .
July 06, 2026 — Christopher G. Hill - Construction Law Musings
It has been a while since I last posted here at Construction Law Musings. Life, law practice, and “blogger’s block” have taken their toll on the posting schedule. Hopefully this will be one of several upcoming posts now that the litigation schedule has lightened a bit over the summer.
Today’s post is about damages. Specifically damage to a homeowner’s roof and her legal damages therefor. That last is of course a sentence that only a construction attorney (or other litigator) could possibly craft and have it make sense. Now, on with the case. . .In Hardesty Construction, Inc. v. Weedon, the facts are as follows:
Ms. Weedon had hail damage to the roof of her home. She hired Hardesty Construction to repair and replace the roof. After the first roof was installed and failed inspection, a second roof was installed. The issue was that the first roof had a warranty and the second roof, installed similarly to the first (and allegedly with the same construction issues according to Ms. Weedon’s expert), was not provided with the promised warranty. As one may expect, Weedon sued Hardesty and Hardesty Construction for fraudulent inducement and breach of contract. At trial, Weedon testified, without objection, that her home was worth $40,000 less because of Hardesty Construction’s work, which was based partially on quotes Weedon received to fix the roof. The Circuit Court granted Hardesty Construction’s motion to strike Weedon’s fraudulent inducement claim, but not her other claims. A jury awarded Weedon $30,253.30 on her breach of contract claim. Hardesty Construction appealed, arguing the Circuit Court erred in (a) allowing the jury to consider Weedon’s valuation testimony because it was not based on her personal knowledge and (b) denying its motion to strike based on insufficient evidence as to damages. Weedon assigned cross-error in the Circuit Court’s decision to grant the motion to strike her fraudulent inducement claim against Samual Hardesty. Read the full story...
Reprinted courtesy of The Law Office of Christopher G. Hill
Mr. Hill may be contacted at chrisghill@constructionlawva.com
New York Enacts First-in-the-Nation Statewide Data Center Moratorium
August 03, 2026 — Joshua L. Sturtevant - Sheppard
As of May 2026, nearly 12 gigawatts of data center load requests were in the New York Independent System Operator interconnection queue, with more than two-thirds of capacity requests entering the queue in 2025 alone. On July 14, 2026, in response to concerns over this rapid growth, Governor Kathy Hochul issued Executive Order No. 62 (the “Order”) imposing a temporary moratorium on data centers in New York State. Among the concerns cited in the Order are the cost burden on ratepayers associated with transmission upgrades required to accommodate large loads, potential environmental impacts, and large-scale water use.
The moratorium is intended to halt activities while the state government develops a comprehensive legal framework for data center development. While dozens of municipal and county-level moratoriums are in place throughout the U.S., and while the legislatures of several states, including Maine, have proposed moratoriums, the Order is the first statewide moratorium to be enacted nationally. Read the full story...
Reprinted courtesy of Joshua L. Sturtevant, Sheppard
Mr. Sturtevant may be contacted at jsturtevant@sheppard.com