Arbitration in Construction Disputes: Process and Best Practices
July 27, 2026 —
Construction ExecutiveArbitration in construction disputes is a private process where owners, contractors, subcontractors, designers or suppliers present claims to one or more neutral arbitrators instead of taking the dispute through court. The arbitrator reviews evidence, hears testimony and issues a decision that is usually binding.
Construction arbitration is common because project disputes are technical, document-heavy and time-sensitive. Claims may involve schedule delays, disputed change orders, defective work, differing site conditions, payment, termination, indemnity, surety issues or professional liability.
Arbitration can be faster and more specialized than litigation, but speed is not guaranteed. Poor contract language, broad discovery, weak records and unclear damages can make arbitration expensive.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Settlement Agreements and Contracts Require a Meeting of the Minds
July 20, 2026 —
David Adelstein - Florida Construction Legal UpdatesA settlement agreement does not need to be executed for it to be enforceable as long as there was a MEETING OF THE MINDS. The same rings true for any contract regardless of whether the contract is signed – THERE NEEDS TO BE A MEETING OF THE MINDS.
In a recent case dealing with the settlement agreement on a construction lien, the essential settlement terms (money and mutual release) were memorialized in an e-mail exchange between the parties (owner and subcontractor). The settlement required the owner to pay the principal amount plus some attorney’s fees and then a mutual general release would be prepared. In response to the confirmatory email, the owner sent a check, which the subcontractor deposited, but the owner refused to sign the release signed and sent by the subcontractor. The owner further claimed it doesn’t need to pay the attorney’s fees because the lien amount was paid in full. The subcontractor sued arguing the owner breached the terms of the settlement. The appellate court agreed.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Preventing Common and Costly Water Intrusion Events in Construction
July 13, 2026 —
Andrew Swift - Construction ExecutiveWater leaking into a building is a leading cause of
damage and loss in the construction industry. On one jobsite, heavy rains flooded a sub-basement, damaging a new electrical transformer—all because a roof drain was not property connected. On another jobsite, a drinking-fountain supply line broke in a multistory building that was undergoing renovation, causing water to run—undetected—for an entire weekend, resulting in water damage to all lower floors, where construction had been finished.
Those loss scenarios could have been prevented with a comprehensive and effective water damage prevention plan (WDPP). This includes routine site inspections to identify uncontrolled water damage exposures and basic maintenance to make sure drains are clean of debris and divert them to a catch basin or low point away from the building. An effective WDPP plan also incorporates technology such as backflow preventers on sewer connections and water sensing technology to monitor the most vulnerable exposures.
Reprinted courtesy of
Andrew Swift, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Pulling the Plug, Preserving the Product: Protecting Rights to a Modular Subcontractor’s Work Post-Termination
June 08, 2026 —
Paul Williamson - ConsensusDocsVolumetric Modular Construction (VMC) is a building method where a structure is divided into large components or modules, fabricated in an offsite factory and then transported to a construction site for assembly.[
1] Proponents of VMC hail it as a cost-efficient alternative to traditional building methods that leads to more consistent quality and shorter construction duration.[
2] Due to a growing labor shortage, high demand for compressed project schedules, and stagnant construction productivity rates, the construction industry is embracing VMC.[
3] A recent report on the market size of prefabricated construction estimates that from 2026 to 2031, VMC will grow at a compound annual growth rate of 7.16% and become a 413.11-billion-dollar industry.[
4]
As VMC becomes more prevalent, owners, general contractors, and subcontractors must consider how to effectively contract for modular construction. One important consideration, which this article focuses on, is navigating termination of a modular subcontractor.
Read the full story...Reprinted courtesy of
Paul Williamson, Peckar & Abramson, P.C.Mr. Williamson may be contacted at
pwilliamson@pecklaw.com
Substantial Evidence of Flood Loss is Not a Substitute for Required Proof of Loss
April 20, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe court found that the insurer properly denied the insured’s claim for loss due to flood because a proof of loss was never submitted. Bay Haven at Coco Bay Condominium Association, Inc. v. Hartford Ins. Co. of the Midwest, 2026 U.S. Dist. LEXIS 6847 (M.D. Fla. Jan. 14, 2026).
Bay Haven managed several condo buildings. When Hurricane Ian hit, it caused significant flood damage to these properties. Bay Haven held federal flood insurance policies through Hartford under “Write-Your-Own” policies. This meant Hartford was essentially a fiscal agent that managed policies and handled claims but paid them using federal funds.
Following the storm, FEMA extended the usual 60-day deadline for filing a proof of loss to one year, or until September 28, 2023. Bay Haven did not submit its proofs of loss until November 2023. FEMA granted an extension but only for the specific amounts in the November requests. Hartford did not waive the 60-day proof of loss requirement for any other proof of loss. Hartford paid the amounts reflected in the November submissions.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Applying Jury Verdict Method in Quantifying Damages Due to Defective Specifications
March 31, 2026 —
David Adelstein - Florida Construction Legal UpdatesAn older case deals with three important considerations: (1) defective specifications; (2) whether the defective specifications were misleading or misrepresentative; and (3) applying the jury verdict method in quantifying damages.
In Metric Construction Co., Inc. v. U.S., 80 Fed. Cl. 178 (Fed. Cl. 2008), a contractor was contracted by the federal government to construct a warehouse. There were defects in the structural steel design specifications underlying the standing seam metal roof installed by the contractor and, as a result, the roof system leaked causing damage. The contractor incurred significant costs in repairing the damage, and pursued recovery of these costs against the government. The contractor claimed the structural steel design serving as the framework for the metal roof was defective and misleading and caused the leaks.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
David Samani Joins BHBA Podcast on Mediation Best Practices
May 05, 2026 —
Lewis BrisboisLos Angeles Partner David Samani recently joined a Beverly Hills Bar Association (BHBA) podcast titled, “Mediation 360: Preparation from the Defense, Plaintiff, and Mediator Perspectives,” during which he shared his insights on various aspects of the mediation process. Mr. Samani, along with a plaintiff’s attorney and a mediator, presented their thoughts on topics including how to determine whether a case is appropriate for mediation, preparing to mediate a case, communicating with clients, and handling the mediation itself.
Mr. Samani explained that early communication with clients is critical so that attorneys may learn what a client’s objectives are and develop an assessment of the case. He described that “from an early stage,” attorneys should determine the cost of litigation and ensure that the client understands “what an aggressive defense might entail.” As the matter progresses, attorneys and clients should “continue the dialogue” regarding costs as well as the strengths and weaknesses of the case, “making sure the client is apprised of the various alternatives that exist.” In addition, Mr. Samani discussed factors to consider when choosing a mediator, noting, “All mediators have their own styles and backgrounds.” He explained that some cases may call for a mediator with specialized knowledge in a particular area such as bankruptcy or securities, while other mediations may benefit from a mediator who understands the realities of private practice.
Read the full story...Reprinted courtesy of
Lewis Brisbois
New York Orders Moratorium on Large Data Center Permits
July 27, 2026 —
Levi W. Barrett - Peckar & Abramson, P.C.Levi W. Barrett, Co-Managing Partner of Peckar & Abramson’s New Jersey office, Co-Chair of the firm’s
Construction Contracts & Risk Management team, and Executive Committee Member, was recently quoted in “New York Orders Moratorium on Large Data Center Permits,” an article written by
Engineering News-Record (ENR). The article examines New York Governor Kathy Hochul’s executive order temporarily halting state environmental permit reviews for certain large-scale data center projects while regulators develop a comprehensive framework to address the sector’s energy demands, water consumption, environmental impacts, and effects on local communities. It also explores the broader implications of the moratorium for developers, contractors, investors, and other stakeholders, as well as the ongoing debate between economic development, AI-driven infrastructure growth, and environmental and utility ratepayer concerns.
Read the full story...Reprinted courtesy of
Levi W. Barrett, Peckar & Abramson, P.C.Mr. Barrett may be contacted at
lbarrett@pecklaw.com