Four HHMR Attorneys Recognized in the 2027 Editions of Best Lawyers®
September 21, 2026 —
Higgins, Hopkins, McLain & Roswell, LLC - Colorado Construction Litigation BlogHiggins, Hopkins, McLain & Roswell, LLC is proud to announce that Best Lawyers® has recognized four HHMR attorneys in the 2027 editions of The Best Lawyers in America® and Best Lawyers: Ones to Watch® in America for their work in construction law and construction litigation.
David M. McLain, Lisa Bondy Dunn, and Steven L. Heisdorffer earned recognition in the 2027 edition of The Best Lawyers in America®. Ricky L. Nolen, Jr. earned recognition in the 2027 edition of Best Lawyers: Ones to Watch® in America.
For a firm that has deliberately focused its practice on construction law and construction litigation for nearly 25 years, we take particular pride in seeing that focus reflected in the recognition of lawyers across different generations of HHMR.
Read the full story...Reprinted courtesy of
Higgins, Hopkins, McLain & Roswell, LLC
USDOT’s DBE Interim Final Rule: How It Affects Current and Out-to-Bid DOT and Airport Projects
June 15, 2026 —
Zachary F. Jacobson - The Construction SeytIn our April 16, 2026 post, we discussed the U.S. Department of Transportation’s Interim Final Rule (IFR) concerning Disadvantaged Business Enterprise (DBE) and Airport Concession Disadvantaged Business Enterprise (ACDBE) certification, specifically as it concerns transportation and airport projects in California.
This post addresses a broader question: What does the IFR mean for current and out-to-bid DOT projects operating under pre-existing DBE goals? The answer is that the IFR did more than change who qualifies as a DBE. It also changed how federally funded transportation and airport projects must be handled during the re-evaluation period. This affects active contracts, pending procurements, airport projects, design-build teams, and anyone relying on old assumptions about DBE goals and counting of DBE and ACDBE credit.
Read the full story...Reprinted courtesy of
Zachary F. Jacobson, Seyfarth Shaw LLPMr. Jacobson may be contacted at
zjacobson@seyfarth.com
Research Illuminates Pollution Problem in Tijuana River Valley
June 29, 2026 —
Jeff Yoders - Engineering News-RecordThe Tijuana River watershed between southern California and northern Mexico has been the epicenter of an environmental and public health crisis for more than two decades. Since October 2023 alone, more than 31 billion gallons of raw sewage and polluted water have flowed into the U.S. and, eventually, the Pacific Ocean.
Read the full story...Reprinted courtesy of
Jeff Yoders, Engineering News-RecordMr. Yoders may be contacted at
yodersj@enr.com
That’s a Wrap! Pennsylvania Court Holds Arbitration Clause in Online Agreement Unenforceable
May 14, 2026 —
Gus Sara - The Subrogation StrategistIn Duffy v. Tatum, 2026 Pa. Super. LEXIS 112, 2026 PA Super 41, the Superior Court of Pennsylvania (Superior Court) considered whether an arbitration provision contained in the online Terms of Service on the defendant’s website were enforceable. The plaintiff, Daniel Duffy (Duffy), visited the website of defendant, Dolly, Inc. (Dolly), to purchase moving services. Duffy selected the number of movers, items to be moved and the type of vehicle needed. To complete the booking, the website required Duffy to checkmark a box labeled “By checking this box I accept the Dolly Terms of Service.” Duffy did not have to open the link or scroll to the bottom of the agreement before being able to click on the checkmark box. The Terms of Service included an arbitration provision requiring that any dispute related to the moving services to be resolved by arbitration in accordance with the American Arbitration Association. The Terms of Service did not include any statement that the user was waiving the right to a jury trial. The Superior Court found the internet Terms of Service unenforceable.
During the moving process, an accident occurred and injured Duffy. In May 2024, Duffy and his wife sued Dolly and other related entities alleging negligence and loss of consortium. Dolly filed preliminary objections alleging that the parties agreed to alternative dispute resolution. The lower court overruled the preliminary objections, finding that Dolly’s website did not provide reasonably obvious notice of its Terms of Service to Duffy and, as such, Duffy never agreed to waive his constructional right to a jury trial. Dolly filed an appeal to the Superior Court.
Read the full story...Reprinted courtesy of
Gus Sara, White and Williams LLPMr. Sara may be contacted at
sarag@whiteandwilliams.com
SDV Celebrates 30th Anniversary Press Release
April 08, 2026 —
Saxe Doernberger & Vita, P.C.Trumbull, Connecticut – Saxe Doernberger & Vita, P.C. (SDV) is proud to announce the celebration of its 30th anniversary.
Founded in 1996 by three attorneys in a small New Haven, Connecticut office, SDV was built on a clear and focused mission: representing policyholders in insurance coverage matters. Three decades later, that commitment remains at the core of the firm’s identity and has been instrumental in its continued success and reputation nationwide.
Today, SDV is a nationally recognized boutique firm with 50 attorneys serving policyholders across the United States. Building on its longstanding reputation for excellence and client advocacy, the firm is pleased to announce the opening of its newest office in Massachusetts—an exciting milestone that reflects SDV’s continued growth. The new office is led by Managing Partner Anna Perry.
Read the full story...Reprinted courtesy of
Saxe Doernberger & Vita, P.C.
Colorado Supreme Court Reverses Course on Public Project Liens: Key Takeaways From Wadsworth v. Regional Rail Partners
July 27, 2026 —
Amanda E. McKinlay - Snell & WilmerOn April 6, 2026, the Colorado Supreme Court issued a unanimous opinion in Ralph L. Wadsworth Construction Company, LLC v. Regional Rail Partners, 2026 CO 19, reversing the Colorado Court of Appeals and providing much-needed clarity regarding verified statements of claim (VSOCs) under the Colorado Public Works Act, C.R.S. §§ 38-26-101 et seq. The decision resolves two issues that have generated significant concern among construction industry professionals since the Court of Appeals issued its opinion on August 1, 2024.
Under C.R.S. § 38-26-107(1), a subcontractor on a public works project may file a VSOC with the contracting public entity for amounts due and unpaid for “…furnished labor, materials, sustenance, or other supplies used or consumed by a contractor or his or her subcontractor in or about the performance of the work contracted to be done or that supplies laborers, rental machinery, tools, or equipment to the extent used in the prosecution of the work….” If a claimant files a VSOC for “an amount greater than the amount due” without a reasonable possibility that the amount is due and with knowledge that the claim is excessive, the claimant “shall forfeit all rights to the amount claimed” and becomes liable for the opposing party’s costs and attorneys’ fees. C.R.S. § 38-26-110.
Read the full story...Reprinted courtesy of
Amanda E. McKinlay, Snell & WilmerMs. McKinlay may be contacted at
amckinlay@swlaw.com
New Law Prompts ABC Minnesota/North Dakota to Design New Telecommunications Safety Training Program
June 29, 2026 —
Grace Calengor - Construction ExecutiveOn the first day of the year, a
Minnesota law requiring installers of underground telecommunication infrastructure broadband, fiber or phone lines (when projects utilize directional drilling, and/or work is being conducted within 10 feet of existing utilities) to undergo a 40-hour certification went into effect.
Originally passed in mid-2024 and proposed to go into effect in July 2025, the law’s requirements were postponed until January 2026, giving
ABC Minnesota/North Dakota—in partnership with
NCCER and the
Minnesota Cable Communications Association—time to roll out their
Safety Qualified Underground Telecommunications Installer training program, which would ensure the workforce of their contractor members were certified.
Reprinted courtesy of
Grace Calengor, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Powering Data Centers in a Moving Regulatory Landscape: Positioning Deals Before FERC’s Next Move
April 27, 2026 —
Stephen J. Humes, Alicia M. McKnight & Andrew H. Jacobs - Gravel2Gavel Construction & Real Estate Law BlogThe explosive growth of data‑center load—driven by artificial intelligence, cloud computing and the expansion of digital infrastructure across industries—has forced U.S. energy regulators into unfamiliar territory. Nowhere is this more evident than at the Federal Energy Regulatory Commission (FERC), which is actively considering how large, concentrated loads can be powered without compromising grid reliability or shifting costs to other customers.
FERC has not yet issued a standalone rulemaking on data centers. But make no mistake, the regulatory framework is quietly and deliberately being built. For developers, hyperscalers, utilities and investors, the period before FERC finalizes its next round of decisions represents the critical window to crystallize advocacy and structure transactions in ways that anticipate regulatory change.
Reprinted courtesy of
Stephen J. Humes, Pillsbury,
Alicia M. McKnight, Pillsbury and
Andrew H. Jacobs, Pillsbury
Mr. Humes may be contacted at stephen.humes@pillsburylaw.com
Ms. McKnight may be contacted at alicia.mcknight@pillsburylaw.com
Mr. Jacobs may be contacted at andrew.jacobs@pillsburylaw.com
Read the full story...